• The Bidding Phase has arrived! (Bonnie Brae Phase 6)

    Share The Bidding Phase has arrived! (Bonnie Brae Phase 6) on Facebook Share The Bidding Phase has arrived! (Bonnie Brae Phase 6) on Twitter Share The Bidding Phase has arrived! (Bonnie Brae Phase 6) on Linkedin Email The Bidding Phase has arrived! (Bonnie Brae Phase 6) link

    After a successful meeting with the Solicitation Review Committee, the Bonnie Brae Phase 6 Improvement Project will advertise for bidding starting on July 19, 2023.

  • News Feed - July (Bonnie Brae Phase 5 _University - Scripture)

    Share News Feed - July (Bonnie Brae Phase 5 _University - Scripture) on Facebook Share News Feed - July (Bonnie Brae Phase 5 _University - Scripture) on Twitter Share News Feed - July (Bonnie Brae Phase 5 _University - Scripture) on Linkedin Email News Feed - July (Bonnie Brae Phase 5 _University - Scripture) link

    With the completion of topographic and boundary surveys as a crucial step in this project phase now complete. Internal Design is currently underway.

  • Waiting on Texas Department of Transportation Letter of Approval! (Bonnie Brae Phase 6)

    Share Waiting on Texas Department of Transportation Letter of Approval! (Bonnie Brae Phase 6) on Facebook Share Waiting on Texas Department of Transportation Letter of Approval! (Bonnie Brae Phase 6) on Twitter Share Waiting on Texas Department of Transportation Letter of Approval! (Bonnie Brae Phase 6) on Linkedin Email Waiting on Texas Department of Transportation Letter of Approval! (Bonnie Brae Phase 6) link

    The Texas Department of Transportation (TxDoT) is completing their final review of the construction plans and project manual. Once that process is complete, TxDoT will issue a Letter of Approval to bid the project.

  • News Feed - June (Bonnie Brae Phase 5 _University - Scripture)

    Share News Feed - June (Bonnie Brae Phase 5 _University - Scripture) on Facebook Share News Feed - June (Bonnie Brae Phase 5 _University - Scripture) on Twitter Share News Feed - June (Bonnie Brae Phase 5 _University - Scripture) on Linkedin Email News Feed - June (Bonnie Brae Phase 5 _University - Scripture) link

    With the completion of topographic and boundary surveys as a crucial step in this project phase now complete. These surveys provide detailed information about the land's features and boundaries, which is essential for accurate design and planning. The data will now be review from our internal Engineering group to design a plan that best fits the Phase 4 and Phase 6 sections.

  • Contract Documents being finalized! (Bonnie Brae Phase 6)

    Share Contract Documents being finalized! (Bonnie Brae Phase 6) on Facebook Share Contract Documents being finalized! (Bonnie Brae Phase 6) on Twitter Share Contract Documents being finalized! (Bonnie Brae Phase 6) on Linkedin Email Contract Documents being finalized! (Bonnie Brae Phase 6) link

    In addition to completing the construction plan set, completing the Contract Documents are equally important. The Contract Documents help in leading the City and the Contractor through the bidding and construction process.

  • Revisions to the 100% Plan Set continues at TxDoT.

    Share Revisions to the 100% Plan Set continues at TxDoT. on Facebook Share Revisions to the 100% Plan Set continues at TxDoT. on Twitter Share Revisions to the 100% Plan Set continues at TxDoT. on Linkedin Email Revisions to the 100% Plan Set continues at TxDoT. link

    The City's Consultant Engineer continues to make revisions as TxDoT progresses with their review.

  • 100 Percent Plans submitted to TxDoT

    Share 100 Percent Plans submitted to TxDoT on Facebook Share 100 Percent Plans submitted to TxDoT on Twitter Share 100 Percent Plans submitted to TxDoT on Linkedin Email 100 Percent Plans submitted to TxDoT link

    The Consultant Engineer in charge of designing the Bonnie Brae Phase 6 plan set has submitted to Texas Department of Transportation for final review.

  • Bonnie Brae Phase 6 (US 380/University Drive to US 77/ N. Elm Street)

    Share Bonnie Brae Phase 6 (US 380/University Drive to US 77/ N. Elm Street) on Facebook Share Bonnie Brae Phase 6 (US 380/University Drive to US 77/ N. Elm Street) on Twitter Share Bonnie Brae Phase 6 (US 380/University Drive to US 77/ N. Elm Street) on Linkedin Email Bonnie Brae Phase 6 (US 380/University Drive to US 77/ N. Elm Street) link

    Bonnie Brae Phase 6 is on track to advertise for bid in Q1 2024 pending the completion of the remaining utility relocation agreements. Staff are working with TxDOT to receive the State Letter of Authority required to advertise the project for construction. Construction is anticipated to begin Q1 of 2024. A Community Meeting will be held prior to the start of construction.

  • Bonnie Brae Phase 6 (US 380/University to US 77/Elm Street)

    Share Bonnie Brae Phase 6 (US 380/University to US 77/Elm Street) on Facebook Share Bonnie Brae Phase 6 (US 380/University to US 77/Elm Street) on Twitter Share Bonnie Brae Phase 6 (US 380/University to US 77/Elm Street) on Linkedin Email Bonnie Brae Phase 6 (US 380/University to US 77/Elm Street) link

    Bonnie Brae Phase 6 is on track to advertise for bid in Q4 2023 pending the completion of the remaining utility relocation agreements. Staff are working with TxDOT to receive the State Letter of Authority required to advertise the project for construction. Construction is anticipated to begin Q1 of 2024. A Community Meeting will be held prior to the start of construction.