January Construction Update

Southeast Denton Package A - Utility crews are completing water/wastewater installation on Wye and Allen streets. Crews will be moving to Mill street and Industrial street for utility installation. Flat work and paving crews will begin on Wye and Allen once utilities crews mobilize out.


Southeast Denton Package B - Contractor has mobilized in and will begin utility installation on Jan 30. First streets will be Smith St at Dallas Dr, E Highland at Locust, Bailey St at Wilson st, and Bradshaw St between Sycamore and Wilson. Paving crews will follow utility installation crews in each segment.