The City owned sewer line that is in conflict with the proposed bridge is being relocated in advance of the TxDOT project beginning. This standalone project has been designed, advertised, and awarded to a local contractor. The City is holding a Pre-Construction meeting with the contractor the second week of April in anticipation for a construction start date the first or second week of May. Once this relocation is completed, the area will be free of all obstacles in order that TxDOT can advertise for the bridge construction project.