2019 Bond Neighborhood 1A

Share 2019 Bond Neighborhood 1A on Facebook Share 2019 Bond Neighborhood 1A on Twitter Share 2019 Bond Neighborhood 1A on Linkedin Email 2019 Bond Neighborhood 1A link

This project consists of full depth reconstruction of 21 street segments within the NBHD-1A project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes limited sidewalk improvements, and street lighting. Following is a summary of key scope items:

  • Street Reconstruction – Approx. 8,000 linear feet
  • Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development
  • Sidewalks – Limited improvements as determined during design development
  • Streetlights – Limited improvements as determined by lighting study




The street segments include Meadow Lane Place, Meadow Lane, Plum Hollow Street, Tanglewood Street, Pheasant Hollow Street, Willow Stone Street, Pear Tree Place, Windbrook St., and Windbrook Court.

STREET SEGMENT

FROM

TO

STREET SEGMENT

FROM

TO

Meadow

Sagewood St

Meadow Lane Pl

Pheasant Hollow

Willow Stone

Brook Hollow E

Meadow

Pheasant Hollow St

Sagewood St

Pheasant Hollow

Plum Hollow

Willow Stone

Meadow

Meadow Lane Pl

Shadow Tr

Plum Hollow

Sagewood

Shadow Tr

Meadow Lane E

Hercules Ln

Meadow Ln

Plum Hollow

Locust N

Pheasant Hollow

Meadow Lane W

Hercules Ln

Meadow Ln

Tanglewood

Locust N

Pheasant Hollow

Pear Tree

Sagewood

Shadow Tr

Tanglewood

Sagewood

Shadow Tr

Pear Tree

Pheasant Hollow

Sagewood

Willow Stone

Sagewood

Shadow Tr

Pheasant Hollow

Meadow

Plum Hollow

Windbrook

Windbrook

North

Pheasant Hollow

Brook Hollow E

Pear Tree Pl

Windbrook

Pheasant Hollow

Windbrook Ct

Pheasant Hollow

Pear Tree Pl

Windbrook

Windbrook

Windbrook Ct

Shadow Tr


Willow Stone

Sagewood

Pheasant Hollow



This project consists of full depth reconstruction of 21 street segments within the NBHD-1A project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes limited sidewalk improvements, and street lighting. Following is a summary of key scope items:

  • Street Reconstruction – Approx. 8,000 linear feet
  • Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development
  • Sidewalks – Limited improvements as determined during design development
  • Streetlights – Limited improvements as determined by lighting study




The street segments include Meadow Lane Place, Meadow Lane, Plum Hollow Street, Tanglewood Street, Pheasant Hollow Street, Willow Stone Street, Pear Tree Place, Windbrook St., and Windbrook Court.

STREET SEGMENT

FROM

TO

STREET SEGMENT

FROM

TO

Meadow

Sagewood St

Meadow Lane Pl

Pheasant Hollow

Willow Stone

Brook Hollow E

Meadow

Pheasant Hollow St

Sagewood St

Pheasant Hollow

Plum Hollow

Willow Stone

Meadow

Meadow Lane Pl

Shadow Tr

Plum Hollow

Sagewood

Shadow Tr

Meadow Lane E

Hercules Ln

Meadow Ln

Plum Hollow

Locust N

Pheasant Hollow

Meadow Lane W

Hercules Ln

Meadow Ln

Tanglewood

Locust N

Pheasant Hollow

Pear Tree

Sagewood

Shadow Tr

Tanglewood

Sagewood

Shadow Tr

Pear Tree

Pheasant Hollow

Sagewood

Willow Stone

Sagewood

Shadow Tr

Pheasant Hollow

Meadow

Plum Hollow

Windbrook

Windbrook

North

Pheasant Hollow

Brook Hollow E

Pear Tree Pl

Windbrook

Pheasant Hollow

Windbrook Ct

Pheasant Hollow

Pear Tree Pl

Windbrook

Windbrook

Windbrook Ct

Shadow Tr


Willow Stone

Sagewood

Pheasant Hollow



  • Project Update

    Share Project Update on Facebook Share Project Update on Twitter Share Project Update on Linkedin Email Project Update link

    Construction will start May 30, 2023 for the Neighborhood 1A Project.

    Expect to see crews in the area along with road closures with changing traffic patterns.

  • Neighborhood 1A Public Meeting for Construction Kickoff

    Share Neighborhood 1A Public Meeting for Construction Kickoff on Facebook Share Neighborhood 1A Public Meeting for Construction Kickoff on Twitter Share Neighborhood 1A Public Meeting for Construction Kickoff on Linkedin Email Neighborhood 1A Public Meeting for Construction Kickoff link

    The Construction Kickoff Public Meeting was held on March 23rd.

    If you were unable to attend the meeting please click on the photo below to watch the recorded presentation.

  • Project Update

    Share Project Update on Facebook Share Project Update on Twitter Share Project Update on Linkedin Email Project Update link

    The City will host a virtual community meeting on 3/23/23 at 6pm. Please click the link in the below update to sign up for the virtual meeting. The contract has been awarded and the contractor will mobilize and start construction once an approved start date is set.

  • Notice of Community Meeting

    Share Notice of Community Meeting on Facebook Share Notice of Community Meeting on Twitter Share Notice of Community Meeting on Linkedin Email Notice of Community Meeting link

    The City of Denton will hold a Virtual Community Meeting at 6pm on Thursday, March 23, regarding street improvements in the Neighborhood 1A area (Cooper Crossing).

    Click Here to sign up for the Virtual Meeting

  • Project Update

    Share Project Update on Facebook Share Project Update on Twitter Share Project Update on Linkedin Email Project Update link

    2019 Street Bond Neighborhood 1A project is on schedule to go to City Council on 2/21/23 to award the project to the Construction Contractor. Once approved, the construction schedule can be finalized including the start and finish date.

  • Project Timeline

    Share Project Timeline on Facebook Share Project Timeline on Twitter Share Project Timeline on Linkedin Email Project Timeline link
    • Final Design Q4 2022
    • Project Bidding Q1 2023
    • Estimated construction contract award and construction start Q2 2023
    • Estimated construction completion Q1 2024