Hickory Creek Road Phase 3 Project
The Hickory Creek Road Phase 3 project is located on Hickory Creek Road from Riverpass Drive to FM-1830. To improve safety and mobility in the area, the project includes the design and construction of a four-lane extension and realignment of Hickory Creek Road from Riverpass Drive to FM-1830, and the construction of a bridge that will span Hickory Creek and remove the safety concern of the 90 degree curve from the current Hickory Creek alignment. This project is part of a larger reconstruction and widening project for Hickory Creek Road with the goal of a continuous four lane divided roadContinue reading
The Hickory Creek Road Phase 3 project is located on Hickory Creek Road from Riverpass Drive to FM-1830. To improve safety and mobility in the area, the project includes the design and construction of a four-lane extension and realignment of Hickory Creek Road from Riverpass Drive to FM-1830, and the construction of a bridge that will span Hickory Creek and remove the safety concern of the 90 degree curve from the current Hickory Creek alignment. This project is part of a larger reconstruction and widening project for Hickory Creek Road with the goal of a continuous four lane divided road along Hickory Creek Road from FM 2499 to FM 1830.
Project Status

-
Project Update
Share Project Update on Facebook Share Project Update on Twitter Share Project Update on Linkedin Email Project Update linkThe Hickory Creek Road Phase 3 project has scheduled for the first part of November the power line raising to be completed as part of the project. The structures for the transfer of the electric line have been completed and are awaiting the scheduled approved timing. As this line is a transmission line and not a distribution line residents in the area should not experience any power outages.
-
Utility Line Relocations
Share Utility Line Relocations on Facebook Share Utility Line Relocations on Twitter Share Utility Line Relocations on Linkedin Email Utility Line Relocations linkThe Hickory Creek Road Phase 3 project is currently having utility relocations done as the project is getting ready to start construction in Q3 2022. If you would like to get the most current project updates please sign up for the project email alerts.
-
Hickory Creek Road Phase 3 Construction Kickoff Virtual Meeting
Share Hickory Creek Road Phase 3 Construction Kickoff Virtual Meeting on Facebook Share Hickory Creek Road Phase 3 Construction Kickoff Virtual Meeting on Twitter Share Hickory Creek Road Phase 3 Construction Kickoff Virtual Meeting on Linkedin Email Hickory Creek Road Phase 3 Construction Kickoff Virtual Meeting linkYou can use the following link to view the virtual Construction Kickoff Meeting.
-
Hickory Creek 3 Visual Presentation
Share Hickory Creek 3 Visual Presentation on Facebook Share Hickory Creek 3 Visual Presentation on Twitter Share Hickory Creek 3 Visual Presentation on Linkedin Email Hickory Creek 3 Visual Presentation link -
Hickory Creek Road Phase 3 Virtual Community Meeting Replay
Share Hickory Creek Road Phase 3 Virtual Community Meeting Replay on Facebook Share Hickory Creek Road Phase 3 Virtual Community Meeting Replay on Twitter Share Hickory Creek Road Phase 3 Virtual Community Meeting Replay on Linkedin Email Hickory Creek Road Phase 3 Virtual Community Meeting Replay linkOn Thursday, July 8, City staff hosted a virtual community meeting regarding the Hickory Creek Road Phase 3 project. View the meeting replay below.
-
Upcoming Virtual Community Meeting
Share Upcoming Virtual Community Meeting on Facebook Share Upcoming Virtual Community Meeting on Twitter Share Upcoming Virtual Community Meeting on Linkedin Email Upcoming Virtual Community Meeting linkThe City of Denton will hold a virtual Community Meeting on Thursday, July 8 at 6 p.m. regarding the roadway extension and realignment of Hickory Creek Road from Riverpass Drive to FM-1830 as part of the Hickory Creek Road Phase 3 Capital Improvement Project (CIP). Sign up to attend the Hickory Creek Road Phase 3 virtual community meeting HERE.
The City will host the virtual community meeting to provide residents and property owners the opportunity to:
- Receive an update on the status of the Hickory Creek Road Phase 3 Project,
- Receive an update on the design and construction timeline for Hickory Creek Road Phase 3; and
- Discuss input and concerns from community members.
Staff from the City of Denton Capital Projects/Engineering Department will be available to discuss the project and answer questions from those participating in the virtual meeting. The meeting will be hosted online using a remote format through the video-conferencing interface Zoom.
Stay Updated and Have Your Say
Click HERE to register to stay informed and ask the project manager a question about the Hickory Creek Road Phase 3 Capital Improvement Project.
Project Information
Budget: $54 Million
Sponsoring Division: Engineering Department
Funding Source: 2019 Bond Program
Project Location: Riverpass Drive to FM 1830
Contact Information:
Multi-phase projects may require different project managers. Below is the current project manager(s) and the phase(s) they manage.
Who's Listening
-
Phone 940-349-8925 Email tracy.beck@cityofdenton.com -
Deputy Director Capital Projects