February Construction Update

Southeast Denton Package A - Utility crews are working on Johnson st and Mill st with installation of the wastewater lines. Paving crews are working on Wye st and Allen st. Paving should begin 2/16 and be complete by 2/24 on Allen and Wye. Project is still on schedule to be complete summer of 2023.

Southeast Denton Package B – Utility crews have begun asphalt milling and excavation for the installation of domestic water and sanitary sewer lines on Bailey St, S Bradshaw St (E Prairie St to Wilson St), E Highland St (S Locust St to Wainwright St), and Smith St – Phase 1 (Dallas Dr to Johnson St). Earthwork and flatwork concrete crews plan to follow in the coming weeks.

  • Upcoming Streets (tentative start date 3/6/23): Maddox St, Avenue S, and Smith St – Phase 2 (Dallas Dr to Hill St)


Share February Construction Update on Facebook Share February Construction Update on Twitter Share February Construction Update on Linkedin Email February Construction Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>