Hickory Creek Interceptor

Share Hickory Creek Interceptor on Facebook Share Hickory Creek Interceptor on Twitter Share Hickory Creek Interceptor on Linkedin Email Hickory Creek Interceptor link
In the Beginning ...

Hickory Creek Interceptor (HCI) Capital Improvement Project Program is a multi-phased sanitary sewer project. The existing interceptor was installed in the 1980s. The new construction will add capacity and improve wastewater services to accommodate future growth projected to occur in the Hickory Creek Basin.

Hickory Creek Interceptor Phase 1&2 Project Status

HCI 1 & 2 includes the replacement of approximately 13,000 linear feet (2.46 miles) of 36, 42, 48 and 54-inch sewer mains along Hickory Creek from Fort Worth Drive (US 377) to I-35W. Construction is ongoing and the project is expected to be complete the first of the new year (2023)


Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Complete

Q1 '23


Hickory Creek Interceptor Phase 3 Project Status

HCI 3 will continue from HCI 1&2 to the north extending the planned improvements to upgrade the Hickory Creek Interceptor Corridor. Installation of approximately 9,700 LF of 30-inch sewer line with an improved alignment to replace the existing 12-inch sewer main and the rehabilitation of an existing 12-inch sewer line that crosses the creek. Utilities, THC, and TxDOT are clear.

The project has started advertising process. Staff evaluated the scope of the project and recommended using CSP (Competitive Sealed Proposal) instead of IFB (Invitation For Bid or “low bid”). CSP will allow staff to consider the contractor's staff, project workload, and history within our highly competitive market without price being the sole consideration.

Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Q1 '23 - Q1 '24

Q1 '24


* All dates are estimates and subject to change without notice.



Hickory Creek Interceptor (HCI) Capital Improvement Project Program is a multi-phased sanitary sewer project. The existing interceptor was installed in the 1980s. The new construction will add capacity and improve wastewater services to accommodate future growth projected to occur in the Hickory Creek Basin.

Hickory Creek Interceptor Phase 1&2 Project Status

HCI 1 & 2 includes the replacement of approximately 13,000 linear feet (2.46 miles) of 36, 42, 48 and 54-inch sewer mains along Hickory Creek from Fort Worth Drive (US 377) to I-35W. Construction is ongoing and the project is expected to be complete the first of the new year (2023)


Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Complete

Q1 '23


Hickory Creek Interceptor Phase 3 Project Status

HCI 3 will continue from HCI 1&2 to the north extending the planned improvements to upgrade the Hickory Creek Interceptor Corridor. Installation of approximately 9,700 LF of 30-inch sewer line with an improved alignment to replace the existing 12-inch sewer main and the rehabilitation of an existing 12-inch sewer line that crosses the creek. Utilities, THC, and TxDOT are clear.

The project has started advertising process. Staff evaluated the scope of the project and recommended using CSP (Competitive Sealed Proposal) instead of IFB (Invitation For Bid or “low bid”). CSP will allow staff to consider the contractor's staff, project workload, and history within our highly competitive market without price being the sole consideration.

Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Q1 '23 - Q1 '24

Q1 '24


* All dates are estimates and subject to change without notice.



  • Project Status Update 2/2023

    Share Project Status Update 2/2023 on Facebook Share Project Status Update 2/2023 on Twitter Share Project Status Update 2/2023 on Linkedin Email Project Status Update 2/2023 link
    supporting image

    January 2023 accomplishment included the substantial completion of HCI 1&2. The remaining items include some pavement and vegetation restoration. For HCI 3, City of Denton Council awarded the Construction Contract to Wilson Contractor Services (Denton). February is starting icy and very cold but hey, it's Texas we'll warm up for Valentine's because Denton Loves Construction! Planned February tasks include wrapping up final paperwork to execute the contracts, setting a Public Meeting date, setting a Pre-Construction Meeting date. The Team will also be working to identify a Notice-to-Proceed (NTP) date and from that date, the project is anticipated to last 400 days (13 months) pending no issues (such as weather or unforeseen conflicts).

  • Project Status Update 1/2023

    Share Project Status Update 1/2023 on Facebook Share Project Status Update 1/2023 on Twitter Share Project Status Update 1/2023 on Linkedin Email Project Status Update 1/2023 link
    supporting image

    It's 2023 and the HCI 1&2 project is schedule to close up over the next couple of months (new line is operating, old line is being abandoned, and final clean up and vegetation is underway. The HCI 3 project is on schedule to go to City Council on 1/24/23 to award the project to the Construction Contractor. Once approved, the construction schedule can be finalized including the start and finish date. The project is expected to take 13-14 months once started.

