Look Ahead Near UNT

We know the impacts of construction are challenging. Below is a long-lead lookahead for Future Construction Impacts Near UNT. The City of Denton, DCTA, and UNT are coordinating work in/around UNT to minimize impacts to work near special events such as commencements and semester move-ins. We are also making our best efforts to maximize work during winter/summer breaks. We appreciate your support for this huge project!!

Spring 2025

  1. Avenue C Roadway
    1. Eagle to Highland: To end by 12/12/24 latest
  2. Welch Roadway
    1. Prairie to Chestnut: 12/18/24 – 3/21/25
    2. Chestnut to Mulberry: 3/31/25 – 06/16/25
  3. Prairie Street Utilities
    1. Welch to Bernard: 11/18/24 – 02/24/25
  4. Prairie Street Roadway Work
    1. Bernard to Welch: 02/25/25 – 06/11/25
  5. Mulberry Utilities
    1. Welch to Bernard: 02/25/25 – 05/13/25
  6. Mulberry Roadway
    1. Welch to Bernard: 05/14/25 – 08/06/25
  7. Bernard South Roadway (Fannin to Lindsey)
    1. Lindsey to Fannin: 12/31/24 – 06/23/25
  8. Avenue A Utilities
    1. Ave A/Maple Intersection: 01/24/25 – 02/28/25

Summer 2025

  1. Chestnut Roadway
    1. Ave C to Ave D: 5/16/25 – 8/25/25
  2. Ave. D Roadway
    1. Chestnut to Mulberry (05/13/25 – 08/12/25
  3. Welch Roadway Work
    1. Chestnut to Mulberry: 3/31/25 – 06/16/25
    2. Mulberry to Hickory: 07/25/24 – 09/22/25
  4. Prairie Street Roadway Work
    1. 02/25/25 – 06/11/25
  5. Union Circle Utilities
    1. South (Prairie): 5/14/25-7/11/25
  6. Union Circle Roadway
    1. All: 7/11/25 – 10/02/25
  7. Mulberry Roadway
    1. Welch to Bernard: 4/23/25-7/22/25
  8. Welch Roadway Work
    1. Mulberry to Hickory: 07/25/25 – 09/22/25

Fall 2025

  1. Chestnut Roadway
    1. Ave C to Ave D: 5/16/25 – 8/25/25
  2. Welch Roadway Work
    1. Eagle to Highland: 08/22/25 – 11/17/25
    2. Highland to Prairie: 10/25 – 01/26/26
  3. Union Circle Utilities
    1. South (Prairie): 5/14/25-7/11/25
    2. West: 5/14/25-7/11/25
    3. North (Chestnut): 5/14/25-7/11/25
  4. Union Circle Roadway
    1. South (Prairie): 7/11/25 – 10/02/25
    2. West: 7/11/25 – 10/02/25
    3. North (Chestnut): 7/11/25 – 10/02/25
  5. Welch Roadway Work
    1. Mulberry to Hickory: 07/25/25 – 09/22/25

Spring 2026

  1. Bernard North Utilities
    1. Hickory to Chestnut: 01/12/26 – 02/27/26
  2. Bernard North Roadway
    1. Hickory to Chestnut: 02/27/26 – 06/09/26
  3. Avenue A Utilities
    1. Eagle to Maple: 2/25/26-4/2/26
    2. Ave A/Maple Intersection: 4/3/26-7/13/26

Summer 2026

  1. Bernard North Roadway
    1. Hickory to Chestnut: 4/3/26-7/8/26
Share Look Ahead Near UNT on Facebook Share Look Ahead Near UNT on Twitter Share Look Ahead Near UNT on Linkedin Email Look Ahead Near UNT link