Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Normal (W. Oak / Scripture) – Services and hydrant to be installed followed by chlorination and pressure testing.
- Ponder (W. Oak / Panhandle) – Chlorination testing followed by tie-ins.
- Alice (Panhandle / Crescent) – Continue installation of sewer lines.
- Parkway (Denton / Carroll) – Boring operations to begin.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
- Carlton (Aileen / Gober) – Light conduit and boxes to begin.
Earthwork/Flatwork:
- Amarillo (Haynes / Congress E) – Continue grading and excavating with mixing operations to follow.
- Avenue G (Prairie / Louise) – Pending asphalt infill.
- Carlton (Aileen / Gober) – Pending striping and signage.
- Cordell (Crescent / Fulton) – Continuing curb, gutter, and driveways followed by backfill and sod.
- Denton St. (Hickory / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
- Emery & Fulton - Lime operations followed by 1st lift of asphalt.
- Mounts (Haynes / Congress E) – Curb and gutter to begin.
- Ponder (Scripture / Grace Temple) – Water service and ATMOS delay.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset (University / Carroll) – Open to traffic.
- Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work to resume.
- Welch (Mulberry / Hickory) – Continue mixing and grading operations followed by 1st lift of asphalt.
Share October 2025 Construction Update - 2 on Facebook
Share October 2025 Construction Update - 2 on Twitter
Share October 2025 Construction Update - 2 on Linkedin
Email October 2025 Construction Update - 2 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends