Look Ahead Near UNT
We know the impacts of construction are challenging. Below is a long-lead lookahead for Future Construction Impacts Near UNT. The City of Denton, DCTA, and UNT are coordinating work in/around UNT to minimize impacts to work near special events such as commencements and semester move-ins. We are also making our best efforts to maximize work during winter/summer breaks. We appreciate your support for this huge project!!
Spring 2025
-
Avenue C Roadway
- Eagle to Highland: To end by 12/12/24 latest
-
Welch Roadway
- Prairie to Chestnut: 12/18/24 – 3/21/25
- Chestnut to Mulberry: 3/31/25 – 06/16/25
-
Prairie Street Utilities
- Welch to Bernard: 11/18/24 – 02/24/25
-
Prairie Street Roadway Work
- Bernard to Welch: 02/25/25 – 06/11/25
-
Mulberry Utilities
- Welch to Bernard: 02/25/25 – 05/13/25
-
Mulberry Roadway
- Welch to Bernard: 05/14/25 – 08/06/25
-
Bernard South Roadway (Fannin to Lindsey)
- Lindsey to Fannin: 12/31/24 – 06/23/25
-
Avenue A Utilities
- Ave A/Maple Intersection: 01/24/25 – 02/28/25
Summer 2025
-
Chestnut Roadway
- Ave C to Ave D: 5/16/25 – 8/25/25
-
Ave. D Roadway
- Chestnut to Mulberry (05/13/25 – 08/12/25
-
Welch Roadway Work
- Chestnut to Mulberry: 3/31/25 – 06/16/25
- Mulberry to Hickory: 07/25/24 – 09/22/25
-
Prairie Street Roadway Work
- 02/25/25 – 06/11/25
-
Union Circle Utilities
- South (Prairie): 5/14/25-7/11/25
-
Union Circle Roadway
- All: 7/11/25 – 10/02/25
-
Mulberry Roadway
- Welch to Bernard: 4/23/25-7/22/25
-
Welch Roadway Work
- Mulberry to Hickory: 07/25/25 – 09/22/25
Fall 2025
-
Chestnut Roadway
- Ave C to Ave D: 5/16/25 – 8/25/25
-
Welch Roadway Work
- Eagle to Highland: 08/22/25 – 11/17/25
- Highland to Prairie: 10/25 – 01/26/26
-
Union Circle Utilities
- South (Prairie): 5/14/25-7/11/25
- West: 5/14/25-7/11/25
- North (Chestnut): 5/14/25-7/11/25
-
Union Circle Roadway
- South (Prairie): 7/11/25 – 10/02/25
- West: 7/11/25 – 10/02/25
- North (Chestnut): 7/11/25 – 10/02/25
-
Welch Roadway Work
- Mulberry to Hickory: 07/25/25 – 09/22/25
Spring 2026
-
Bernard North Utilities
- Hickory to Chestnut: 01/12/26 – 02/27/26
-
Bernard North Roadway
- Hickory to Chestnut: 02/27/26 – 06/09/26
-
Avenue A Utilities
- Eagle to Maple: 2/25/26-4/2/26
- Ave A/Maple Intersection: 4/3/26-7/13/26
Summer 2026
-
Bernard North Roadway
- Hickory to Chestnut: 4/3/26-7/8/26
Share Look Ahead Near UNT on Facebook
Share Look Ahead Near UNT on Twitter
Share Look Ahead Near UNT on Linkedin
Email Look Ahead Near UNT link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends