Westgate Drive Improvement Project

Share Westgate Drive Improvement Project on Facebook Share Westgate Drive Improvement Project on Twitter Share Westgate Drive Improvement Project on Linkedin Email Westgate Drive Improvement Project link

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

  • The 90% Plan Set review continues at the City!

    Share The 90% Plan Set review continues at the City! on Facebook Share The 90% Plan Set review continues at the City! on Twitter Share The 90% Plan Set review continues at the City! on Linkedin Email The 90% Plan Set review continues at the City! link

    The 90% Plan Set submitted by Halff Associates continues to be reviewed by both external and internal stakeholders.

  • 90% Plan Set submitted to the City.

    Share 90% Plan Set submitted to the City. on Facebook Share 90% Plan Set submitted to the City. on Twitter Share 90% Plan Set submitted to the City. on Linkedin Email 90% Plan Set submitted to the City. link

    Halff has submitted the prepared 90% Plan Set for City review.

  • Halff Associates continues to work on permanent and temporary construction easement documents.

    Share Halff Associates continues to work on permanent and temporary construction easement documents. on Facebook Share Halff Associates continues to work on permanent and temporary construction easement documents. on Twitter Share Halff Associates continues to work on permanent and temporary construction easement documents. on Linkedin Email Halff Associates continues to work on permanent and temporary construction easement documents. link

    Halff Associates continues to work on the permanent and temporary construction easements that will be needed for the construction project.

  • ROW acquisitions to begin soon.

    Share ROW acquisitions to begin soon. on Facebook Share ROW acquisitions to begin soon. on Twitter Share ROW acquisitions to begin soon. on Linkedin Email ROW acquisitions to begin soon. link

    The City of Denton Real Estate Department and the Consultant Engineer have begun the process of preparing documents for right-of-way acquisitions.

  • Completing plan revisions

    Share Completing plan revisions on Facebook Share Completing plan revisions on Twitter Share Completing plan revisions on Linkedin Email Completing plan revisions link

    The Consultant Engineer is completing the recommended changes to the 60% Plan Set.

  • 60 percent plan set is complete!

    Share 60 percent plan set is complete! on Facebook Share 60 percent plan set is complete! on Twitter Share 60 percent plan set is complete! on Linkedin Email 60 percent plan set is complete! link

    The Consultant Engineer has submitted to the City the 60% Plan Set for its review. City Staff is checking the plan set for compliance with current standards.

  • 30 Percent Plan Schematic is complete.

    Share 30 Percent Plan Schematic is complete. on Facebook Share 30 Percent Plan Schematic is complete. on Twitter Share 30 Percent Plan Schematic is complete. on Linkedin Email 30 Percent Plan Schematic is complete. link

    The 30% Plan Schematic has been completed by the Consultant Engineer. City Staff has reviewed it and given direction to the Consultant to move forward towards the 60% Plans Set.

  • Design Survey is Complete.

    Share Design Survey is Complete. on Facebook Share Design Survey is Complete. on Twitter Share Design Survey is Complete. on Linkedin Email Design Survey is Complete. link

    The Design Consultant, Halff, has completed their design survey. The completion of the survey will allow the Consultant to begin the design of the construction plan set.

  • Westgate Drive

    Share Westgate Drive on Facebook Share Westgate Drive on Twitter Share Westgate Drive on Linkedin Email Westgate Drive link

    Halff Associates, Inc. have started the design plans. The anticipated completion of the project plans and specifications is September 2023.

  • Choosing the Consultant Engineer for Design

    Share Choosing the Consultant Engineer for Design on Facebook Share Choosing the Consultant Engineer for Design on Twitter Share Choosing the Consultant Engineer for Design on Linkedin Email Choosing the Consultant Engineer for Design link

    The Engineering/Capital Improvement Project Department have completed their review of the "request for qualifications" process from a list of prequalified engineering firms. The selected engineering firm has been approached by City staff to submit their proposal for the completion of the design.

Page last updated: 30 Apr 2025, 01:57 PM