2019 Bond Neighborhood 2 & 6

Share 2019 Bond Neighborhood 2 & 6 on Facebook Share 2019 Bond Neighborhood 2 & 6 on Twitter Share 2019 Bond Neighborhood 2 & 6 on Linkedin Email 2019 Bond Neighborhood 2 & 6 link

The 2019 Bond Neighborhoods 2 & 6 project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 2 & 6 project as well as the breakdown of the phases (Packages 1, 2 & 3). Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.

Project Timeline Q4 2022 - Q4 2026*

*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle, including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.

The 2019 Bond Neighborhoods 2 & 6 project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 2 & 6 project as well as the breakdown of the phases (Packages 1, 2 & 3). Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.

Project Timeline Q4 2022 - Q4 2026*

*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle, including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.

  • October Construction Update - 3

    Share October Construction Update - 3 on Facebook Share October Construction Update - 3 on Twitter Share October Construction Update - 3 on Linkedin Email October Construction Update - 3 link

    Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

    Streets with active construction:

    Utilities:

    • Normal (W. Oak / Scripture) – Chlorination and pressure testing is ongoing.
    • Ponder (W. Oak / Panhandle) – Chlorination testing passed and tie-ins rescheduled.
    • Alice (Panhandle / Crescent) – Continue installation of sewer lines.
    • Parkway (Denton / Carroll) – Continue sewer line with boring scheduled.

    Electrical:

    • Aileen (Panhandle / Cordell) – Light conduit and boxes continued.

    Earthwork/Flatwork:

    • Cordell (Crescent / Fulton) – Final lift of asphalt scheduled followed by striping and signage.
    • Denton St. (Hickory / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
    • Denton at Oak – ATMOS delay
    • Egan (West) – Curb and gutter to begin.
    • Mounts (Haynes / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
    • Ponder (Scripture / Grace Temple) – Lime remix and final grading followed by 1st lift of asphalt, curb and gutter.
    • Scripture (Jagoe / Ponder) – ATMOS re-design.
    • Sunset (University / Alice) – Parking lot work to begin
    • Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work followed by backfill and sod.
    • Welch (Mulberry / Hickory) – Continue curb, gutter, driveways, and miscellaneous concrete work.
  • October 2025 Construction Update - 2

    Share October 2025 Construction Update - 2 on Facebook Share October 2025 Construction Update - 2 on Twitter Share October 2025 Construction Update - 2 on Linkedin Email October 2025 Construction Update - 2 link

    Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

    Streets with active construction:

    Utilities:

    • Normal (W. Oak / Scripture) – Services and hydrant to be installed followed by chlorination and pressure testing.
    • Ponder (W. Oak / Panhandle) – Chlorination testing followed by tie-ins.
    • Alice (Panhandle / Crescent) – Continue installation of sewer lines.
    • Parkway (Denton / Carroll) – Boring operations to begin.

    Electrical:

    • Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
    • Carlton (Aileen / Gober) – Light conduit and boxes to begin.

    Earthwork/Flatwork:

    • Amarillo (Haynes / Congress E) – Continue grading and excavating with mixing operations to follow.
    • Avenue G (Prairie / Louise) – Pending asphalt infill.
    • Carlton (Aileen / Gober) – Pending striping and signage.
    • Cordell (Crescent / Fulton) – Continuing curb, gutter, and driveways followed by backfill and sod.
    • Denton St. (Hickory / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
    • Emery & Fulton - Lime operations followed by 1st lift of asphalt.
    • Mounts (Haynes / Congress E) – Curb and gutter to begin.
    • Ponder (Scripture / Grace Temple) – Water service and ATMOS delay.
    • Scripture (Jagoe / Ponder) – ATMOS re-design.
    • Sunset (University / Carroll) – Open to traffic.
    • Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work to resume.
    • Welch (Mulberry / Hickory) – Continue mixing and grading operations followed by 1st lift of asphalt.
  • October 2025 Construction Update

    Share October 2025 Construction Update on Facebook Share October 2025 Construction Update on Twitter Share October 2025 Construction Update on Linkedin Email October 2025 Construction Update link

    Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

    Streets with active construction:

    Utilities:

    • Normal (W. Oak / Scripture) – Continue water main and lateral.
    • Ponder (W. Oak / Panhandle) – Chlorination testing.
    • Alice (Panhandle / Crescent) – Backfill bore operation followed by installation of sewer line.

    Electrical:

    • Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
    • Carlton (Aileen / Gober) – Light conduit and boxes to begin.

