Crews have completed the utility installation on Morse Street, Jackson Street, Hill Alley Street, and Martin Street. Testing procedures will begin the week of September 12th followed by roadway demo and stabilization. Paving is anticipated to start the first week of October, pending weather. Utility crews have moved to Robertson Street to be followed by Cook Street. Southeast Denton Package A is still on schedule to be complete by summer of 2023.