Dry Fork Sanitary Sewer

Share Dry Fork Sanitary Sewer on Facebook Share Dry Fork Sanitary Sewer on Twitter Share Dry Fork Sanitary Sewer on Linkedin Email Dry Fork Sanitary Sewer link

Installation of approximately 4,600 linear feet of 24-inch sewer main north of Highland Park at Bonnie Brae west to I-35W Frontage Road and south to Corbin Road will provide wastewater services to Southwest Denton Area residents.

Project Status


Project Location

Installation of approximately 4,600 linear feet of 24-inch sewer main north of Highland Park at Bonnie Brae west to I-35W Frontage Road and south to Corbin Road will provide wastewater services to Southwest Denton Area residents.

Project Status


Project Location

  • Update for Estimated Project Timeline

    Share Update for Estimated Project Timeline on Facebook Share Update for Estimated Project Timeline on Twitter Share Update for Estimated Project Timeline on Linkedin Email Update for Estimated Project Timeline link
    supporting image

    ESTIMATED SCHEDULE OF PROJECT

    Final Design/Advertise - Q2 2023

    Construction Contract Award - Q3 2023

    Construction - Q3 2023 - Q3 2024

    Project Closeout - Q4 2024

  • Estimated Project Timeline Update

    Share Estimated Project Timeline Update on Facebook Share Estimated Project Timeline Update on Twitter Share Estimated Project Timeline Update on Linkedin Email Estimated Project Timeline Update link
    supporting image

    ESTIMATED SCHEDULE OF PROJECT

    Final Design/Advertise - Q1 2023

    Construction Contract Award - Q2 2023

    Construction - Q3 2023 - Q3 2024

    Project Closeout - Q4 2024

  • Estimated Project Timeline Update

    Share Estimated Project Timeline Update on Facebook Share Estimated Project Timeline Update on Twitter Share Estimated Project Timeline Update on Linkedin Email Estimated Project Timeline Update link
    supporting image

    ESTIMATED SCHEDULE OF PROJECT

    Final Design/Advertised - Q4 2022

    Construction Contract Award - Q2 2023

    Construction - Q2 2023 thru Q2 2024

    Project Closeout - Q3 2024

  • Updated Estimated Project Timeline

    Share Updated Estimated Project Timeline on Facebook Share Updated Estimated Project Timeline on Twitter Share Updated Estimated Project Timeline on Linkedin Email Updated Estimated Project Timeline link
    supporting image

    ESTIMATED SCHEDULE OF PROJECT

    Final Design/Advertised – Q3 2022

    Construction Contract Awarded – Q1 2023

    Construction – Q1 2023 thru Q4 2024

    Project Closeout – Q1 2025

  • Estimated Project Timeline

    Share Estimated Project Timeline on Facebook Share Estimated Project Timeline on Twitter Share Estimated Project Timeline on Linkedin Email Estimated Project Timeline link
    supporting image

    Estimated Design Completion: Quarter 1 of 2022

    Estimated Construction Start: Quarter 4 of 2022

    Estimated Project Completion: Quarter 3 of 2023

Page last updated: 01 Apr 2024, 05:12 AM