September 2025 Construction Update - 2
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Amarillo (Haynes / Congress E) – Pressure test complete with chlorination and tie-in schedule.
- Egan (Carroll / Bolivar) – Pressure test complete with chlorination and tie-in schedule.
- Normal (W. Oak / Scripture) – Started water main and lateral.
- Ponder (W. Oak / Panhandle) – Continue laterals.
- Alice (Panhandle / Crescent) – Boring operations to being with sewer installation to follow.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
- Carlton (Aileen / Gober) – Light conduit and boxes to begin.
- Welch (Prairie) – Installation of signal conduit to begin.
- Welch (Chestnut) – Installation of signal conduit to begin.
- Union Circle – Reprogramming signals.
Earthwork/Flatwork:
- Aileen (Panhandle / Cordell) – Complete.
- Avenue G (Prairie / Louise) – Pending asphalt infill.
- Carlton (Aileen / Gober) – Continuing placement of curb, gutter, and driveways.
- Congress E (Ponder / Denton) – Backfill and sod.
- Congress E (Denton / Carroll) – Started curb, gutter, and driveways.
- Cordell (Crescent / Fulton) – Curb, gutter, and driveways have started.
- Cordell (Fulton / Alice) - Demo and removals have started with grading and excavation to follow.
- Crescent (Aileen / Malone) – Backfilling and sod.
- Denton St. (Hickory / Congress E) – First lift of asphalt scheduled.
- Egan (West) - Demo and removals started with grading and excavation to follow.
- Mounts (Haynes / Congress E) – First lift of asphalt started.
- Mulberry (Welch / Bernard N) – Pending asphalt infill.
- Ponder (Panhandle / W. Oak) – ATMOS work.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset North (University / Carroll) – First lift of asphalt complete and curb and gutter has started.
- Union Circle North and West - Striping started with sod to follow.
- Welch (Sycamore / Mulberry) – Infill around inlet.
- Welch (Highland / Prairie) – Demo and removals started with grading and excavation to follow.
Share September 2025 Construction Update - 2 on Facebook
Share September 2025 Construction Update - 2 on Twitter
Share September 2025 Construction Update - 2 on Linkedin
Email September 2025 Construction Update - 2 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends