Hickory Creek Road Phase 3 Project

Share Hickory Creek Road Phase 3 Project on Facebook Share Hickory Creek Road Phase 3 Project on Twitter Share Hickory Creek Road Phase 3 Project on Linkedin Email Hickory Creek Road Phase 3 Project link

The Hickory Creek Road Phase 3 project is located on Hickory Creek Road from Riverpass Drive to FM-1830. To improve safety and mobility in the area, the project includes the design and construction of a four-lane extension and realignment of Hickory Creek Road from Riverpass Drive to FM-1830, and the construction of a bridge that will span Hickory Creek and remove the safety concern of the 90 degree curve from the current Hickory Creek alignment. This project is part of a larger reconstruction and widening project for Hickory Creek Road with the goal of a continuous four lane divided road

The Hickory Creek Road Phase 3 project is located on Hickory Creek Road from Riverpass Drive to FM-1830. To improve safety and mobility in the area, the project includes the design and construction of a four-lane extension and realignment of Hickory Creek Road from Riverpass Drive to FM-1830, and the construction of a bridge that will span Hickory Creek and remove the safety concern of the 90 degree curve from the current Hickory Creek alignment. This project is part of a larger reconstruction and widening project for Hickory Creek Road with the goal of a continuous four lane divided road along Hickory Creek Road from FM 2499 to FM 1830.

Project Status




  • November 2024 Project Update

    Share November 2024 Project Update on Facebook Share November 2024 Project Update on Twitter Share November 2024 Project Update on Linkedin Email November 2024 Project Update link




    QUICK update - We don't have an exact date when we will RESTART Hickory Creek Road/Bridge Phase 3 but we are continually making progress on the remaining items. For example - you may have noticed work in the area (such as new and removed utility poles). You will also see Atmos gas coming thru with a new line on the east side of the new bridge. Although the new road/bridge work won't be able to start by the close of this year, it's promising to kick off in the early new year. Stay tuned to this page for updates on the actual start date as well as ongoing updates through construction.

  • September Project Update

    Share September Project Update on Facebook Share September Project Update on Twitter Share September Project Update on Linkedin Email September Project Update link

    Thank you all for your patience! I'm the new Project Manager as of August and I know you have been waiting for this project to start and I know it's been a challenge for you. We are actively working behind the scenes to start the project back up. No one intended for this delay. Contractors and Inspectors are happiest in the field and I LOVE getting projects across the finish line. Stay tuned for updates. We're trying get started as soon as possible.

    Tracy

  • August Project Update

    Share August Project Update on Facebook Share August Project Update on Twitter Share August Project Update on Linkedin Email August Project Update link

    The Hickory Creek Road Phase 3 project is currently experiencing a delay in construction due to rail road coordination and the ONCOR distribution line relocation. ONCOR crews have began pole installation and are project to finish this month. City of Denton staff is also coordinating with the railroad to get all railroad requirements required to get the project back going. The current estimated completion for the project is projected for Q4 2026, but we anticipate the bridge to be open in late 2025. Please use caution and observe all work zone signs while in the Hickory Creek RD area. The project has a new City of Denton Project Manager that will be taking the project over moving forward. Her name is Tracy Beck, and if you have any questions or concerns please contact her at Tracy.Beck@cityofdenton.com or by using the ask a project manager link on the Discuss Denton project page.


  • July Project Update

    Share July Project Update on Facebook Share July Project Update on Twitter Share July Project Update on Linkedin Email July Project Update link

    The Hickory Creek Road Phase 3 project is currently experiencing a delay in construction due to rail road coordination and the ONCOR distribution line relocation. ONCOR crews have began project staking and are ready to mobilize in the next two weeks pending no major weather delays. City of Denton staff is also coordinating with the railroad to get all railroad requirements required to get the project back going. Please use caution and observe all work zone signs while in the Hickory Creek RD area. If you have any questions or concerns please contact me at Dustin.Draper@cityofdenton.com or by using the ask a project manager link on the Discuss Denton project page.


