Robinwood Reconstruction

Share Robinwood Reconstruction on Facebook Share Robinwood Reconstruction on Twitter Share Robinwood Reconstruction on Linkedin Email Robinwood Reconstruction link

This project consists of a full-depth road reconstruction of the following street segments:

  • Robinwood Ln
  • Clover Ln
  • Live Oak St
  • Shadywood St
  • Mistywood Ln

This includes subgrade stabilization, asphalt paving, concrete curb and gutter, and (Driveway replacement if necessary). The project will adhere to a holistic approach aimed at replacing the roadway from the Internal and Franchise Utility upgrades.




This project consists of a full-depth road reconstruction of the following street segments:

  • Robinwood Ln
  • Clover Ln
  • Live Oak St
  • Shadywood St
  • Mistywood Ln

This includes subgrade stabilization, asphalt paving, concrete curb and gutter, and (Driveway replacement if necessary). The project will adhere to a holistic approach aimed at replacing the roadway from the Internal and Franchise Utility upgrades.




  • News Feed - June

    Share News Feed - June on Facebook Share News Feed - June on Twitter Share News Feed - June on Linkedin Email News Feed - June link

    The completion of design plans and the uploading of Seal, Project Manual, and Bid Quantity information to the City of Denton's Solicitation Review Committee (SRC) marks a significant milestone in the project development process. This action facilitates the advertisement phase, allowing contractors to submit bids for the upcoming work. It is an essential phase in the sequence of steps leading to the official commencement of construction, ensuring that all necessary pre-construction requirements and reviews are met in accordance with the city's established guidelines.

  • News Feed- May

    Share News Feed- May on Facebook Share News Feed- May on Twitter Share News Feed- May on Linkedin Email News Feed- May link

    Progressing steadily, 90% of the design plans have been produced and are slated for Internal review. This review process will make sure the design meets the required standards and specifications before Final plans are produced.

  • News Feed - April

    Share News Feed - April on Facebook Share News Feed - April on Twitter Share News Feed - April on Linkedin Email News Feed - April link

    Progressing steadily, 60% of the design plans have been produced and are slated for a thorough review. This review process is crucial to ensure that all aspects of the design meet the required standards and specifications before moving on to the next phase. It's an essential step in maintaining the integrity and quality of the project, setting the stage for the subsequent rounds of reviews and refinements.

  • News Feed - March

    Share News Feed - March on Facebook Share News Feed - March on Twitter Share News Feed - March on Linkedin Email News Feed - March link

    30% Design published and submitted for Internal Review. 60% in progress.

  • News Feed - February

    Share News Feed - February on Facebook Share News Feed - February on Twitter Share News Feed - February on Linkedin Email News Feed - February link

    Survey of Robinwood and adjacent streets has concluded. 30% design of the project is currently underway.

  • News Feed - January

    Share News Feed - January on Facebook Share News Feed - January on Twitter Share News Feed - January on Linkedin Email News Feed - January link

    Project Funds have been processed and allocated to the correct accounts. CIP Project Manager Sheldon Gatewood has been assigned the Robinwood Reconstruction project. Design inquire is underway.