October 2025 Construction Update - 2

Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.

Streets with active construction:

Utilities:

  • Normal (W. Oak / Scripture) – Services and hydrant to be installed followed by chlorination and pressure testing.
  • Ponder (W. Oak / Panhandle) – Chlorination testing followed by tie-ins.
  • Alice (Panhandle / Crescent) – Continue installation of sewer lines.
  • Parkway (Denton / Carroll) – Boring operations to begin.

Electrical:

  • Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
  • Carlton (Aileen / Gober) – Light conduit and boxes to begin.

Earthwork/Flatwork:

  • Amarillo (Haynes / Congress E) – Continue grading and excavating with mixing operations to follow.
  • Avenue G (Prairie / Louise) – Pending asphalt infill.
  • Carlton (Aileen / Gober) – Pending striping and signage.
  • Cordell (Crescent / Fulton) – Continuing curb, gutter, and driveways followed by backfill and sod.
  • Denton St. (Hickory / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
  • Emery & Fulton - Lime operations followed by 1st lift of asphalt.
  • Mounts (Haynes / Congress E) – Curb and gutter to begin.
  • Ponder (Scripture / Grace Temple) – Water service and ATMOS delay.
  • Scripture (Jagoe / Ponder) – ATMOS re-design.
  • Sunset (University / Carroll) – Open to traffic.
  • Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work to resume.
  • Welch (Mulberry / Hickory) – Continue mixing and grading operations followed by 1st lift of asphalt.