Category 2025 Show all
-
December 2025 Construction Update
Share December 2025 Construction Update on Facebook Share December 2025 Construction Update on Twitter Share December 2025 Construction Update on Linkedin Email December 2025 Construction Update linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities (Water / Wastewater Installation):
- Alice (Panhandle / Crescent) – Continue sewer lines followed by water main.
- Parkway (Denton / Carroll) – Continue sewer lines followed by water main.
Earthwork/Flatwork (Roadway Reconstruction):
- Amarillo (Congress / Haynes) – Curb, gutter, driveways, and miscellaneous concrete followed by backfill and sod.
- Cordell (Fulton / Coit) – Curb and gutter to begin.
- Denton St. (Hickory / Congress E) – ATMOS re-design.
- Egan (East) – Grading followed by mixing subgrade and 1st lift of asphalt.
- Emery and Fulton – Begin curb and gutter.
- Mounts (Haynes / Congress E) – Removals followed by subgrade, asphalt, and flatwork concrete.
- Normal (W. Oak / Scripture) – Grading roadway followed by mixing subgrade.
- Ponder (Scripture / Grace Temple) – Begin curb and gutter.
- Ponder (Panhandle / Egan) – Removals to being.
- Prairie (Bernard / Welch) – Mixing subgrade followed by grading and 1st lift of asphalt.
- Scripture – ATMOS re-design.
- Welch / Sycamore Intersection – Removals, grading, flexbase install, and 1st lift of asphalt to begin.
- Welch (Mulberry / Hickory) – Final lift of asphalt followed by signage, sod, and traffic control removal.
-
November 2025 Construction Update
Share November 2025 Construction Update on Facebook Share November 2025 Construction Update on Twitter Share November 2025 Construction Update on Linkedin Email November 2025 Construction Update linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities (Water / Wastewater Installation):
- Normal (W. Oak / Scripture) – Continue installing reinforced concrete pipe.
- Alice (Panhandle / Crescent) – Continue sewer lines followed by water main and laterals.
- Parkway (Denton / Carroll) – Continue boring water line across Carroll and sewer main followed by water lines.
Earthwork/Flatwork (Roadway Reconstruction):
- Amarillo (Congress / Haynes) – Curb, gutter, driveways, and miscellaneous concrete.
- Cordell (Crescent / Fulton) – Sod, striping, signage, and traffic control removal to be completed.
- Denton St. (Hickory / Congress E) – ATMOS re-design.
- Egan (West) – Continue curb, gutter, and miscellaneous concrete work followed by sod and final lift of asphalt.
- Egan (East) – Traffic control placement followed by removals.
- Emery and Fulton – Begin curb and gutter.
- Mounts (Haynes / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work followed by sod.
- Normal (W. Oak / Scripture) – Traffic control placed followed by removals.
- Ponder (Scripture / Grace Temple) – Begin curb and gutter.
- Ponder (Egan / Scripture) – Lime followed by fine grading and 1st lift of asphalt.
- Prairie (Bernard / Welch) – Continue removals followed by grading.
- Scripture – ATMOS re-design.
- Sunset (University to Alice) – Parking lot asphalt to be placed.
- Welch (Highland / Prairie) – 2nd lift of asphalt complete followed by 3rd lift, striping, signage, and traffic control removal.
- Welch (Mulberry / Hickory) – Continue curb, gutter, driveways, and miscellaneous concrete work followed by sod and final lift of asphalt.
-
October 2025 Construction Update - 3
Share October 2025 Construction Update - 3 on Facebook Share October 2025 Construction Update - 3 on Twitter Share October 2025 Construction Update - 3 on Linkedin Email October 2025 Construction Update - 3 linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Normal (W. Oak / Scripture) – Chlorination and pressure testing is ongoing.
- Ponder (W. Oak / Panhandle) – Chlorination testing passed and tie-ins rescheduled.
- Alice (Panhandle / Crescent) – Continue installation of sewer lines.
- Parkway (Denton / Carroll) – Continue sewer line with boring scheduled.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
Earthwork/Flatwork:
- Amarillo (Congress / Haynes) - Continue curb, gutter, driveways, and miscellaneous concrete work.
- Cordell (Crescent / Fulton) – Final lift of asphalt scheduled followed by striping and signage.
- Denton St. (Hickory / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
- Denton at Oak – ATMOS delay
- Egan (West) – Curb and gutter to begin.
- Mounts (Haynes / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
- Ponder (Scripture / Grace Temple) – Lime remix and final grading followed by 1st lift of asphalt, curb and gutter.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset (University / Alice) – Parking lot work to begin
- Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work followed by backfill and sod.
- Welch (Mulberry / Hickory) – Continue curb, gutter, driveways, and miscellaneous concrete work.
-
October 2025 Construction Update - 2
Share October 2025 Construction Update - 2 on Facebook Share October 2025 Construction Update - 2 on Twitter Share October 2025 Construction Update - 2 on Linkedin Email October 2025 Construction Update - 2 linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Normal (W. Oak / Scripture) – Services and hydrant to be installed followed by chlorination and pressure testing.
- Ponder (W. Oak / Panhandle) – Chlorination testing followed by tie-ins.
- Alice (Panhandle / Crescent) – Continue installation of sewer lines.
- Parkway (Denton / Carroll) – Boring operations to begin.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
- Carlton (Aileen / Gober) – Light conduit and boxes to begin.
Earthwork/Flatwork:
- Amarillo (Haynes / Congress E) – Continue grading and excavating with mixing operations to follow.
- Avenue G (Prairie / Louise) – Pending asphalt infill.
- Carlton (Aileen / Gober) – Pending striping and signage.
- Cordell (Crescent / Fulton) – Continuing curb, gutter, and driveways followed by backfill and sod.
- Denton St. (Hickory / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
- Emery & Fulton - Lime operations followed by 1st lift of asphalt.
- Mounts (Haynes / Congress E) – Curb and gutter to begin.
- Ponder (Scripture / Grace Temple) – Water service and ATMOS delay.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset (University / Carroll) – Open to traffic.
- Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work to resume.
- Welch (Mulberry / Hickory) – Continue mixing and grading operations followed by 1st lift of asphalt.
-
October 2025 Construction Update
Share October 2025 Construction Update on Facebook Share October 2025 Construction Update on Twitter Share October 2025 Construction Update on Linkedin Email October 2025 Construction Update linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Normal (W. Oak / Scripture) – Continue water main and lateral.
- Ponder (W. Oak / Panhandle) – Chlorination testing.
- Alice (Panhandle / Crescent) – Backfill bore operation followed by installation of sewer line.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
- Carlton (Aileen / Gober) – Light conduit and boxes to begin.
Earthwork/Flatwork:
- Amarillo (Haynes / Congress E) – Demo saw cutting followed by asphalt and concrete removals.
- Avenue G (Prairie / Louise) – Pending asphalt infill.
- Carlton (Aileen / Gober) – Backfill, sod, striping, and signage.
- Congress E (Denton / Carroll) – Striping and signage.
- Cordell (Crescent / Fulton) – Continuing curb, gutter, and driveways.
- Cordell (Fulton / Alice) – Fine grading follow by 1st lift of asphalt and flatwork activities.
- Denton St. (Hickory / Congress E) – Curb, gutter, driveways, and miscellaneous concrete work.
- Egan (West) – First lift of asphalt followed by curb, gutter, and driveways.
- Mounts (Haynes / Congress E) – Curb, gutter, driveways, and miscellaneous concrete work.
- Ponder (Scripture / Grace Temple) – Continuing concrete removals followed by rough grading and lime mixing.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset North (University / Carroll) – Concrete driveways and miscellaneous concrete work.
- Union Circle - open to traffic.
- Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work.
- Welch (Chestnut Intersections) – Striping
- Welch (Mulberry / Hickory) – Asphalt and concrete removals to being followed by rough grading.
-
September 2025 Construction Update - 2
Share September 2025 Construction Update - 2 on Facebook Share September 2025 Construction Update - 2 on Twitter Share September 2025 Construction Update - 2 on Linkedin Email September 2025 Construction Update - 2 linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Amarillo (Haynes / Congress E) – Pressure test complete with chlorination and tie-in schedule.
- Egan (Carroll / Bolivar) – Pressure test complete with chlorination and tie-in schedule.
- Normal (W. Oak / Scripture) – Started water main and lateral.
- Ponder (W. Oak / Panhandle) – Continue laterals.
- Alice (Panhandle / Crescent) – Boring operations to being with sewer installation to follow.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
- Carlton (Aileen / Gober) – Light conduit and boxes to begin.
- Welch (Prairie) – Installation of signal conduit to begin.
- Welch (Chestnut) – Installation of signal conduit to begin.
- Union Circle – Reprogramming signals.
Earthwork/Flatwork:
- Aileen (Panhandle / Cordell) – Complete.
- Avenue G (Prairie / Louise) – Pending asphalt infill.
- Carlton (Aileen / Gober) – Continuing placement of curb, gutter, and driveways.
- Congress E (Ponder / Denton) – Backfill and sod.
- Congress E (Denton / Carroll) – Started curb, gutter, and driveways.
- Cordell (Crescent / Fulton) – Curb, gutter, and driveways have started.
- Cordell (Fulton / Alice) - Demo and removals have started with grading and excavation to follow.
- Crescent (Aileen / Malone) – Backfilling and sod.
- Denton St. (Hickory / Congress E) – First lift of asphalt scheduled.
- Egan (West) - Demo and removals started with grading and excavation to follow.
- Mounts (Haynes / Congress E) – First lift of asphalt started.
- Mulberry (Welch / Bernard N) – Pending asphalt infill.
- Ponder (Panhandle / W. Oak) – ATMOS work.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset North (University / Carroll) – First lift of asphalt complete and curb and gutter has started.
- Union Circle North and West - Striping started with sod to follow.
- Welch (Sycamore / Mulberry) – Infill around inlet.
- Welch (Highland / Prairie) – Demo and removals started with grading and excavation to follow.
