Share 3/29/24 Update on Facebook
Share 3/29/24 Update on Linkedin
Email 3/29/24 Update link
Good Friday is wrapping up as is good progress on the Neighborhood 2&6 project street sections. On behalf of the Team, we appreciate your support and wish you a Safe and Happy Easter Weekend! There won't be any work this weekend but we'll be back on site Monday.
For more project information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
Share 3/22/2024 Update on Facebook
Share 3/22/2024 Update on Linkedin
Email 3/22/2024 Update link
(All dates are subject to change due to weather impacts or unforeseen circumstances)
MAPLE St.
- Completed - Northside curb and gutter installation. Remaining concrete activities on this north side are several ramps and small amount of sidewalk.
-
Next week - Second lift of asphalt is scheduled for Tuesday 3/26 and Wednesday 3/27. Traffic Control Plan activities will follow second lift of asphalt which will require switching work to the south side for upcoming removal activities.
BROADWAY St.
- Completed - Earthwork activities have been completed this week and the lime-stabilized subgrade is now ready for the first lift of asphalt.
-
Next week - First Lift of Asphalt scheduled for Monday 3/25. Following the asphalt installation concrete crew will begin curb and gutter, driveways, and a couple curb ramps.
CRESCENT / HILLCREST
- Completed - Installation of the sewer manholes (2) and piping on Cresent between Ector and Hillcrest.
-
Next week - Trench work and pipe installation to begin at the intersection of Hillcrest/Crescent and move south.
For more information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
Share February Update on Facebook
Share February Update on Linkedin
Email February Update link
Neighborhood 2 & 6 project is currently in the design and construction phases.
Expect to see survey crews and staff in the areas of the project.
Construction has started for Package 1. Expect to see crews, equipment and street closures in the areas of package one. (reference map)
Detour routes will be provided for street closures.
Share January Update on Facebook
Share January Update on Linkedin
Email January Update link
Neighborhood 2 & 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start for Package 1 will be January 2024
Share December Update for Neighborhood 2 & 6 on Facebook
Share December Update for Neighborhood 2 & 6 on Linkedin
Email December Update for Neighborhood 2 & 6 link
Neighborhood 2 & 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start for Package 1 will be January 2024
Share November Update for Neighborhood 6 on Facebook
Share November Update for Neighborhood 6 on Linkedin
Email November Update for Neighborhood 6 link
Neighborhood 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start is Q1 2024
Share September Update for Neighborhood 6 on Facebook
Share September Update for Neighborhood 6 on Linkedin
Email September Update for Neighborhood 6 link
Neighborhood 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start is Q4 2023
Share Update for Neighborhood 6 Project on Facebook
Share Update for Neighborhood 6 Project on Linkedin
Email Update for Neighborhood 6 Project link
Neighborhood 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start is Q4 2023
Share Update for Neighborhood 6 Project on Facebook
Share Update for Neighborhood 6 Project on Linkedin
Email Update for Neighborhood 6 Project link
Neighborhood 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start is Q4 2023
Share Update for Neighborhood 6 Project on Facebook
Share Update for Neighborhood 6 Project on Linkedin
Email Update for Neighborhood 6 Project link
Neighborhood 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start is Q4 2023