  • Hickory Creek Road Phase 3 Project Update

    Share Hickory Creek Road Phase 3 Project Update on Facebook Share Hickory Creek Road Phase 3 Project Update on Twitter Share Hickory Creek Road Phase 3 Project Update on Linkedin Email Hickory Creek Road Phase 3 Project Update link

    The Hickory Creek Road Phase 3 project is currently experiencing a delay in construction due to rail road coordination and the ONCOR distribution line relocation. Over the last month and a half the project area has experienced an abnormally large amount of rain events. This has delayed ONCOR from being able to relocate the distribution line as most areas of the project have been inaccessible due to the rain. ONCOR crews are currently on emergency response with the storms over the last few weeks as well. As soon as the ONCOR crews are off of emergency response the relocation will begin. City of Denton staff is also coordinating with the railroad to get the project on track. Please use caution and observe all work zone signs while in the Hickory Creek RD area. If you have any questions or concerns please contact me at Dustin.Draper@cityofdenton.com or by using the ask a project manager link on the Discuss Denton project page.

  • Monthly Project Update

    Share Monthly Project Update on Facebook Share Monthly Project Update on Twitter Share Monthly Project Update on Linkedin Email Monthly Project Update link

    The Hickory Creek Road Phase 3 Project's bridge abutments are in the settlement phase of the construction. The bridge abutments (or approaches) require a settlement time before they can be built on to ensure that they do not settle after the road is completed. The ONCOR distribution line relocation is scheduled for completion in May and City staff is continuing coordination with the contractor to address any concerns with the temporary pavement section of the existing Hilltop Road. Please remember to observe all construction warning signs and detour routes as the project progress toward the Q2 2025 estimated completion date. WIth the rains we have been experiencing we also ask that you use caution around the project after a rain event, If you have any questions please feel free to reach out to Dustin Draper at Dustin.Draper@cityofdenton.com or by using the ask a Project Manager link on the project page.

  • Monthly Project Update

    Share Monthly Project Update on Facebook Share Monthly Project Update on Twitter Share Monthly Project Update on Linkedin Email Monthly Project Update link

    The Hickory Creek Road Phase 3 Project's bridge abutments are in the settlement phase of the construction. The bridge abutments (or approaches) require a settlement time before they can be built on to ensure that they do not settle after the road is completed. The ONCOR distribution line relocation is scheduled for completion this month and City staff is continuing coordination with the contractor to address citizen concerns with the temporary pavement section of the existing Hilltop Road. Please remember to observe all construction warning signs and detour routes as the project progress toward the Q2 2025 estimated completion date. If you have any questions please feel free to reach out to Dustin Draper at Dustin.Draper@cityofdenton.com(External link)(External link) or by using the ask a Project Manager link on the project page.

  • Monthly Project Update

    Share Monthly Project Update on Facebook Share Monthly Project Update on Twitter Share Monthly Project Update on Linkedin Email Monthly Project Update link

    The Hickory Creek Road Phase 3 Project's bridge abutments are in the settlement phase of the construction. The bridge abutments (or approaches) require a settlement time before they can be built on to ensure that they do not settle after the road is completed. Staff is also still working with ONCOR and Kansas City Southern Railroad to reschedule the relocation of the ONCOR line and will post timelines once they have been confirmed. City staff is also coordinating with the contractor to address citizen concerns with the temporary pavement section of the existing Hilltop Road. Please remember to observe all construction warning signs and detour routes as the project progress toward the Q2 2025 estimated completion date. If you have any questions please feel free to reach out to Dustin Draper at Dustin.Draper@cityofdenton.com(External link) or by using the ask a Project Manager link on the project page.

  • Monthly Project Update

    Share Monthly Project Update on Facebook Share Monthly Project Update on Twitter Share Monthly Project Update on Linkedin Email Monthly Project Update link

    The relocation of the ONCOR line was scheduled to begin in January for the Hickory Creek Rd PH 3 project, but do to the inclement weather conditions and railroad coordination it had to be rescheduled . Staff is working with ONCOR and Kansas City Southern Railroad to reschedule the relocation and will post timelines once they have been confirmed. City staff is also coordinating with the contractor to address citizen concerns with the temporary pavement section of the existing Hilltop Road. Please remember to observe all construction warning signs and detour routes as the project progress toward the Q2 2025 estimated completion date. If you have any questions please feel free to reach out to Dustin Draper at Dustin.Draper@cityofdenton.com or by using the ask a Project Manager link on the project page.

  • Monthly Project Update

    Share Monthly Project Update on Facebook Share Monthly Project Update on Twitter Share Monthly Project Update on Linkedin Email Monthly Project Update link

    The relocation of the ONCOR line is scheduled to begin this month for the Hickory Creek Rd PH 3 project. Please remember to observe all construction warning signs and detour routes as the project progress toward the Q2 2025 estimated completion date. If you have any questions please feel free to reach out to Dustin Draper at Dustin.Draper@cityofdenton.com or by using the ask a Project Manager link on the project page.