4/22/2024 Update and Lookahead
(All dates are subject to change due to weather impacts or unforeseen circumstances.)
Maple Street:
Completed - Lime was mixed last week and left to mellow over the weekend.
What's Next - Lime will be remixed 4/22/24 followed by compaction and fine grading this week. Asphalt is currently scheduled for April 30th.
Broadway Street:
Completed - Made great progress on concrete driveway placements last week!
What's Next - This week Sundt will be forming and placing the remaining concrete driveways and the inlet throat adjacent to Malone. Asphalt currently scheduled for May 2nd.
Hillcrest St:
Completed - 8" main installation was completed last week and substantial progress was made on the laterals.
What's Next - Complete laterals this week. The camera crew is schedule for Thursday. Plan to mill Hillcrest Friday 26th and Monday the 27th.
Crescent St (Ector St to Hillcrest St):
Completed - Removals completed last week followed rough grade starting.
What's Next - Rough grading continuing and Lime is currently scheduled for Thursday 25th.
Thomas/Crescent/Linden:
What's Next - Notice to Residents will be going out Wednesday & Traffic Control will be placed Friday. Sewer Installation will begin next week.
For more information - follow the SUNDT Project Update Site at:
Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)