August 2025 Construction Update

Construction for Package 1 (GMP1) has completed.

Packages 2 and 3 are in construction with anticipated completion Q4 2026

Streets with active construction:

Aileen - (Panhandle to Cordell) **Had significant delays due to weather and Atmos conflicts but nearing completion.

Ave. D - (Chestnut to Mulberry)

Chestnut - (Ave. D to Ave. C)

Congress - (Ponder St. to Carroll)

Congress West - (Malone to Bryan)

Crescent East - (Carroll to Bolivar) **Asphalt completion Aug. 5-6

Crescent West - (Aileen to Malone)

Denton St. - (Hickory to Congress)

Egan St. - (Carroll to Bolivar)

Mulberry St. - (Welch to Bernard)

Ponder Ave. - (Oak to Panhandle)

Sunset St. 1 - (University to Carroll)

Sunset St. 2 - (Carroll to Bolivar)

Union Circle - (Prairie to Chestnut)

Welch St. - (Eagle to Hickory) ****Constructed in segments. Completed segments are Highland to Eagle and Prairie to Sycamore

Scripture St. - (Jagoe to Ponder) ***Delayed due to Atmos conflicts. Atmos conflicts are scheduled to be completed 9/1/25 at which point roadway construction will resume