Robinwood Reconstruction

Share Robinwood Reconstruction on Facebook Share Robinwood Reconstruction on Twitter Share Robinwood Reconstruction on Linkedin Email Robinwood Reconstruction link

This project consists of a full-depth road reconstruction of the following street segments:

  • Robinwood Ln
  • Clover Ln
  • Live Oak St
  • Shadywood St
  • Mistywood Ln

This includes subgrade stabilization, asphalt paving, concrete curb and gutter, and (Driveway replacement if necessary). The project will adhere to a holistic approach aimed at replacing the roadway from the Internal and Franchise Utility upgrades.




This project consists of a full-depth road reconstruction of the following street segments:

  • Robinwood Ln
  • Clover Ln
  • Live Oak St
  • Shadywood St
  • Mistywood Ln

This includes subgrade stabilization, asphalt paving, concrete curb and gutter, and (Driveway replacement if necessary). The project will adhere to a holistic approach aimed at replacing the roadway from the Internal and Franchise Utility upgrades.




  • News Feed - April

    Share News Feed - April on Facebook Share News Feed - April on Twitter Share News Feed - April on Linkedin Email News Feed - April link

    After material exchange and approval, work has begun for the Robinwood Reconstruction project. Contractor is in the process of Mixing the cement stabilizer into the subgrade for Robinwood. Afterward yielding passing density reports the first lift of asphalt will be laid before Curb, Gutter, and Drive approaches work will begin.

  • News Feed - March

    Share News Feed - March on Facebook Share News Feed - March on Twitter Share News Feed - March on Linkedin Email News Feed - March link

    The groundwork for the project has been temporarily paused as a result of a change order related to materials, necessitated by unforeseen site conditions.

    Despite the pause in major groundwork activities, the contractor remains committed to ensuring the project site is safe and accessible. They will conduct on-site visits to perform necessary repairs and maintenance, ensuring that the surface remains traversable for both workers and any necessary equipment.

  • News Feed - February

    Share News Feed - February on Facebook Share News Feed - February on Twitter Share News Feed - February on Linkedin Email News Feed - February link

    The City of Denton contractor is currently on site and actively engaged in the installation of curb and gutter systems, as well as drive approaches throughout the project area. In tandem with these efforts, milling and subgrade stabilization operations are progressing throughout Phase 2 of the project. Additionally, the project team is also focused on the removal and replacement of stormwater inlets.

  • News Feed - January

    Share News Feed - January on Facebook Share News Feed - January on Twitter Share News Feed - January on Linkedin Email News Feed - January link

    Texasbit is scheduled to remobilize on January 6 to commence demolition work for the first phase and to prepare for the upcoming dirt work. Additionally, their subcontractors will begin work on the drainage section of phase 3 at the same time.

  • News Feed - December

    Share News Feed - December on Facebook Share News Feed - December on Twitter Share News Feed - December on Linkedin Email News Feed - December link

    The Notice to Proceed has been issued, signaling the official start of the construction project. Work is scheduled to commence during the first week of December.

  • News Feed - November

    Share News Feed - November on Facebook Share News Feed - November on Twitter Share News Feed - November on Linkedin Email News Feed - November link

    TexasBit is currently in the process of finalizing all necessary project submissions before initiating the project.

  • News Feed - October

    Share News Feed - October on Facebook Share News Feed - October on Twitter Share News Feed - October on Linkedin Email News Feed - October link

    A preconstruction meeting has been held. The contractor is currently securing contracts with subcontractors. A Notice to Proceed will be issued once all internal requirements have been fulfilled

  • News Feed - September

    Share News Feed - September on Facebook Share News Feed - September on Twitter Share News Feed - September on Linkedin Email News Feed - September link

    The contractor for the Robinwood Reconstruction project has been selected, marking a significant step forward. Before issuing the Notice to Proceed, the project must undergo a review and approval process with both the Public Utility Board (PUB) and the City Council. This step is crucial to ensure all regulatory and community considerations are addressed before formal project initiation.

  • News Feed - August

    Share News Feed - August on Facebook Share News Feed - August on Twitter Share News Feed - August on Linkedin Email News Feed - August link

    The project is transitioning from bid evaluation to the final phases of contractor selection and contract execution. The evaluation of bids is complete, and the next steps involve selecting the most suitable contractor based on the evaluation results, finalizing and awarding the contract, and obtaining approvals from the Public Utility Board and City Council. Once these approvals are secured, the Notice to Proceed will be issued to the selected contractor, officially commencing the project. This process ensures that all necessary approvals and preparations are in place to facilitate a smooth start to the project.

  • News Feed - July

    Share News Feed - July on Facebook Share News Feed - July on Twitter Share News Feed - July on Linkedin Email News Feed - July link

    The project has now entered the pre-bid/Bid phase. This step is crucial in the project development. It marks the transition from planning to the possibility of execution, where City approved potential contractors of service providers get the opportunity to propose their plans and costs to be evaluated for selection.