In 2018, the City of Denton acquired a 6.5-acre parcel at 6414 Edwards Rd., located at the intersection of Swisher Road and Edwards Road, earmarked for a future park. The overarching vision for this property is to create a vibrant recreational space that caters specifically to the diverse needs and preferences of the local community.
In December 2020, marking a significant milestone, the City of Denton took a decisive step forward by enlisting the expertise of a consultant to develop a comprehensive Master Plan for the Villages of Carmel Property. This marked the commencement of a collaborative process geared towards envisioning the park's potential and strategically shaping its future. Subsequently, from March to July 2021, the City of Denton, working hand-in-hand with the consultant, delved into an intensive phase of coordination and design. This inclusive process integrated public perspectives through multiple engagement forums, involving crucial stakeholders such as the City Council, Parks Board, Committee of Persons with Disabilities, internal staff, and the local community. The culmination of these efforts resulted in a final park rendering that authentically reflects the collective vision and aspirations of those set to benefit from this community space.
For the latest updates and news related to the Villages of Carmel Park development, please follow the project and visit the news feed below. We extend an invitation for you to stay actively engaged and informed as we navigate through this transformative journey. Your ongoing input and feedback play a pivotal role in ensuring the success of this project.
In 2018, the City of Denton acquired a 6.5-acre parcel at 6414 Edwards Rd., located at the intersection of Swisher Road and Edwards Road, earmarked for a future park. The overarching vision for this property is to create a vibrant recreational space that caters specifically to the diverse needs and preferences of the local community.
In December 2020, marking a significant milestone, the City of Denton took a decisive step forward by enlisting the expertise of a consultant to develop a comprehensive Master Plan for the Villages of Carmel Property. This marked the commencement of a collaborative process geared towards envisioning the park's potential and strategically shaping its future. Subsequently, from March to July 2021, the City of Denton, working hand-in-hand with the consultant, delved into an intensive phase of coordination and design. This inclusive process integrated public perspectives through multiple engagement forums, involving crucial stakeholders such as the City Council, Parks Board, Committee of Persons with Disabilities, internal staff, and the local community. The culmination of these efforts resulted in a final park rendering that authentically reflects the collective vision and aspirations of those set to benefit from this community space.
For the latest updates and news related to the Villages of Carmel Park development, please follow the project and visit the news feed below. We extend an invitation for you to stay actively engaged and informed as we navigate through this transformative journey. Your ongoing input and feedback play a pivotal role in ensuring the success of this project.
Share When will construction start it stated that March 2025. Very excited about this new project near our community on FacebookShare When will construction start it stated that March 2025. Very excited about this new project near our community on TwitterShare When will construction start it stated that March 2025. Very excited about this new project near our community on LinkedinEmail When will construction start it stated that March 2025. Very excited about this new project near our community link
When will construction start it stated that March 2025. Very excited about this new project near our community
EveH
asked
about 1 month ago
Hello!
We received bid proposals on March 7th and they came in very high. We are still evaluating the bids, the project's scope and potential funding sources. Stay tuned!
Mary Gardocki, Park Planning Manager
Share Has the parks department started building this park yet? We’ve been waiting a very long time for this park. on FacebookShare Has the parks department started building this park yet? We’ve been waiting a very long time for this park. on TwitterShare Has the parks department started building this park yet? We’ve been waiting a very long time for this park. on LinkedinEmail Has the parks department started building this park yet? We’ve been waiting a very long time for this park. link
Has the parks department started building this park yet? We’ve been waiting a very long time for this park.
Shelby
asked
about 2 months ago
Hello! We apologize for the delay in responding. We received bid proposals on March 7th and they came in very high. We are still evaluating the bids, the project's scope and potential funding sources. Stay tuned!
Mary Gardocki, Park Planning Manager
mary.gardocki@cityofdenton.com
Share Hello,
Has Construction started for this park yet? I see you were planning on a summer 2024 start date with expectations to finish in 2025. Thank you! on FacebookShare Hello,
Has Construction started for this park yet? I see you were planning on a summer 2024 start date with expectations to finish in 2025. Thank you! on TwitterShare Hello,
Has Construction started for this park yet? I see you were planning on a summer 2024 start date with expectations to finish in 2025. Thank you! on LinkedinEmail Hello,
Has Construction started for this park yet? I see you were planning on a summer 2024 start date with expectations to finish in 2025. Thank you! link
Hello,
Has Construction started for this park yet? I see you were planning on a summer 2024 start date with expectations to finish in 2025. Thank you!
Andrew B
asked
9 months ago
Hello Andrew,
Construction has not started for this park yet and is anticipated to start this winter. This would push the park opening to 2025. Please stay tuned for more details as we hope to have this project out to bid in the next few weeks!
