Westgate Drive Improvement Project

Share Westgate Drive Improvement Project on Facebook Share Westgate Drive Improvement Project on Twitter Share Westgate Drive Improvement Project on Linkedin Email Westgate Drive Improvement Project link

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

Ask the Project Manager

Submit your questions on the Westgate Improvements project to the Construction Projects Manager here. We will respond to your question within three (3) business days.
loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Are there 60% plans that can be shared with residents? I would love to see the potential layout of streets and sidewalks. on Facebook Share Are there 60% plans that can be shared with residents? I would love to see the potential layout of streets and sidewalks. on Twitter Share Are there 60% plans that can be shared with residents? I would love to see the potential layout of streets and sidewalks. on Linkedin Email Are there 60% plans that can be shared with residents? I would love to see the potential layout of streets and sidewalks. link

    Are there 60% plans that can be shared with residents? I would love to see the potential layout of streets and sidewalks.

    Dac1825 asked over 1 year ago

    During the design phase, the 60% plan set is release to City Staff as a preliminary plan set and is only used for review and comment.  At this time, the 60% plan set cannot be shared with residents.  In order to best respond to your question, the Consultant Engineer will be asked to prepare an exhibit showcasing the major streets of East/West Westgate Drive, North/South Westgate Drive and Windsor Drive and how they intersect with the smaller residential streets along the project area.  As soon as the exhibit is ready it will be posted to the project within the Discuss Denton website. Thank you for your interest concerning the City of Denton Westgate Drive Improvement Project. 