December Update and Lookahead

NBHD 1B

  • Sunnydale – Curb backfilling next week. Final grading and sod over the next few weeks.
  • Northridge Roadway – 1st lift of HMA down on all blocks. Concrete crew working through curb and gutter to be followed by other concrete flatwork.
  • Donna – SS manhole set at 0+34 with mainline work started. Road will be open to traffic through the Holidays. Sewer work will resume in January.
  • Pershing – Water main and service work progressing. Chlorination and testing tentatively beginning of January.
  • Sheraton – 1st lift of HMA placed today. Concrete work to follow Northridge Street.
  • Huntington – 1st lift oof HMA placed today. Concrete work to follow Sheraton.
  • Apollo – Sanitary sewer complete. Water main construction progressed. Water service construction next week with main line work resuming in January.
  • Titan Trail – Sanitary sewer complete. Water main construction started
  • Camelot – Repair of water main construction being scheduled.
  • Yellowstone – Final Streets walk tentatively mid-January.
  • Juno – Manhole lining complete. Final walk tentatively mid-January.
  • Cactus Cir – Manhole lining complete. Final walk tentatively mid-January.
  • Huisache – Manhole lining complete. Final walk tentatively mid-January.
  • Redstone – SS delayed for Atmos gas line conflicts. Coordination on-going to work through conflicts.