Share November Construction Update on Facebook
Share November Construction Update on Linkedin
Email November Construction Update link
Parkway restoration and sod placement to be completed by December 1.
Project closeout to follow.
Share October Construction Update on Facebook
Share October Construction Update on Linkedin
Email October Construction Update link
Parkway restoration and sod placement underway.
Project nearing final completion
Share September Construction Update on Facebook
Share September Construction Update on Linkedin
Email September Construction Update link
Paving complete on Thunderbird and Colonial.
Parkway restoration and sod placement underway.
Share August Construction Update on Facebook
Share August Construction Update on Linkedin
Email August Construction Update link
Utility installs nearing completion on Thunderbird.
Paving operations have started on Colonial and Thunderbird.
Expect multiple and changing road closures in areas of construction.
Share May Construction Update on Facebook
Share May Construction Update on Linkedin
Email May Construction Update link
Utility installs have completed on Lakewood and set to begin on Thunderbird.
Paving operations have started on Augusta, Greenway and Brook Hollow.
Expect multiple and changing road closures in areas of construction.
Share Project Update for Sector I on Facebook
Share Project Update for Sector I on Linkedin
Email Project Update for Sector I link
Street reconstruction and paving has started on Augusta and Greenway.
Wastewater utility installs nearing completion on Lakewood.
Water utility install on Lakewood nearing completion.
Expect multiple and changing road closures in areas of construction.
Share Construction Update on Facebook
Share Construction Update on Linkedin
Email Construction Update link
Street reconstruction and paving has started on Augusta and Greenway.
Wastewater utility installs nearing completion on Brookhollow and Lakewood.
Water utility install to begin on Lakewood
Expect multiple and changing road closures in areas of construction.
Share Project Update on Facebook
Share Project Update on Linkedin
Email Project Update link
Street reconstruction and paving starting on Augusta and Greenway.
Wastewater utility installs underway on Brookhollow and Lakewood.
Expect multiple and changing road closures in areas of construction.
Share Project Update for Utility Replacements on Facebook
Share Project Update for Utility Replacements on Linkedin
Email Project Update for Utility Replacements link
Water and wastewater utility replacements on Augusta Dr., Greenway Dr. and Colonial Dr. are nearing completion.
Wastewater utility installs have started on BrookHollow Dr.
Street reconstruction and paving to follow completion of utility installs.
Expect street closures with detour routes in areas of construction.
Share Utility Replacements on Facebook
Share Utility Replacements on Linkedin
Email Utility Replacements link
Water and wastewater utility replacements on Augusta Dr. and Greenway Dr. are nearing completion. Construction on Colonial Dr. underway.
Street reconstruction and paving to follow completion of utility installs.
Expect street closures with detour routes in areas of construction.