6/10/24 Update and Lookahead
THE LIST IS GROWING!!! SUNDT Construction and their Subs are making great progress - below are what's taken place last week and what's expected this week. Dates are always subject to change due to weather and other issues.
For even more information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
Maple Street (south side):
This week we completed the subgrade drainage and placed concrete for the remaining curb & gutter and sidewalks. We have the ramps at Ave B and the valley gutter scope remaining. We are planning on placing the ramps and valley gutter concrete this week.
** Full Road Closure - The second lift of asphalt on the south side is scheduled for Monday June 17, with the final cap from Ave D through Ave C June 18 & 19th.
Broadway:
This past week the sod was completed and we started the joint sealant of the concrete.
This week we will complete the sealant and start the Sundt punch process.
Crescent (East):
This past week we completed backfilling of curbs for future sod installation.
This week we will be placing the second and final lifts of asphalt.
Hillcrest:
This past week the fine grading was completed on the entirety of Hillcrest after some rain impact and we asphalt primed the subgrade.
This week we will be placing the first lift of asphalt followed by mobilization of a concrete crew.
Crescent (Crescent to Panhandle):
This past week we completed milling of the asphalt for this section and started miscellaneous concrete removals including curb & gutter and driveways.
This week we will continue the removals this week followed by excavating subgrade.
Thomas (Emery to Crescent):
This past week John Burns continued installing main line and laterals south from Emery.
This week John Burns will continue installations southward.
Crescent (West of Thomas) and Linden:
This past week we completed milling of the asphalt for this section last week.
This week we will begin the removals this week followed by excavating subgrade.
Central:
This past week locates and survey were completed early in the week. We completed the milling of asphalt and miscellaneous concrete removals by the end of the week.
This week we will begin excavating subgrade.
Welch (Eagle to Highland):
This past week traffic control was placed, survey was completed, locates were started adjacent to Eagle, and saw cutting for the new water line was completed up to Highland. John Burns was able to place the first pipe section by the end of the week.
This week John Burns will continue locates and placing new water main piping.
Ave. D & Chestnut
This past week traffic control was placed, survey was completed, saw cutting for the new sewer main completed on both Ave D and Chestnut, locates were started at the intersection and at the Mulberry intersection, and John Burns removed the existing sewer manholes at the intersection. This week John Burns also started trenching and placing new sewer main on Ave D at Mulberry southward.
Share 6/10/24 Update and Lookahead on Facebook
Share 6/10/24 Update and Lookahead on Twitter
Share 6/10/24 Update and Lookahead on Linkedin
Email 6/10/24 Update and Lookahead link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends