Phase 6 - Contractor continues to work on concrete pavement detour.
Share Phase 6 - Contractor continues to work on concrete pavement detour. on Facebook Share Phase 6 - Contractor continues to work on concrete pavement detour. on Twitter Share Phase 6 - Contractor continues to work on concrete pavement detour. on Linkedin Email Phase 6 - Contractor continues to work on concrete pavement detour. linkContractor continues to work on concrete pavement detour at the intersection of Bonnie Brae and Riney Road. After traffic is moved over to the detour the Contractor will start working on constructing the new street intersection.
-
PHASE 3 - (Airport Road/FM 1515 to Roselawn) BONNIE BRAE between Willowwood and Parvin TO CLOSE June 23 - October 24, 2025
Share PHASE 3 - (Airport Road/FM 1515 to Roselawn) BONNIE BRAE between Willowwood and Parvin TO CLOSE June 23 - October 24, 2025 on Facebook Share PHASE 3 - (Airport Road/FM 1515 to Roselawn) BONNIE BRAE between Willowwood and Parvin TO CLOSE June 23 - October 24, 2025 on Twitter Share PHASE 3 - (Airport Road/FM 1515 to Roselawn) BONNIE BRAE between Willowwood and Parvin TO CLOSE June 23 - October 24, 2025 on Linkedin Email PHASE 3 - (Airport Road/FM 1515 to Roselawn) BONNIE BRAE between Willowwood and Parvin TO CLOSE June 23 - October 24, 2025 linkOn Monday June 23, 2025, the contractor will fully close Bonnie Brae between Willowwood and Parvin to install major drainage infrastructure, embankment and subgrade work for the widening in preparation for paving. Access will only be available to National Wholesale customers & area residents. This closure is expected to last until Friday October 24, 2025 (weather permitting).
Message Boards will be updated and detour signs will be posted.
We appreciate your continued patience as we make these much needed improvements.
-
Phase 6 - Contractor continues to install 16-inch ductile iron pipe along Bonnie Brae
Share Phase 6 - Contractor continues to install 16-inch ductile iron pipe along Bonnie Brae on Facebook Share Phase 6 - Contractor continues to install 16-inch ductile iron pipe along Bonnie Brae on Twitter Share Phase 6 - Contractor continues to install 16-inch ductile iron pipe along Bonnie Brae on Linkedin Email Phase 6 - Contractor continues to install 16-inch ductile iron pipe along Bonnie Brae linkThe Contractor continues to install the 16-inch ductile iron pipe along Bonnie Brae from Riney Road to Windsor Drive.
-
Phase 6 - Installation of 12-inch waterline for Reeves Elementary School
Share Phase 6 - Installation of 12-inch waterline for Reeves Elementary School on Facebook Share Phase 6 - Installation of 12-inch waterline for Reeves Elementary School on Twitter Share Phase 6 - Installation of 12-inch waterline for Reeves Elementary School on Linkedin Email Phase 6 - Installation of 12-inch waterline for Reeves Elementary School linkTiseo Paving Company is installing a 12-inch waterline where the Contractor building Reeves Elementary School will tie-in for their water supply.
-
PHASE 3 - FM1515/Airport Road to Roselawn
Share PHASE 3 - FM1515/Airport Road to Roselawn on Facebook Share PHASE 3 - FM1515/Airport Road to Roselawn on Twitter Share PHASE 3 - FM1515/Airport Road to Roselawn on Linkedin Email PHASE 3 - FM1515/Airport Road to Roselawn linkPhase 3 is progressing with installation of the new water and sanitary sewer systems as well as new underground drainage infrastructure at both the north and south ends of the project. On January 27th, Bonnie Brae at Airport Road was fully closed to all traffic. The contractor is working to complete all the underground improvements as well as paving of the section of Bonnie Brae between Airport Road and Main Stadium Drive to ensure this section of roadway can be open and accept traffic from TxDOT's 35E-Merge project which is now also under construction. Weather permitting, paving activities in this section will be complete and re-open to traffic in mid June 2025.
