April Construction Update
Southeast Denton Package B - Work is progressing steadily on Southeast Denton Package B as there are three main operations currently ongoing throughout the SED-B construction limits.
Utility crews continue the installation of domestic water and sanitary sewer lines from W Highland St (S Elm St to Carroll Blvd), Pierce St (Stroud St to W Prairie St), Austin St, W Mulberry St (Austin to Industrial), W Mulberry St (Industrial St to Bell St), and W Prairie St ( Bell to DCTA Rail).
Earthwork crews are preparing the roadways for asphalt paving along Maple St (Carroll Blvd to S Elm St), Myrtle St (Eagle Dr to Maple), Myrtle St (Maple to W Highland), E Mulberry St (Crawford St to Wood St), W Mulberry (Austin to Industrial St).
Concrete crews continue flatwork for new sidewalks, curb and gutter, and pavement along Maple St (Carroll Blvd to S Elm St), Myrtle St (Maple to Eagle Dr).