    Earthwork/Flatwork:

    • Amarillo (Haynes / Congress E) – Demo saw cutting followed by asphalt and concrete removals.
    • Avenue G (Prairie / Louise) – Pending asphalt infill.
    • Carlton (Aileen / Gober) – Backfill, sod, striping, and signage.
    • Congress E (Denton / Carroll) – Striping and signage.
    • Cordell (Crescent / Fulton) – Continuing curb, gutter, and driveways.
    • Cordell (Fulton / Alice) – Fine grading follow by 1st lift of asphalt and flatwork activities.
    • Denton St. (Hickory / Congress E) – Curb, gutter, driveways, and miscellaneous concrete work.
    • Egan (West) – First lift of asphalt followed by curb, gutter, and driveways.
    • Mounts (Haynes / Congress E) – Curb, gutter, driveways, and miscellaneous concrete work.
    • Ponder (Scripture / Grace Temple) – Continuing concrete removals followed by rough grading and lime mixing.
    • Scripture (Jagoe / Ponder) – ATMOS re-design.
    • Sunset North (University / Carroll) – Concrete driveways and miscellaneous concrete work.
    • Union Circle - open to traffic.
    • Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work.
    • Welch (Chestnut Intersections) – Striping
    • Welch (Mulberry / Hickory) – Asphalt and concrete removals to being followed by rough grading.
  • September 2025 Construction Update - 2

    Share September 2025 Construction Update - 2 on Facebook Share September 2025 Construction Update - 2 on Twitter Share September 2025 Construction Update - 2 on Linkedin Email September 2025 Construction Update - 2 link

    Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

    Streets with active construction:

    Utilities:

    • Amarillo (Haynes / Congress E) – Pressure test complete with chlorination and tie-in schedule.
    • Egan (Carroll / Bolivar) – Pressure test complete with chlorination and tie-in schedule.
    • Normal (W. Oak / Scripture) – Started water main and lateral.
    • Ponder (W. Oak / Panhandle) – Continue laterals.
    • Alice (Panhandle / Crescent) – Boring operations to being with sewer installation to follow.

    Electrical:

    • Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
    • Carlton (Aileen / Gober) – Light conduit and boxes to begin.
    • Welch (Prairie) – Installation of signal conduit to begin.
    • Welch (Chestnut) – Installation of signal conduit to begin.
    • Union Circle – Reprogramming signals.

    Earthwork/Flatwork:

    • Aileen (Panhandle / Cordell) – Complete.
    • Avenue G (Prairie / Louise) – Pending asphalt infill.
    • Carlton (Aileen / Gober) – Continuing placement of curb, gutter, and driveways.
    • Congress E (Ponder / Denton) – Backfill and sod.
    • Congress E (Denton / Carroll) – Started curb, gutter, and driveways.
    • Cordell (Crescent / Fulton) – Curb, gutter, and driveways have started.
    • Cordell (Fulton / Alice) - Demo and removals have started with grading and excavation to follow.
    • Crescent (Aileen / Malone) – Backfilling and sod.
    • Denton St. (Hickory / Congress E) – First lift of asphalt scheduled.
    • Egan (West) - Demo and removals started with grading and excavation to follow.
    • Mounts (Haynes / Congress E) – First lift of asphalt started.
    • Mulberry (Welch / Bernard N) – Pending asphalt infill.
    • Ponder (Panhandle / W. Oak) – ATMOS work.
    • Scripture (Jagoe / Ponder) – ATMOS re-design.
    • Sunset North (University / Carroll) – First lift of asphalt complete and curb and gutter has started.
    • Union Circle North and West - Striping started with sod to follow.
    • Welch (Sycamore / Mulberry) – Infill around inlet.
    • Welch (Highland / Prairie) – Demo and removals started with grading and excavation to follow.
  • September 2025 Construction Update

    Share September 2025 Construction Update on Facebook Share September 2025 Construction Update on Twitter Share September 2025 Construction Update on Linkedin Email September 2025 Construction Update link

    Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

    Streets with active construction:

    Utilities:

    • Amarillo (Haynes / Congress E) – Continue waterlines and laterals.
    • Egan (Carroll / Bolivar) – Pressure test and chlorination with tie-ins to follow.
    • Normal (W. Oak / Scripture) – Installing 18" RCP and Junction Boxes followed by water line.
    • Ponder (W. Oak / Panhandle) – Continue waterlines and laterals.
    • Alice (Panhandle / Crescent) - Boring operations to being.

    Electrical:

    • Aileen (Panhandle / Cordell) - Light conduit and boxes to begin.
    • Union Circle North - Installing conduit boxes.