Paving has begun on the south end of the project near Roselawn. Sections of both the north and south bound lanes have been installed between Erskine and Roselawn.
Ongoing spot road closures through-out south Bonnie Brae will continue as underground storm drain facilities are installed and utility services are crossed under Bonnie Brae and tied-in to the new infrastructure. Message boards will be updated in advance of these planned closures. Follow posted detour signs.
The overall project is expected to be complete in November of 2026. Look for progress pictures and videos under the coordinating tab on the right.
We appreciate everyone's patience as we work hard to make these necessary improvements. Please remember to be considerate of work zones and road conditions, driving safely and according to the conditions.
-
Phase 6 - Full Notice to Proceed given to Tiseo Paving Company
Share Phase 6 - Full Notice to Proceed given to Tiseo Paving Company on Facebook Share Phase 6 - Full Notice to Proceed given to Tiseo Paving Company on Twitter Share Phase 6 - Full Notice to Proceed given to Tiseo Paving Company on Linkedin Email Phase 6 - Full Notice to Proceed given to Tiseo Paving Company linkOn March 10, 2025, the City of Denton issued a full Notice to Proceed to Tiseo Paving Company to be able to fully mobilize into the project limits. Tiseo will begin by concentrating on Riney Road from Bonnie Brae to Hardaway Road.
-
Partial Notice to Proceed issued to Tiseo Paving Company
Share Partial Notice to Proceed issued to Tiseo Paving Company on Facebook Share Partial Notice to Proceed issued to Tiseo Paving Company on Twitter Share Partial Notice to Proceed issued to Tiseo Paving Company on Linkedin Email Partial Notice to Proceed issued to Tiseo Paving Company linkCity Staff issued a Partial Notice to Proceed (NTP) to Tiseo Paving Company on February 10, 2025. The Partial NTP allows the Contractor to order material needed for the project which may have large lead time to get from factory to project site. The Partial NTP also allows for the Contractor to complete some work tasks agreed to between the City and the Contractor.
-
Construction Award to Tiseo Paving Company (Bonnie Brae Phase 6 - University Dr. to N. Elm St.)
Share Construction Award to Tiseo Paving Company (Bonnie Brae Phase 6 - University Dr. to N. Elm St.) on Facebook Share Construction Award to Tiseo Paving Company (Bonnie Brae Phase 6 - University Dr. to N. Elm St.) on Twitter Share Construction Award to Tiseo Paving Company (Bonnie Brae Phase 6 - University Dr. to N. Elm St.) on Linkedin Email Construction Award to Tiseo Paving Company (Bonnie Brae Phase 6 - University Dr. to N. Elm St.) linkOn December 17, 2024, the City Council award a contract to Tiseo Paving Company for the construction of the Bonnie Brae Phase 6 Improvement Project.
-
News Feed - January (Bonnie Brae Phase 5_ University - Scripture)
Share News Feed - January (Bonnie Brae Phase 5_ University - Scripture) on Facebook Share News Feed - January (Bonnie Brae Phase 5_ University - Scripture) on Twitter Share News Feed - January (Bonnie Brae Phase 5_ University - Scripture) on Linkedin Email News Feed - January (Bonnie Brae Phase 5_ University - Scripture) linkCity Council has voted this project to be reclassified to a Mill/Overlay project and for the funds to be disruptive to other Capital Projects.
-
News Feed - December (Bonnie Brae Phase 5_ University - Scripture)
Share News Feed - December (Bonnie Brae Phase 5_ University - Scripture) on Facebook Share News Feed - December (Bonnie Brae Phase 5_ University - Scripture) on Twitter Share News Feed - December (Bonnie Brae Phase 5_ University - Scripture) on Linkedin Email News Feed - December (Bonnie Brae Phase 5_ University - Scripture) linkThe City of Denton Internal Engineering team has completed the 30% design phase of the project. This design is currently under review by both internal and external stakeholders.