McKinney Sidewalks

Share McKinney Sidewalks on Facebook Share McKinney Sidewalks on Twitter Share McKinney Sidewalks on Linkedin Email McKinney Sidewalks link
Construction extents of McKinney Sidewalk Improvements

SCOPE OF WORK:

Construct new and improve accessibility of sidewalk along South side of E. Mckinney Street to provide connectivity from Loop 288 to Audra Ln.

Project Length: Approx. 6500 Linear Feet.



PROJECT PHASE & STATUS




SCOPE OF WORK:

Construct new and improve accessibility of sidewalk along South side of E. Mckinney Street to provide connectivity from Loop 288 to Audra Ln.

Project Length: Approx. 6500 Linear Feet.



PROJECT PHASE & STATUS




  • April Update

    Share April Update on Facebook Share April Update on Twitter Share April Update on Linkedin Email April Update link

    Beginning to work through the necessary easement and Right of Way acquisitions with property owners along this stretch. Approaching a 90% complete plan set to be submitted to the City for review.

  • January 2025

    Share January 2025 on Facebook Share January 2025 on Twitter Share January 2025 on Linkedin Email January 2025 link

    The City has received, reviewed and provided comments for the 30% submittal from the Consultant. The consultant is presently working to incorporate the provided comments to be included in the 60% submittal.

  • November

    Share November on Facebook Share November on Twitter Share November on Linkedin Email November link

    After careful consideration, this project's scope of work has been revised to include a continuous 5-foot-wide sidewalk in lieu of the originally proposed 10' sidewalk along the south side of McKinney St. to help expedite the construction of the sidewalk. A revised 30% plan set is presently under design.

  • September update

    Share September update on Facebook Share September update on Twitter Share September update on Linkedin Email September update link

    The City of Denton has received the 30% design plans, which are currently being reviewed internally. The design consultant will begin working toward the 60% design plans when the review is complete.