  • Project Status 12/2022

    Share Project Status 12/2022 on Facebook Share Project Status 12/2022 on Twitter Share Project Status 12/2022 on Linkedin Email Project Status 12/2022 link
    supporting image

    Hickory Creek Interceptor 1&2, like 2022, is winding down as the project continues towards a mid-January 2023 completion. The siphons are complete, final tie-ins are being made on the upstream, the old line is being abandoned. The City and Contractor have started the final walkthroughs & punch lists and the disturbed land is being restored and vegetated.

    Hickory Creek Interceptor 3 has been advertised for construction, proposals have been evaluated, and final selection of a construction contractor is underway. Upon approval by the Public Utilities Board and City Council, the project is scheduled to be awarded in January 2023 and construction will start within 1-2 months thereafter.


  • Project Status Update 11/2022

    Share Project Status Update 11/2022 on Facebook Share Project Status Update 11/2022 on Twitter Share Project Status Update 11/2022 on Linkedin Email Project Status Update 11/2022 link
    supporting image

    It's November, a time to give thanks and this November we have a lot to be thankful for with respect to Hickory Creek Interceptor (HCI) projects. Mountain Cascade of Texas continues to work hard at wrapping up the final items on the HCI 1&2 project and we start to give thought to the next phase - Close Out (final inspections and walk throughs, preparation of As Built drawings and getting the vegetation established to help our watershed).

    For HCI 3, we are thankful Advertising for bids has closed, and the Bids have been opened. The HCI 3 Project is being delivered using Competitive Sealed Proposals (CSP) versus "Low Bid" method. The CSP method requires that all bidders to provide more detail in their proposal such as qualifications of key personnel, quality, reputation, experience, safety, schedule and work plan in addition to their price bid. This additional effort allows the bidders the opportunity share why they feel they are best qualified. Similarly, this approach places additional responsibility on the City to thoroughly review all bids and not just rely on the contractor with the lowest price. The result - better information sharing between bidders and city and ideally a better project experience for all stakeholders.

    Staff has started the review of the proposals. Evaluations will take place through the week of Thanksgiving and once complete and once all procurement documentation is finalized, Staff will target the earliest possible Public Utilities Board and City Council dates to award the project (both meetings are anticipated in January 2023). Construction is anticipated to start March 2023 (all dates are subject to change).

  • 10/2022 Status Update

    Share 10/2022 Status Update on Facebook Share 10/2022 Status Update on Twitter Share 10/2022 Status Update on Linkedin Email 10/2022 Status Update link

    Construction is winding down for Hickory Creek Interceptor 1&2. Final work on the siphon and the connections to the existing lines are underway and vegetative establishment is beginning. Meanwhile, Hickory Creek Interceptor 3 is "out to bid" for construction. Over the next two months, advertising will close, bids will be opened, and staff will evaluate the contractor submittals and make a recommendation to the Public Utilities Board and City Council to award the project. Construction is expected to start in February 2023 and will last approximately 12 months.

  • Project Status Update 9-2022

    Share Project Status Update 9-2022 on Facebook Share Project Status Update 9-2022 on Twitter Share Project Status Update 9-2022 on Linkedin Email Project Status Update 9-2022 link
    supporting image

    The Hickory Creek Interceptor Phase 1&2 progress continues. Current activities include restoring the worksite, getting ready to connect the north end and south end to the existing sewer line, and construction of the inverted siphon. The project is still on schedule to be complete by the close of 2022.

  • Project Status 8-2022

    Share Project Status 8-2022 on Facebook Share Project Status 8-2022 on Twitter Share Project Status 8-2022 on Linkedin Email Project Status 8-2022 link

    Hickory Creek Interceptor Phase 1&2 is continuing progress. Completion is still on schedule for end of 2022 and closeout in the New Year.

  • Beneath The Surface: Hickory Creek Interceptor

    Share Beneath The Surface: Hickory Creek Interceptor on Facebook Share Beneath The Surface: Hickory Creek Interceptor on Twitter Share Beneath The Surface: Hickory Creek Interceptor on Linkedin Email Beneath The Surface: Hickory Creek Interceptor link
    supporting image

    Short video overview of the Hickory Creek Interceptor Phase 1&2.

  • Hickory Creek Interceptor Project Updates

    Share Hickory Creek Interceptor Project Updates on Facebook Share Hickory Creek Interceptor Project Updates on Twitter Share Hickory Creek Interceptor Project Updates on Linkedin Email Hickory Creek Interceptor Project Updates link
    supporting image

    As of June 3, 2022, construction work has been progressing favorably and is on tract to stay on schedule as the summer promises to turn up the heat.

    On Monday, January 3, 2022, Mountain Cascade of Texas was able to start construction with no further obstructions and a plan to be complete by the end of the year.

    On Monday, August 2, 2021 the Hickory Creek Interceptor CIP was issued a Notice To Proceed and construction activities started with an anticipated completion date of August 2, 2022, while construction coordination continued with the Texas Historical Commission and the Union Pacific Railroad.

Page last updated: 30 Apr 2024, 04:13 PM