October 2025 Construction Update - 3
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities:
- Normal (W. Oak / Scripture) – Chlorination and pressure testing is ongoing.
- Ponder (W. Oak / Panhandle) – Chlorination testing passed and tie-ins rescheduled.
- Alice (Panhandle / Crescent) – Continue installation of sewer lines.
- Parkway (Denton / Carroll) – Continue sewer line with boring scheduled.
Electrical:
- Aileen (Panhandle / Cordell) – Light conduit and boxes continued.
Earthwork/Flatwork:
- Amarillo (Congress / Haynes) - Continue curb, gutter, driveways, and miscellaneous concrete work.
- Cordell (Crescent / Fulton) – Final lift of asphalt scheduled followed by striping and signage.
- Denton St. (Hickory / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
- Denton at Oak – ATMOS delay
- Egan (West) – Curb and gutter to begin.
- Mounts (Haynes / Congress E) – Continue curb, gutter, driveways, and miscellaneous concrete work.
- Ponder (Scripture / Grace Temple) – Lime remix and final grading followed by 1st lift of asphalt, curb and gutter.
- Scripture (Jagoe / Ponder) – ATMOS re-design.
- Sunset (University / Alice) – Parking lot work to begin
- Welch (Highland / Prairie) – Curb, gutter, driveways, and miscellaneous concrete work followed by backfill and sod.
- Welch (Mulberry / Hickory) – Continue curb, gutter, driveways, and miscellaneous concrete work.
Share October 2025 Construction Update - 3 on Facebook
Share October 2025 Construction Update - 3 on Twitter
Share October 2025 Construction Update - 3 on Linkedin
Email October 2025 Construction Update - 3 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends