Westgate Drive Improvement Project

Share Westgate Drive Improvement Project on Facebook Share Westgate Drive Improvement Project on Twitter Share Westgate Drive Improvement Project on Linkedin Email Westgate Drive Improvement Project link
Reinforced Concrete Paving

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

  • Phase 1 December Update

    Share Phase 1 December Update on Facebook Share Phase 1 December Update on Twitter Share Phase 1 December Update on Linkedin Email Phase 1 December Update link

    Whew that went fast! We have 99% of the east and westbound paving installed, and all north and southbound concrete paving as well. The contractor is currently working on installing the streetlights throughout the project. Once these are installed, we will be making preparations to hopefully open an east and westbound lane by the end of the month. Although we will not be complete with the project, our goal is to allow local traffic to begin utilizing the improvements for access and convenience. Stay tuned for more updates and please feel free to ask all your questions at Ask the Project Manager


  • Phase 1 November Update

    Share Phase 1 November Update on Facebook Share Phase 1 November Update on Twitter Share Phase 1 November Update on Linkedin Email Phase 1 November Update link

    Boom! The waterline is completed and tied into the existing system. All west and eastbound paving is installed, with the exception of one small piece on the eastbound side of Westgate Dr. Additionally, we still have the southbound lane to pave and then all paving will be complete. Stay tuned for more updates and please feel free to ask all your questions at Ask the Project Manager


  • Phase 1 October Update

    Share Phase 1 October Update on Facebook Share Phase 1 October Update on Twitter Share Phase 1 October Update on Linkedin Email Phase 1 October Update link

    And just like that, we have installed the majority of the drainage system! We have also begun installing the proposed waterline near the high school. Additionally, we have placed a substantial portion of the concrete paving on the south side of the road. Stay tuned for more updates and please feel free to ask all your questions at Ask the Project Manager

  • Phase 1 September Update

    Share Phase 1 September Update on Facebook Share Phase 1 September Update on Twitter Share Phase 1 September Update on Linkedin Email Phase 1 September Update link

    We are well underway! we have installed almost half of the proposed drainage system and are soon going to be gearing up for the waterline installation near the new High School. Stay tuned for more updates and please feel free to ask all your questions at Ask the Project Manager

  • Phase 1 August Update

    Share Phase 1 August Update on Facebook Share Phase 1 August Update on Twitter Share Phase 1 August Update on Linkedin Email Phase 1 August Update link

    It's official... This project is underway! The contractor has mobilized equipment and begun clearing out all vegetation and debris. In the coming weeks you will see the area start to take shape with them balancing the grade in preparation for utility work. DME has been actively working to relocate some of their facilities that were found to be in conflict with the proposed improvements.

  • Phase 1 July Update

    Share Phase 1 July Update on Facebook Share Phase 1 July Update on Twitter Share Phase 1 July Update on Linkedin Email Phase 1 July Update link

    This contract was awarded to McMahon Contracting LLP on June 17th, 2025. The Pre-Construction meeting is scheduled for the week of July 7th. The Notice to Proceed will be issued to McMahon within the next two weeks for them to begin construction which is anticipated to be substantially completed near March of 2026.

  • Phase 2 - Right-of-way Acquistion is on hold

    Share Phase 2 - Right-of-way Acquistion is on hold on Facebook Share Phase 2 - Right-of-way Acquistion is on hold on Twitter Share Phase 2 - Right-of-way Acquistion is on hold on Linkedin Email Phase 2 - Right-of-way Acquistion is on hold link

    Right-of-way acquisition for Phase 2 is on hold until further notice. Once again, the project limits for Phase 2 are from Barrow Drive to Windsor Drive and then from Westgate Drive to the I35 Access Road.

  • Phase 2 - Project Limit Reminder

    Share Phase 2 - Project Limit Reminder on Facebook Share Phase 2 - Project Limit Reminder on Twitter Share Phase 2 - Project Limit Reminder on Linkedin Email Phase 2 - Project Limit Reminder link

    The Westgate Drive Improvement Project has been split into two phases. Phase 2 project limits are from Barrow Drive to Windsor Drive along Westgate Drive. And then Windsor Drive from Westgate Drive to the I-35 access road.

  • Phase 1 April Update

    Share Phase 1 April Update on Facebook Share Phase 1 April Update on Twitter Share Phase 1 April Update on Linkedin Email Phase 1 April Update link

    Phase 1 of this project is currently open for bidding, with the submission deadline set for April 9th. After receiving the bids, the City will conduct a thorough review, select a contractor, and award the contract. Once awarded, a Pre-Construction meeting will be held with the chosen contractor to finalize details and determine the construction start date.

  • Phase 2 - Right-of-way Acquisition

    Share Phase 2 - Right-of-way Acquisition on Facebook Share Phase 2 - Right-of-way Acquisition on Twitter Share Phase 2 - Right-of-way Acquisition on Linkedin Email Phase 2 - Right-of-way Acquisition link

    Right-of-way acquisition continues for Westgate Drive Phase 2 Project. The City must acquire permanent right-of-way, temporary construction easements, drainage and slope easements. Initial offer letters are being prepared by the Consultant Engineer.

Page last updated: 08 Dec 2025, 08:23 AM