News Feed - April

After material exchange and approval, work has begun for the Robinwood Reconstruction project. Contractor is in the process of Mixing the cement stabilizer into the subgrade for Robinwood. Afterward yielding passing density reports the first lift of asphalt will be laid before Curb, Gutter, and Drive approaches work will begin.