4/5/2024 Update and Lookahead

(All dates are subject to change due to weather impacts or unforeseen circumstances.)


Maple Street:

Completed - Transitioned traffic control to close the south side of Maple St. followed by pedestrian control measures including snow fence and chain link fence panels. Milling of the existing asphalt was completed with temporary pedestrian crosswalks installed afterwards. Concrete removals will be complete 4/5/24 .

Next week - Rough grading, with lime currently scheduled for Wednesday 4/10/24 with mixing and mellowing through the weekend.


Broadway Street:

Completed - Curb and gutter formwork this week and will be pouring the first round of concrete 4/5/24.

Next week - Concrete placements everyday to complete all curb and gutter and begin driveways followed by curb ramps and leadwalks.


Hillcrest St:
ONGOING - continued this week installing hundreds of feet of 8" sewer mains and a new manhole at Linden.


Next week - Complete the main line and manhole at Panhandle. Service laterals will follow, starting at Crescent and working southward.


For more information - follow the SUNDT Project Update Site at:

Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)

Share 4/5/2024 Update and Lookahead on Facebook Share 4/5/2024 Update and Lookahead on Twitter Share 4/5/2024 Update and Lookahead on Linkedin Email 4/5/2024 Update and Lookahead link
#<Object:0x000000003d693448>