2019 Bond Neighborhood 2 & 6

Share 2019 Bond Neighborhood 2 & 6 on Facebook Share 2019 Bond Neighborhood 2 & 6 on Twitter Share 2019 Bond Neighborhood 2 & 6 on Linkedin Email 2019 Bond Neighborhood 2 & 6 link

The 2019 Bond Neighborhoods 2 & 6 project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 2 & 6 project as well as the breakdown of the phases (Packages 1, 2 & 3). Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.

Project Timeline Q4 2022 - Q4 2026*

*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle, including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.

The 2019 Bond Neighborhoods 2 & 6 project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 2 & 6 project as well as the breakdown of the phases (Packages 1, 2 & 3). Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.

Project Timeline Q4 2022 - Q4 2026*

*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle, including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.

  • 3/29/24 Update

    Share 3/29/24 Update on Facebook Share 3/29/24 Update on Twitter Share 3/29/24 Update on Linkedin Email 3/29/24 Update link
    supporting image

    Good Friday is wrapping up as is good progress on the Neighborhood 2&6 project street sections. On behalf of the Team, we appreciate your support and wish you a Safe and Happy Easter Weekend! There won't be any work this weekend but we'll be back on site Monday.

    For more project information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)

  • 3/22/2024 Update

    Share 3/22/2024 Update on Facebook Share 3/22/2024 Update on Twitter Share 3/22/2024 Update on Linkedin Email 3/22/2024 Update link

    (All dates are subject to change due to weather impacts or unforeseen circumstances)


    MAPLE St.

    • Completed - Northside curb and gutter installation. Remaining concrete activities on this north side are several ramps and small amount of sidewalk.
    • Next week - Second lift of asphalt is scheduled for Tuesday 3/26 and Wednesday 3/27. Traffic Control Plan activities will follow second lift of asphalt which will require switching work to the south side for upcoming removal activities.

    BROADWAY St.

    • Completed - Earthwork activities have been completed this week and the lime-stabilized subgrade is now ready for the first lift of asphalt.
    • Next week - First Lift of Asphalt scheduled for Monday 3/25. Following the asphalt installation concrete crew will begin curb and gutter, driveways, and a couple curb ramps.

    CRESCENT / HILLCREST

    • Completed - Installation of the sewer manholes (2) and piping on Cresent between Ector and Hillcrest.
    • Next week - Trench work and pipe installation to begin at the intersection of Hillcrest/Crescent and move south.

    For more information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)

  • February Update

    Share February Update on Facebook Share February Update on Twitter Share February Update on Linkedin Email February Update link
    supporting image

    Neighborhood 2 & 6 project is currently in the design and construction phases.

    Expect to see survey crews and staff in the areas of the project.

    Construction has started for Package 1. Expect to see crews, equipment and street closures in the areas of package one. (reference map)

    Detour routes will be provided for street closures.

  • January Update

    Share January Update on Facebook Share January Update on Twitter Share January Update on Linkedin Email January Update link
    supporting image

    Neighborhood 2 & 6 project is currently in the planning and design phase.

    Expect to see survey crews and staff in the areas of the project.

    Estimated construction start for Package 1 will be January 2024

  • December Update for Neighborhood 2 & 6

    Share December Update for Neighborhood 2 & 6 on Facebook Share December Update for Neighborhood 2 & 6 on Twitter Share December Update for Neighborhood 2 & 6 on Linkedin Email December Update for Neighborhood 2 & 6 link
    supporting image

    Neighborhood 2 & 6 project is currently in the planning and design phase.

    Expect to see survey crews and staff in the areas of the project.

    Estimated construction start for Package 1 will be January 2024

  • November Update for Neighborhood 6

    Share November Update for Neighborhood 6 on Facebook Share November Update for Neighborhood 6 on Twitter Share November Update for Neighborhood 6 on Linkedin Email November Update for Neighborhood 6 link
    supporting image

    Neighborhood 6 project is currently in the planning and design phase.

    Expect to see survey crews and staff in the areas of the project.

    Estimated construction start is Q1 2024

  • September Update for Neighborhood 6

    Share September Update for Neighborhood 6 on Facebook Share September Update for Neighborhood 6 on Twitter Share September Update for Neighborhood 6 on Linkedin Email September Update for Neighborhood 6 link
    supporting image

    Neighborhood 6 project is currently in the planning and design phase.

    Expect to see survey crews and staff in the areas of the project.

    Estimated construction start is Q4 2023

  • Update for Neighborhood 6 Project

    Share Update for Neighborhood 6 Project on Facebook Share Update for Neighborhood 6 Project on Twitter Share Update for Neighborhood 6 Project on Linkedin Email Update for Neighborhood 6 Project link
    supporting image

    Neighborhood 6 project is currently in the planning and design phase.

    Expect to see survey crews and staff in the areas of the project.

    Estimated construction start is Q4 2023

  • Update for Neighborhood 6 Project

    Share Update for Neighborhood 6 Project on Facebook Share Update for Neighborhood 6 Project on Twitter Share Update for Neighborhood 6 Project on Linkedin Email Update for Neighborhood 6 Project link
    supporting image

    Neighborhood 6 project is currently in the planning and design phase.

    Expect to see survey crews and staff in the areas of the project.

    Estimated construction start is Q4 2023

  • Update for Neighborhood 6 Project

    Share Update for Neighborhood 6 Project on Facebook Share Update for Neighborhood 6 Project on Twitter Share Update for Neighborhood 6 Project on Linkedin Email Update for Neighborhood 6 Project link
    supporting image

    Neighborhood 6 project is currently in the planning and design phase.

    Expect to see survey crews and staff in the areas of the project.

    Estimated construction start is Q4 2023

Page last updated: 03 Nov 2025, 06:53 AM