Getting Started

The laydown yard has been successfully set up, featuring office trailers to accommodate contractor staff, conex boxes for secure materials and tool storage, and flexbase to ensure a clean and safe working environment. The electrical subcontractor has commenced preliminary tasks, while Archer Western has been diligently conducting surveys to prepare for the upcoming intensive work phase.

In parallel, demolition activities and necessary bypasses for the construction of the new chemical containment pit are actively underway. We’ve also seen multiple visits from suppliers, allowing us to fine-tune our parts orders and strategically manage high lead-time items to minimize delays.