Look-Ahead UPDATE 08/24/24
Maple Street:
Last Week and next week finalizing the last details of Sundt's punch work.
Crescent (East - Ector to Hillcrest):
Last Week - Completed the corrections to the curb & gutters & driveway on the south side.
Next Week - Cleaning up the roadway, pulling back the TCP measures, etc.
Hillcrest:
Last Week - Completed the replacement of the curb inlet top.
Next Week - Stripping and backfilling the area and also cleaning up the roadway, pulling back the Traffic Control devices.
Thomas (Panhandle to Emery):
Last Week - Started form work and reinforcement placement for the curb & gutter, starting at Panhandle and working north.
Next Week - continue form work and start concrete placement (currently scheduled for late in the week).
Crescent (West- Thomas to Stanley) & Linden (Thomas to Bonnie Brae):
Last Week - Asphalt completed
Next Week - Cleaning up the roadway, pulling back the TCP measures, etc.
Central (Maple to Highland):
Last Week - Completed the concrete work on the curb & gutter and driveway into the parking lot (east entry) and placed both the second and final asphalt lifts. Saturday morning (8/24/24) we will be restoring vehicular access to the parking garage.
Next Week - Work will continue with the existing sidewalk/ramp connection at the northeast corner at Maple. Will be cleaning up the roadway, pulling back the Traffic Control devices. Striping scheduled for Friday.
Welch (Chestnut to Prairie):
Continue new water infrastructure and next week with chlorination to follow (Chestnut back to Eagle).
Ave. D & Chestnut:
Next Tuesday the Water Department will exercise several existing valves on Sycamore to confirm their functionality.
Friday (8/30) plan on connecting multiple fire services to UNT buildings if chlorination results are confirmed prior.
Houston Place (Bradley to Thomas):
Last Week - Lime stabilization continued, and fine grade elevations finalized.
Monday (8/26) Will place the first lift of asphalt. Concrete activities to follow.
Houston Place (Marietta to Bradley):
Utility work demobilized and earthwork began locate activities ahead of asphalt and concrete demolition for next week.
Ave C (Eagle to Highland):
Last Week - Concrete removals continued as well as rough grading.
Next Week - Grading efforts will continue with lime treatment scheduled for the first week of September.
Bernard Mid-South/Collins (Bernard from Fanin to Greenlee, Collins from Bernard to Ave A):
Utiltity Work continues moving south on Bernard installing new sewer main and manholes. As work continues south to Greenlee next week, Traffic Control devices will be installed from Greenlee to Lindsay.
On Collins the sewer installation continued, nearing completion. Work on the new water main will begin next week and continue throughout the next couple weeks.
Marietta (Scripture to Oak):
Last Week - Utility Contractor mobilized to this roadway from Houston. Layout and saw cutting for the new sewer main were completed.
Monday (8/26) Traffic Control devices will be placed on Scripture so a new manhole can be installed, and piping will start at this intersection and move south down the block through the week.