Fire House #5 and #6

Share Fire House #5 and #6 on Facebook Share Fire House #5 and #6 on Twitter Share Fire House #5 and #6 on Linkedin Email Fire House #5 and #6 link
Rendering of Station #5 and #6

Two (2) new Fire Stations with approximately 12,500 to 14,500 square feet. One (1) fire station, including four (4) apparatus bays, and one (1) fire station, including three (3) apparatus bays with living spaces that will support (10) personnel, including two (2) officers.

Two (2) new Fire Stations with approximately 12,500 to 14,500 square feet. One (1) fire station, including four (4) apparatus bays, and one (1) fire station, including three (3) apparatus bays with living spaces that will support (10) personnel, including two (2) officers.

  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link

    ACHIEVEMENTS:

    • 100% Design Documents

    • 100% Extreme Modular Building Design Document

    • Early Estimate Received from CMAR and Reviewed by City Stakeholders

    • 50% CD’s 01-Oct

    • Preconstruction efforts/Site Investigation

    • FF&E/IT Budgeting Meetings

    • EMB Foundation Design

    • CoD Capital Projects Partnering Session for FS5&6 13-Sep


    NEXT STEPS:

    • Terracon Engineering Services Scope and Contract to CC 22-Oct

    • 50% Construction Documents (City Review)

    • 50% Estimates

    • 90% Construction Documents 12-Nov

    • Extreme Modular Building Construction Documents to be Approved by State

    • 100% CD Issued for Permitting and Bidding 17-Dec

    • Extreme Modular Building Construction

    • GMP-01 to CC 22-NOV (EMB/Early Site Work/Gensets)

    • Project Kickoff 31-Oct

    • Early Permitting

    • Acquire Storm Shelter Consulting Service

    • Art Package to CoD Art Committee

  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link


    ACHIEVEMENTS:

    üCMAR Preconstruction Negotiation
    ü100% Schematic Design complete
    ü100% Design Documents 20-Aug
    üStorm Shelter Proposal Recieved

    NEXT STEPS:

    qTerracon Engineering Scope and Contract
    q100% DD Review by City
    qInitial Estimates (Mid-Sept)
    q50% Construction Documents 01-Oct
    q100% CD’s Complete 29-Nov
    q100% CD’s City Review (6 weeks)

  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link
    supporting image


    ACHIEVEMENTS:

    üMaterial Testing
    üFinal Scoring of CMAR and Selection
    üCMAR Preconstruction Negotiation
    ü100% Schematic Design complete

    NEXT STEPS:

    qPrecon CMAR GMP - City Council Date Pending
    qTerracon Engineering Services Scope and Contract
    q100% Extreme Modular Building Construction Doc.
    q100% Design Documents
    q50% Construction Documents
    q100% CD Issued for Permitting and Bidding
    qExtreme Modular Building Delivery Dec-Jan
    qGMP to City Council Dec-Jan



  • Schematic Desing Phase

    Share Schematic Desing Phase on Facebook Share Schematic Desing Phase on Twitter Share Schematic Desing Phase on Linkedin Email Schematic Desing Phase link

    ACHIEVEMENTS:

    üBegin Discussions with internal Team Members
    üA/E Team Kickoff Meeting
    üBegin Programming
    üPre-Bid Meeting and Site Walk
    üSolicit CMAR
    üLocation of Extreme Modular Building (EMB) for temporary CoD Fire Department
    üMaterial Testing
    üFinal Scoring of CMAR