-
September 2025 Construction Update
Share September 2025 Construction Update on Facebook Share September 2025 Construction Update on Twitter Share September 2025 Construction Update on Linkedin Email September 2025 Construction Update linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Amarillo (Haynes / Congress E) – Continue waterlines and laterals.
- Egan (Carroll / Bolivar) – Pressure test and chlorination with tie-ins to follow.
- Normal (W. Oak / Scripture) – Installing 18" RCP and Junction Boxes followed by water line.
- Ponder (W. Oak / Panhandle) – Continue waterlines and laterals.
- Alice (Panhandle / Crescent) - Boring operations to being.
Electrical:
- Aileen (Panhandle / Cordell) - Light conduit and boxes to begin.
- Union Circle North - Installing conduit boxes.
Earthwork/Flatwork:
- Aileen (Panhandle / Cordell) – Pending striping and signage.
- Avenue G (Prairie / Louise) – Completed asphalt with TCP pick-up on 9/5.
- Carlton (Aileen / Gober) – Asphalt completed and continuing placement of curb and gutter.
- Congress E (Ponder / Denton) – Continuing curb, gutter, and driveways.
- Congress E (Denton / Carroll) – 1st lift of asphalt scheduled with curb and gutter to follow.
- Congress W (Malone / Bryan) – Asphalt completed with striping, signage, and TCP pick-up to follow.
- Cordell (Fulton / Crescent) – 1st lift of asphalt completed.
- Crescent (Carroll / Bolivar) – Continuing concrete driveway and miscellaneous concrete work.
- Denton St. (Hickory / Congress E) – Rough grading completed with cem-line scheduled.
- Mounts (Haynes / Congress E) – Demo completed and mixing schedule with mellow and remixing to follow.
- Mulberry (Welch / Bernard N) – Backfill completed and pending sod.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset South (University / Carroll) – Traffic switch completed with removals and earthwork started.
- Union Circle North - Continuing concrete work with backfiling to follow.
- Welch (Sycamore / Mulberry) – Throats and tops to be completed with backfill to follow.
-
August 2025 Construction Update - 2
Share August 2025 Construction Update - 2 on Facebook Share August 2025 Construction Update - 2 on Twitter Share August 2025 Construction Update - 2 on Linkedin Email August 2025 Construction Update - 2 linkWork Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Amarillo (Haynes / Congress E) – Continue waterlines and laterals.
- Egan (Carroll / Bolivar) – Boring has started with waterline and laterals to follow.
- Normal (W. Oak / Scripture) – Started storm sewer.
- Ponder (W. Oak / Panhandle) – Continue waterlines and laterals.
Earthwork/Flatwork:
- Aileen (Panhandle / Cordell) – Final asphalt lift completed. Pending striping, signage, sod, and electrical.
- Avenue G (Prairie / Louise) – C&G, driveway, and valley gutter poured.
- Carlton (Aileen / Gober) – Finish grade completed and pending placement of asphalt.
- Congress E (Ponder / Denton) – 1st lift of asphalt completed.
- Congress E (Denton / Carroll) – Mixing lime with remix to follow.
- Congress W (Malone / Bryan) – Curb and gutter concrete placement completed and continuing to backfill for sod.
- Cordell (Fulton / Crescent) – Finish grade completed with asphalt to follow.
- Crescent (Carroll / Bolivar) – C&G and driveways formed and poured.
- Denton St. (Hickory / Congress E) – Asphalt millings started with earthwork to follow.
- Mounts (Haynes / Congress E) – Potholing and demo has started.
- Mulberry (Welch / Bernard N) – C&G and driveways formed and pending concrete placement.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset South (University / Carroll) – Completing valley gutter with asphalt and traffic switch to follow.
- Union Circle North - Electrical boxes installed and C&G to continue.
- Welch (Sycamore / Mulberry) – Standard Inlets to begin.
-
August 2025 Construction Update
Share August 2025 Construction Update on Facebook Share August 2025 Construction Update on Twitter Share August 2025 Construction Update on Linkedin Email August 2025 Construction Update linkConstruction for Package 1 (GMP1) has completed.
Packages 2 and 3 are in construction with anticipated completion Q4 2026
Streets with active construction:
Aileen - (Panhandle to Cordell) **Had significant delays due to weather and Atmos conflicts but nearing completion.
Ave. D - (Chestnut to Mulberry)
Chestnut - (Ave. D to Ave. C)
Congress - (Ponder St. to Carroll)
Congress West - (Malone to Bryan)
Crescent East - (Carroll to Bolivar) **Asphalt completion week of Aug.11
Crescent West - (Aileen to Malone)
Denton St. - (Hickory to Congress)
Egan St. - (Carroll to Bolivar)
Mulberry St. - (Welch to Bernard)
Ponder Ave. - (Oak to Panhandle)
Sunset St. 1 - (University to Carroll)
Sunset St. 2 - (Carroll to Bolivar)
Union Circle - (Prairie to Chestnut)
Welch St. - (Eagle to Hickory) ****Constructed in segments. Completed segments are Highland to Eagle and Prairie to Sycamore
Scripture St. - (Jagoe to Ponder) ***Delayed due to Atmos conflicts. Atmos conflicts are scheduled to be completed 9/1/25 at which point roadway construction will resume