3/22/2024 Update

(All dates are subject to change due to weather impacts or unforeseen circumstances)


MAPLE St.

  • Completed - Northside curb and gutter installation. Remaining concrete activities on this north side are several ramps and small amount of sidewalk.
  • Next week - Second lift of asphalt is scheduled for Tuesday 3/26 and Wednesday 3/27. Traffic Control Plan activities will follow second lift of asphalt which will require switching work to the south side for upcoming removal activities.

BROADWAY St.

  • Completed - Earthwork activities have been completed this week and the lime-stabilized subgrade is now ready for the first lift of asphalt.
  • Next week - First Lift of Asphalt scheduled for Monday 3/25. Following the asphalt installation concrete crew will begin curb and gutter, driveways, and a couple curb ramps.

CRESCENT / HILLCREST

  • Completed - Installation of the sewer manholes (2) and piping on Cresent between Ector and Hillcrest.
  • Next week - Trench work and pipe installation to begin at the intersection of Hillcrest/Crescent and move south.

For more information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)

Share 3/22/2024 Update on Facebook Share 3/22/2024 Update on Twitter Share 3/22/2024 Update on Linkedin Email 3/22/2024 Update link
#<Object:0x000000002b57eb78>