February Construction Update
Southeast Denton Package A - Utility crews are working on Johnson st and Mill st with installation of the wastewater lines. Paving crews are working on Wye st and Allen st. Paving should begin 2/16 and be complete by 2/24 on Allen and Wye. Project is still on schedule to be complete summer of 2023.
Southeast Denton Package B – Utility crews have begun asphalt milling and excavation for the installation of domestic water and sanitary sewer lines on Bailey St, S Bradshaw St (E Prairie St to Wilson St), E Highland St (S Locust St to Wainwright St), and Smith St – Phase 1 (Dallas Dr to Johnson St). Earthwork and flatwork concrete crews plan to follow in the coming weeks.
- Upcoming Streets (tentative start date 3/6/23): Maddox St, Avenue S, and Smith St – Phase 2 (Dallas Dr to Hill St)
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends