December 2025 Construction Update
Work Packages 2 and 3 are in construction with anticipated completion Q4 2026.
Streets with active construction:
Utilities (Water / Wastewater Installation):
- Alice (Panhandle / Crescent) – Continue sewer lines followed by water main.
- Parkway (Denton / Carroll) – Continue sewer lines followed by water main.
Earthwork/Flatwork (Roadway Reconstruction):
- Amarillo (Congress / Haynes) – Curb, gutter, driveways, and miscellaneous concrete followed by backfill and sod.
- Cordell (Fulton / Coit) – Curb and gutter to begin.
- Denton St. (Hickory / Congress E) – ATMOS re-design.
- Egan (East) – Grading followed by mixing subgrade and 1st lift of asphalt.
- Emery and Fulton – Begin curb and gutter.
- Mounts (Haynes / Congress E) – Removals followed by subgrade, asphalt, and flatwork concrete.
- Normal (W. Oak / Scripture) – Grading roadway followed by mixing subgrade.
- Ponder (Scripture / Grace Temple) – Begin curb and gutter.
- Ponder (Panhandle / Egan) – Removals to being.
- Prairie (Bernard / Welch) – Mixing subgrade followed by grading and 1st lift of asphalt.
- Scripture – ATMOS re-design.
- Welch / Sycamore Intersection – Removals, grading, flexbase install, and 1st lift of asphalt to begin.
- Welch (Mulberry / Hickory) – Final lift of asphalt followed by signage, sod, and traffic control removal.
Share December 2025 Construction Update on Facebook
Share December 2025 Construction Update on Twitter
Share December 2025 Construction Update on Linkedin
Email December 2025 Construction Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends