September 2025 Construction Update - 2

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

Streets with active construction:

Utilities:

  • Amarillo (Haynes / Congress E) – Pressure test complete with chlorination and tie-in schedule.
  • Egan (Carroll / Bolivar) – Pressure test complete with chlorination and tie-in schedule.
  • Normal (W. Oak / Scripture) – Started water main and lateral.
  • Ponder (W. Oak / Panhandle) – Continue laterals.
  • Alice (Panhandle / Crescent) – Boring operations to being with sewer installation to follow.

Electrical:

  • Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
  • Carlton (Aileen / Gober) – Light conduit and boxes to begin.
  • Welch (Prairie) – Installation of signal conduit to begin.
  • Welch (Chestnut) – Installation of signal conduit to begin.
  • Union Circle – Reprogramming signals.

Earthwork/Flatwork:

  • Aileen (Panhandle / Cordell) – Complete.
  • Avenue G (Prairie / Louise) – Pending asphalt infill.
  • Carlton (Aileen / Gober) – Continuing placement of curb, gutter, and driveways.
  • Congress E (Ponder / Denton) – Backfill and sod.
  • Congress E (Denton / Carroll) – Started curb, gutter, and driveways.
  • Cordell (Crescent / Fulton) – Curb, gutter, and driveways have started.
  • Cordell (Fulton / Alice) - Demo and removals have started with grading and excavation to follow.
  • Crescent (Aileen / Malone) – Backfilling and sod.
  • Denton St. (Hickory / Congress E) – First lift of asphalt scheduled.
  • Egan (West) - Demo and removals started with grading and excavation to follow.
  • Mounts (Haynes / Congress E) – First lift of asphalt started.
  • Mulberry (Welch / Bernard N) – Pending asphalt infill.
  • Ponder (Panhandle / W. Oak) – ATMOS work.
  • Scripture (Jagoe / Ponder) – ATMOS re-design.
  • Sunset North (University / Carroll) – First lift of asphalt complete and curb and gutter has started.
  • Union Circle North and West - Striping started with sod to follow.
  • Welch (Sycamore / Mulberry) – Infill around inlet.
  • Welch (Highland / Prairie) – Demo and removals started with grading and excavation to follow.