Sincerely,
Colleen Fitzpatrick, Park Project Coordinator
Share Hello, Are you still planning on starting on this park this summer?
Is this on track to be open early 2025? Thank you on FacebookShare Hello, Are you still planning on starting on this park this summer?
Is this on track to be open early 2025? Thank you on TwitterShare Hello, Are you still planning on starting on this park this summer?
Is this on track to be open early 2025? Thank you on LinkedinEmail Hello, Are you still planning on starting on this park this summer?
Is this on track to be open early 2025? Thank you link
Hello, Are you still planning on starting on this park this summer?
Is this on track to be open early 2025? Thank you
Andrew B
asked
9 months ago
Hello Andrew,
There have been several delays on this project. We expect to receive approvals from development services within the month, which will initiate the procurement process to advertise the project and receive bids for construction. We are hoping to break ground this winter. Thanks for reaching out!
Sincerely,
Colleen Fitzpatrick, Park Project Coordinator
Share When is the park construction supposed to begin/end? We are so excited to have a nice city park around the corner! on FacebookShare When is the park construction supposed to begin/end? We are so excited to have a nice city park around the corner! on TwitterShare When is the park construction supposed to begin/end? We are so excited to have a nice city park around the corner! on LinkedinEmail When is the park construction supposed to begin/end? We are so excited to have a nice city park around the corner! link
When is the park construction supposed to begin/end? We are so excited to have a nice city park around the corner!
Annie Skipper
asked
about 1 year ago
Hello,
We anticipate this project to begin construction this summer of 2024 and expect the project to last approximately 9-12 months pending weather conditions.
Share Hello!
Are there any plans to construct climbing boulders similar to the McKenna park project at this park?
Do we have an estimate on when construction will begin? on FacebookShare Hello!
Are there any plans to construct climbing boulders similar to the McKenna park project at this park?
Do we have an estimate on when construction will begin? on TwitterShare Hello!
Are there any plans to construct climbing boulders similar to the McKenna park project at this park?
Do we have an estimate on when construction will begin? on LinkedinEmail Hello!
Are there any plans to construct climbing boulders similar to the McKenna park project at this park?
Do we have an estimate on when construction will begin? link
Hello!
Are there any plans to construct climbing boulders similar to the McKenna park project at this park?
Do we have an estimate on when construction will begin?
Ghaeger
asked
about 1 year ago
Hello,
The boulders that are shown on the design are not similar to McKenna Park. The boulders placed around the playground area depicted in the renders are natural boulders that exist within the property.
The park is estimated to start this summer with the completion coming sometime in 2025. Stay tuned for more information.
Villages of Carmel Park Construction Project has finished this stage
Step 1 of the Master Plan process includes the following items to be conducted by the Project team which includes the consultant & city staff:
Identify Community Needs
Site Analyses
Concept Creation
Community Engagement & Workshop Meetings
Villages of Carmel Park Construction Project has finished this stage
Step 2 of the Master Plan process includes the following items to be conducted by the Project team which includes the consultant & city staff engaging the community.
Understand wants and needs
Introduce Visuals & Ideas
Gain & implement Feedback
Boards & Commissions Engagement
Villages of Carmel Park Construction Project has finished this stage
Step 3 of the Master Plan process includes the following items to be conducted by the Project team which includes the consultant & city staff engaging the boards & commissions (Parks, Recreation, & Beautification Board, City Council, Etc.)
Provide Community Feedback
Introduce Visuals & Ideas
Gain & Implement Feedback
Final Plan Adoption
Villages of Carmel Park Construction Project has finished this stage
Step 4 of the Master Plan process includes the following items to be conducted by the Project team which includes the consultant & city staff engaging the boards & commissions seeking approval of the proposed master plan. (Parks, Recreation, & Beautification Board, City Council, Etc.)
Incorporate Feedback from prior meetings/direction
Council & Board Final Approval
Construction Documents Deliverables & Funding
Villages of Carmel Park Construction Project is currently at this stage
Step 5 of the Master Plan process includes the following items to be conducted by the Project & Consulting team which complete the creation of the construction documents depending on the initial scope (30% or 100%). Additional this step held identify the funding sources and if applicable go through an official grant process.
Consultant to deliver the final creation of the agreed-upon set of construction documents.
Approval of construction plans from the City of Denton Development Services Team.
Identify funding mechanisms: park dedication/development funds, grants, operating account, etc.
*If grants are applicable, submit application and await award response.
*If grant is awarded, wait until funding contract is executed and notice to proceed is issued.
Construction & Grand Opening
this is an upcoming stage for Villages of Carmel Park Construction Project
Step 6 of the Master Plan process includes the following items to be conducted by the Project team and contractor that is selected to construct the project. Once funding is secured, the City will go through an official RFP process and award the contract to start construction of the project. Once construction starts projects may last 10-18 months.