    Earthwork/Flatwork:

    • Aileen (Panhandle / Cordell) – Pending striping and signage.
    • Avenue G (Prairie / Louise) – Completed asphalt with TCP pick-up on 9/5.
    • Carlton (Aileen / Gober) – Asphalt completed and continuing placement of curb and gutter.
    • Congress E (Ponder / Denton) – Continuing curb, gutter, and driveways.
    • Congress E (Denton / Carroll) – 1st lift of asphalt scheduled with curb and gutter to follow.
    • Congress W (Malone / Bryan) – Asphalt completed with striping, signage, and TCP pick-up to follow.
    • Cordell (Fulton / Crescent) – 1st lift of asphalt completed.
    • Crescent (Carroll / Bolivar) – Continuing concrete driveway and miscellaneous concrete work.
    • Denton St. (Hickory / Congress E) – Rough grading completed with cem-line scheduled.
    • Mounts (Haynes / Congress E) – Demo completed and mixing schedule with mellow and remixing to follow.
    • Mulberry (Welch / Bernard N) – Backfill completed and pending sod.
    • Scripture (Jagoe / Ponder) – ATMOS re-design.
    • Sunset South (University / Carroll) – Traffic switch completed with removals and earthwork started.
    • Union Circle North - Continuing concrete work with backfiling to follow.
    • Welch (Sycamore / Mulberry) – Throats and tops to be completed with backfill to follow.
  • August 2025 Construction Update - 2

    Share August 2025 Construction Update - 2 on Facebook Share August 2025 Construction Update - 2 on Twitter Share August 2025 Construction Update - 2 on Linkedin Email August 2025 Construction Update - 2 link

    Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

    Streets with active construction:

    Utilities:

    • Amarillo (Haynes / Congress E) – Continue waterlines and laterals.
    • Egan (Carroll / Bolivar) – Boring has started with waterline and laterals to follow.
    • Normal (W. Oak / Scripture) – Started storm sewer.
    • Ponder (W. Oak / Panhandle) – Continue waterlines and laterals.

    Earthwork/Flatwork:

    • Aileen (Panhandle / Cordell) – Final asphalt lift completed. Pending striping, signage, sod, and electrical.
    • Avenue G (Prairie / Louise) – C&G, driveway, and valley gutter poured.
    • Carlton (Aileen / Gober) – Finish grade completed and pending placement of asphalt.
    • Congress E (Ponder / Denton) – 1st lift of asphalt completed.
    • Congress E (Denton / Carroll) – Mixing lime with remix to follow.
    • Congress W (Malone / Bryan) – Curb and gutter concrete placement completed and continuing to backfill for sod.
    • Cordell (Fulton / Crescent) – Finish grade completed with asphalt to follow.
    • Crescent (Carroll / Bolivar) – C&G and driveways formed and poured.
    • Denton St. (Hickory / Congress E) – Asphalt millings started with earthwork to follow.
    • Mounts (Haynes / Congress E) – Potholing and demo has started.
    • Mulberry (Welch / Bernard N) – C&G and driveways formed and pending concrete placement.
    • Scripture (Jagoe / Ponder) – ATMOS re-design.
    • Sunset South (University / Carroll) – Completing valley gutter with asphalt and traffic switch to follow.
    • Union Circle North - Electrical boxes installed and C&G to continue.
    • Welch (Sycamore / Mulberry) – Standard Inlets to begin.
  • August 2025 Construction Update

    Share August 2025 Construction Update on Facebook Share August 2025 Construction Update on Twitter Share August 2025 Construction Update on Linkedin Email August 2025 Construction Update link

    Construction for Package 1 (GMP1) has completed.

    Packages 2 and 3 are in construction with anticipated completion Q4 2026

    Streets with active construction:

    Aileen - (Panhandle to Cordell) **Had significant delays due to weather and Atmos conflicts but nearing completion.

    Ave. D - (Chestnut to Mulberry)

    Chestnut - (Ave. D to Ave. C)

    Congress - (Ponder St. to Carroll)

    Congress West - (Malone to Bryan)

    Crescent East - (Carroll to Bolivar) **Asphalt completion week of Aug.11

    Crescent West - (Aileen to Malone)

    Denton St. - (Hickory to Congress)

    Egan St. - (Carroll to Bolivar)

    Mulberry St. - (Welch to Bernard)

    Ponder Ave. - (Oak to Panhandle)

    Sunset St. 1 - (University to Carroll)

    Sunset St. 2 - (Carroll to Bolivar)

    Union Circle - (Prairie to Chestnut)

    Welch St. - (Eagle to Hickory) ****Constructed in segments. Completed segments are Highland to Eagle and Prairie to Sycamore

    Scripture St. - (Jagoe to Ponder) ***Delayed due to Atmos conflicts. Atmos conflicts are scheduled to be completed 9/1/25 at which point roadway construction will resume


  • 12/12/2024 NEW TRAFFIC PATTERN - AVENUE C IS OPENING UP TODAY!

    Share 12/12/2024 NEW TRAFFIC PATTERN - AVENUE C IS OPENING UP TODAY! on Facebook Share 12/12/2024 NEW TRAFFIC PATTERN - AVENUE C IS OPENING UP TODAY! on Twitter Share 12/12/2024 NEW TRAFFIC PATTERN - AVENUE C IS OPENING UP TODAY! on Linkedin Email 12/12/2024 NEW TRAFFIC PATTERN - AVENUE C IS OPENING UP TODAY! link

    CONGRATULATIONS GRADUATES!

