Pecan Creek 4 - Phase 3 and 4

Share Pecan Creek 4 - Phase 3 and 4 on Facebook Share Pecan Creek 4 - Phase 3 and 4 on Twitter Share Pecan Creek 4 - Phase 3 and 4 on Linkedin Email Pecan Creek 4 - Phase 3 and 4 link

Overview:

Pecan Creek-4 Phases 3 and 4 Drainage Improvements project which includes:

  • 2,700 linear feet of reinforced concrete box
  • 2,300 linear feet of waterline relocation and lowering
  • 1,700 linear feet of sanitary sewer line relocation and adjustment
  • pavement repair from West Prairie Street to the beginning of the open channel near the intersection of West Mulberry Street and Bernard Street;

Overview:

Pecan Creek-4 Phases 3 and 4 Drainage Improvements project which includes:

  • 2,700 linear feet of reinforced concrete box
  • 2,300 linear feet of waterline relocation and lowering
  • 1,700 linear feet of sanitary sewer line relocation and adjustment
  • pavement repair from West Prairie Street to the beginning of the open channel near the intersection of West Mulberry Street and Bernard Street;
  • News Feed - April

    Share News Feed - April on Facebook Share News Feed - April on Twitter Share News Feed - April on Linkedin Email News Feed - April link

    We are actively progressing towards finalizing our project design, with our current completion at 95%. Our consultant is collaborating closely with the Real Estate team to acquire the necessary parcels required for the successful execution of the project. We appreciate your continued support as we work to bring this project to life.

  • News Feed - March

    Share News Feed - March on Facebook Share News Feed - March on Twitter Share News Feed - March on Linkedin Email News Feed - March link

    City Staff were authorized by the City Council to proceed with seeking eminent domain to purchase property required for the project. The application of eminent domain enables the city to obtain private property for public use in return for offering reasonable compensation for the property.

    With this approval, City Staff/ Engineering Staff also went through the 95% design plans of the project with detailed specifications and engineering designs. We have already begun preparing to respond to comments and feedback from the review process to prepare necessary adjustments before finalizing the plans. The design team is working diligently on these changes to present the plans for formal approval and construction.

  • News Feed - February

    Share News Feed - February on Facebook Share News Feed - February on Twitter Share News Feed - February on Linkedin Email News Feed - February link

    We are pleased to report that the 95% plan set have successfully undergone the Quality Assurance/Quality Control (QA/QC) process. Concurrently our Right of Way (ROW) team is diligently preparing for the acquisition of the necessary easements. This phase is critical, as securing these easements will facilitate the smooth progression of our project and ensure that we have legal access to the land required for construction and operations.

  • News Feed - January

    Share News Feed - January on Facebook Share News Feed - January on Twitter Share News Feed - January on Linkedin Email News Feed - January link

    .The surveys and title work for all essential easements required for the project have been completed. The Real Estate Department of the City of Denton is now in the process of preparing the necessary documents to present to the City Council. This will provide the city with the authority to make offers on the properties needed for the project.

  • News Feed - December

    Share News Feed - December on Facebook Share News Feed - December on Twitter Share News Feed - December on Linkedin Email News Feed - December link

    The City of Denton Internal Real Estate department is currently finalizing the necessary paperwork to submit to the City Council for approval of key land acquisitions needed for the project. Meanwhile, the project design phase is ongoing.

  • News Feed - November

    Share News Feed - November on Facebook Share News Feed - November on Twitter Share News Feed - November on Linkedin Email News Feed - November link

    Pinnacle and the City of Denton Internal Real Estate are currently finalizing all required documentation to present to the City Council for approval of key land acquisitions necessary for the project. Design work for the project is ongoing.

  • News Feed - October

    Share News Feed - October on Facebook Share News Feed - October on Twitter Share News Feed - October on Linkedin Email News Feed - October link

    Pinnacle has distributed introductory letters to all properties affected by the project. The project is currently advancing through the design phase.

  • News Feed - September

    Share News Feed - September on Facebook Share News Feed - September on Twitter Share News Feed - September on Linkedin Email News Feed - September link

    The topographic survey and Subsurface Utility Engineering (SUE) activities have been successfully completed, providing a solid foundation for the next phases of the project. The Third Party Real Estate team is currently working on processing the necessary Right of Way and easements, which are crucial for project progression. Meanwhile, the design work is advancing and is approximately 95% complete. As these critical elements come together, attention will soon turn to finalizing the remaining design details and addressing any outstanding issues related to property acquisition and coordination.

  • News Feed - August

    Share News Feed - August on Facebook Share News Feed - August on Twitter Share News Feed - August on Linkedin Email News Feed - August link

    The project is progressing well, with the topographic survey nearing completion and Subsurface Utility Engineering (SUE) activities continuing. Temporary and permanent easements have been forwarded to the third-party Right of Way/Real Estate consultant for processing. The next significant milestone for the design project is scheduled for the last week of November. This timeline marks a critical point in the project, where progress will be reviewed, and further steps will be planned based on the outcomes.

  • News Feed - July

    Share News Feed - July on Facebook Share News Feed - July on Twitter Share News Feed - July on Linkedin Email News Feed - July link

    The project is advancing well, with the design phase nearly complete at 95% to incorporate the additional scope. Concurrently, Right of Way services are actively securing the necessary land required for the project's progression