September Update

We are well underway! we have installed almost half of the proposed drainage system and are soon going to be gearing up for the waterline installation near the new High School. Stay tuned for more updates and please feel free to ask all your questions at Ask the Project Manager

Share September Update on Facebook Share September Update on Twitter Share September Update on Linkedin Email September Update link