    The City and Sundt Construction and all those working on the roads and sidewalks and utilities want to CONGRATULATE all those who are graduation this month! SO MUCH HARD WORK to get here! And we want to tell you we worked equally hard on the road/sidewalks/utility work to make access to your graduation as seamless as possible. Denton is PROUD of your Accomplishment!


    ONGOING WORK AND SCHEDULES AROUND UNT


  • 2024 11-18 UNT Area Update

    Share 2024 11-18 UNT Area Update on Facebook Share 2024 11-18 UNT Area Update on Twitter Share 2024 11-18 UNT Area Update on Linkedin Email 2024 11-18 UNT Area Update link

    Construction is ALWAYS Subject to Change (due to weather, and other hurdles). With that said - below is the TARGET construction work planned around UNT.

    THIS WEEK, weather permitting, you will start seeing fencing and mobilization efforts on WELCH between W. HICKORY and W. MULBERRY.

  • Look Ahead Near UNT

    Share Look Ahead Near UNT on Facebook Share Look Ahead Near UNT on Twitter Share Look Ahead Near UNT on Linkedin Email Look Ahead Near UNT link

    We know the impacts of construction are challenging. Below is a long-lead lookahead for Future Construction Impacts Near UNT. The City of Denton, DCTA, and UNT are coordinating work in/around UNT to minimize impacts to work near special events such as commencements and semester move-ins. We are also making our best efforts to maximize work during winter/summer breaks. We appreciate your support for this huge project!!

    Spring 2025

    1. Avenue C Roadway
      1. Eagle to Highland: To end by 12/12/24 latest
    2. Welch Roadway
      1. Prairie to Chestnut: 12/18/24 – 3/21/25
      2. Chestnut to Mulberry: 3/31/25 – 06/16/25
    3. Prairie Street Utilities
      1. Welch to Bernard: 11/18/24 – 02/24/25
    4. Prairie Street Roadway Work
      1. Bernard to Welch: 02/25/25 – 06/11/25
    5. Mulberry Utilities
      1. Welch to Bernard: 02/25/25 – 05/13/25
    6. Mulberry Roadway
      1. Welch to Bernard: 05/14/25 – 08/06/25
    7. Bernard South Roadway (Fannin to Lindsey)
      1. Lindsey to Fannin: 12/31/24 – 06/23/25
    8. Avenue A Utilities
      1. Ave A/Maple Intersection: 01/24/25 – 02/28/25

    Summer 2025

    1. Chestnut Roadway
      1. Ave C to Ave D: 5/16/25 – 8/25/25
    2. Ave. D Roadway
      1. Chestnut to Mulberry (05/13/25 – 08/12/25
    3. Welch Roadway Work
      1. Chestnut to Mulberry: 3/31/25 – 06/16/25
      2. Mulberry to Hickory: 07/25/24 – 09/22/25
    4. Prairie Street Roadway Work
      1. 02/25/25 – 06/11/25
    5. Union Circle Utilities
      1. South (Prairie): 5/14/25-7/11/25
    6. Union Circle Roadway
      1. All: 7/11/25 – 10/02/25
    7. Mulberry Roadway
      1. Welch to Bernard: 4/23/25-7/22/25
    8. Welch Roadway Work
      1. Mulberry to Hickory: 07/25/25 – 09/22/25

    Fall 2025

    1. Chestnut Roadway
      1. Ave C to Ave D: 5/16/25 – 8/25/25
    2. Welch Roadway Work
      1. Eagle to Highland: 08/22/25 – 11/17/25
      2. Highland to Prairie: 10/25 – 01/26/26
    3. Union Circle Utilities
      1. South (Prairie): 5/14/25-7/11/25
      2. West: 5/14/25-7/11/25
      3. North (Chestnut): 5/14/25-7/11/25
    4. Union Circle Roadway
      1. South (Prairie): 7/11/25 – 10/02/25
      2. West: 7/11/25 – 10/02/25
      3. North (Chestnut): 7/11/25 – 10/02/25
    5. Welch Roadway Work
      1. Mulberry to Hickory: 07/25/25 – 09/22/25

    Spring 2026

    1. Bernard North Utilities
      1. Hickory to Chestnut: 01/12/26 – 02/27/26
    2. Bernard North Roadway
      1. Hickory to Chestnut: 02/27/26 – 06/09/26
    3. Avenue A Utilities
      1. Eagle to Maple: 2/25/26-4/2/26
      2. Ave A/Maple Intersection: 4/3/26-7/13/26

    Summer 2026

    1. Bernard North Roadway
      1. Hickory to Chestnut: 4/3/26-7/8/26
Page last updated: 29 Oct 2025, 02:30 PM