6/4/24 Update and Lookahead
We hope you have been safe. Winds and Rains have definitely been an issue for construction - and continues to be! Thank you for your patience and understanding! Below is an update on what has taken place last week and what's planned this week (weather permitting)
Central:
LAST Week: Utility Locates were completed. Survey is working on R.O.W. staking and work limits.
THIS Week: Traffic control measures will be on the road Monday to be utilized for the road shutdown to begin road reconstruction starting with potholing.
Welch (Eagle to Highland):
LAST Week: Utility Locates were completed. Survey is working on providing staking.
THIS Week: Traffic control measures will be on the road Monday to be utilized for the road shutdown to begin utility work.
Ave. D & Chestnut
LAST Week: Locates were completed. Survey is working on providing staking.
THIS Week: Traffic control measures will be on the road Monday to be utilized for the road shutdown to begin utility work Tuesday.
Maple Street (south side):
LAST Week: The continuance of concrete curb and gutter formwork, reinforcement install, and concrete placements occurred in limited amounts this week due to weather.
THIS Week: will the added drainage adjacent to the intersection of Ave B and continue concrete placements for sidewalks.
Broadway:
LAST Week: The majority of the sod was installed at BOC adjoining existing residential lawns.
THIS Week: Plan to complete the sod and start the Sundt punch process.
Hillcrest:
LAST Week: The lime mixing process, compaction, and lime depth testing completed with fine grading started.
THIS Week: Complete the grading and seal the roadway with an emulsion coat prior to Texas Materials placing asphalt Friday into the following week.
Crescent (Crescent to Panhandle):
LAST Week: Completed potholing of existing utility crossings at the Back of Curbs. Saw cutting for concrete removals was completed.
THIS Week: Start the milling of asphalt. After several days of milling, will begin the concrete removal process.
Thomas (Emery to Crescent):
LAST Week: Progress made on the sewer main and laterals moving south from Emery.
THIS Week: Will continue south with both the main and laterals.
Crescent (West of Thomas) and Linden:
THIS Week: Will be completing potholing and saw cutting in preparation for milling to follow.
For more information - follow the SUNDT Project Update Site at:
Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends