Ray Roberts Water Treatment Plant Capacity Re-rate and Performance Improvements

Share Ray Roberts Water Treatment Plant Capacity Re-rate and Performance Improvements on Facebook Share Ray Roberts Water Treatment Plant Capacity Re-rate and Performance Improvements on Twitter Share Ray Roberts Water Treatment Plant Capacity Re-rate and Performance Improvements on Linkedin Email Ray Roberts Water Treatment Plant Capacity Re-rate and Performance Improvements link

Welcome to our page! We're thrilled to have you join us on this journey and eagerly anticipate sharing exciting updates as our project unfolds. Water, the lifeblood of our community, holds a special place in our hearts at Denton Water Utilities. It's our unwavering commitment to safeguarding this precious resource for today and the generations to come.

At the heart of our endeavor lies the Lake Ray Roberts Water Treatment Plant, a vital hub in our mission for water security. Since its inception in 2002, this facility has served us well but, like all things, it's time for an upgrade. Our vision? To not just maintain, but to enhance its capabilities, ensuring it stands resilient against the test of time and the demands of a growing populace.

This ambitious project encompasses a comprehensive overhaul, from enhancing chemical containment systems to optimizing pre-ozone contactors and sedimentation processes. We're leaving no stone unturned, with improvements spanning across intermediate ozone contactors, filter valves, transfer pump stations, and more. Moreover, we're modernizing our infrastructure to streamline operations, with upgrades to ammonia injection sites, ozone facilities, and liquid chemical systems. It is expected that this project will increase the current 20 Million Gallons a Day (MDG) treatment capacity by an additional 6 -10 MGD due to improved filter performance.

As we embark on this transformative journey, we're excited to announce the commencement of our project in the summer of 2024, with a targeted completion in the fourth quarter of 2028. Join us as we set the stage for a brighter, more sustainable future for Denton and beyond.

Welcome to our page! We're thrilled to have you join us on this journey and eagerly anticipate sharing exciting updates as our project unfolds. Water, the lifeblood of our community, holds a special place in our hearts at Denton Water Utilities. It's our unwavering commitment to safeguarding this precious resource for today and the generations to come.

At the heart of our endeavor lies the Lake Ray Roberts Water Treatment Plant, a vital hub in our mission for water security. Since its inception in 2002, this facility has served us well but, like all things, it's time for an upgrade. Our vision? To not just maintain, but to enhance its capabilities, ensuring it stands resilient against the test of time and the demands of a growing populace.

This ambitious project encompasses a comprehensive overhaul, from enhancing chemical containment systems to optimizing pre-ozone contactors and sedimentation processes. We're leaving no stone unturned, with improvements spanning across intermediate ozone contactors, filter valves, transfer pump stations, and more. Moreover, we're modernizing our infrastructure to streamline operations, with upgrades to ammonia injection sites, ozone facilities, and liquid chemical systems. It is expected that this project will increase the current 20 Million Gallons a Day (MDG) treatment capacity by an additional 6 -10 MGD due to improved filter performance.

As we embark on this transformative journey, we're excited to announce the commencement of our project in the summer of 2024, with a targeted completion in the fourth quarter of 2028. Join us as we set the stage for a brighter, more sustainable future for Denton and beyond.

  • Plant Back to 100%

    Share Plant Back to 100% on Facebook Share Plant Back to 100% on Twitter Share Plant Back to 100% on Linkedin Email Plant Back to 100% link

    We’re excited to announce that the plant is back online and running at full capacity! Here’s the latest scoop on our progress:

    • Chain of Flight Systems: Three out of four systems have been swapped out with shiny new ones, boosting efficiency and reliability.

    • Sand Filters: All filters have fresh media, ready to keep things crystal clear.

    • Chemical Containment Pit: We’re wrapping up work here, ensuring everything is safe and secure.

    • Ground Storage Tank: It’s up and wound tight! Finishing touches kick off next week.

    • Variable Frequency Drive Building: The structure is complete, and we’re putting the final polish on the interior.

  • Project Update and Upcoming Plant Shut Down

    Share Project Update and Upcoming Plant Shut Down on Facebook Share Project Update and Upcoming Plant Shut Down on Twitter Share Project Update and Upcoming Plant Shut Down on Linkedin Email Project Update and Upcoming Plant Shut Down link

    Denton Water Utilities is excited to share a construction update for our Ray Roberts Water Treatment Plant Re-Rate Project!

    The Ray Roberts Treatment Plant, which is currently able to treat 20 Million Gallons of water per Day (MGD), will be taken offline from March 3rd through March 14th for upgrades and improvements to existing plant infrastructure. This work will make significant strides towards the additional 6 MGD treatment capacity we will have upon project completion in 2027.

    To make these upgrades, the Ray Roberts plant will be completely off-line from March 3rd through March 14th. There will be no impact to our customers as demands in March average around 18 MGD, and the Lewisville Treatment Plant has a 30 MGD capacity.


    The most recently completed construction while the plant has remained in service is as follows:

    The foundation has been poured and is curing at the High Service Pump Station. Pump pre-removal testing has been completed at the High Service Pump Station. Coating at the chemical containment pit has been completed. Piping has been installed at the Ground Storage Tank and the foundation is being finished out. Filter media and underlayment caps have been replaced on filters 1 through 4 and they have been returned to service. Archer Western is now working on doing the same for updates on filters 7 and 8.

  • Construction Update: Progress Report

    Share Construction Update: Progress Report on Facebook Share Construction Update: Progress Report on Twitter Share Construction Update: Progress Report on Linkedin Email Construction Update: Progress Report link
    supporting image

    The project is progressing according to schedule with several key milestones achieved. The installation of the main drain sump line nears completion, marking a significant advancement in this critical aspect of the project.

    Furthermore, the application of a protective coating at the Chemical Containment Pit has been successfully completed. At the Ground Storage Tank (GST) site, excavation and installation of essential piping infrastructure are currently underway.

    Finally, to enhance the overall system efficiency, the filter media within Filters 3 and 4 is undergoing a planned replacement. These concurrent activities demonstrate the project's commitment to timely execution and adherence to the established timeline.

  • Lots of Work Underway

    Share Lots of Work Underway on Facebook Share Lots of Work Underway on Twitter Share Lots of Work Underway on Linkedin Email Lots of Work Underway link
    supporting image

    Our team has made substantial progress on various aspects of the project. The chemical containment pit's foundation, walls, and piers are now complete. The ground storage tank foundation is ready for the next phase, with excavation, backfilling, and mud slab pouring finished. Additionally, hundreds of feet of duct bank have been installed for the electrical system. As we move into next week, we'll begin drilling piers for the Variable Frequency Drive building.

  • Getting Started

    Share Getting Started on Facebook Share Getting Started on Twitter Share Getting Started on Linkedin Email Getting Started link

    The laydown yard has been successfully set up, featuring office trailers to accommodate contractor staff, conex boxes for secure materials and tool storage, and flexbase to ensure a clean and safe working environment. The electrical subcontractor has commenced preliminary tasks, while Archer Western has been diligently conducting surveys to prepare for the upcoming intensive work phase.

    In parallel, demolition activities and necessary bypasses for the construction of the new chemical containment pit are actively underway. We’ve also seen multiple visits from suppliers, allowing us to fine-tune our parts orders and strategically manage high lead-time items to minimize delays.

  • Mobilization Begins

    Share Mobilization Begins on Facebook Share Mobilization Begins on Twitter Share Mobilization Begins on Linkedin Email Mobilization Begins link

    Progress is steadily advancing on the Ray Roberts Treatment Plant re-rate project. We recently held a preconstruction meeting that brought together Plant Management, the City of Denton Project Management team, Archer Western Construction Contractors, and Freese & Nichols Engineering team. With surveying and the rollout of the laydown yard now underway, Archer Western and CF Electric have begun mobilizing materials onto the site.

  • How do we treat the raw water coming from Lake Ray Roberts?

    Share How do we treat the raw water coming from Lake Ray Roberts? on Facebook Share How do we treat the raw water coming from Lake Ray Roberts? on Twitter Share How do we treat the raw water coming from Lake Ray Roberts? on Linkedin Email How do we treat the raw water coming from Lake Ray Roberts? link
    supporting image

    Surface Water Disinfection Process in a Nutshell

    Ensuring safe drinking water from surface sources involves a complex, multi-step process utilizing advanced technologies and substantial resources.

    1. Coagulation: Water treatment begins with coagulation, where coagulants like aluminum sulfate, ferric chloride, and organic polymers are rapidly mixed into the water. This process alters the electrical charges around suspended particles, causing them to attract and form larger clumps called flocs.
    2. Flocculation: The water is gently agitated to encourage these flocs to collide, stick together, and trap other suspended particles, forming even larger, heavier particles.
    3. Sedimentation: The flocculated water moves slowly through a basin or tank, allowing the heavy particles to settle at the bottom for removal.
    4. Filtration: The water then passes through a filter made of sand, coal particles, or similar materials, which removes finer particles like silt and some pathogens. This step further reduces turbidity, resulting in crystal-clear water.
    5. Carbon Adsorption: Activated carbon may be used to remove chemical contaminants. These contaminants adhere to the surface of the carbon, effectively removing them from the water.
    6. Disinfection: Ozone is added to the water to destroy harmful germs such as bacteria, viruses, parasites, and other organisms. A residual amount of chlorine disinfectant is maintained in the water to continue killing pathogens as the water travels through pipelines to consumers.
    7. Aeration: If necessary, air is mixed with water to remove undesirable amounts of iron and manganese, which remain in solution in the absence of oxygen. Aeration improves the water's color, taste, and odor.
    8. Fluoridation: Fluoride is added to reduce tooth decay.
    9. Storage: Treated water is stored in a clear well ready to be pumped to your tap for consumption.

    Each of these steps ensures that surface water is thoroughly treated and safe for consumption by the time it reaches the tap.