Neighborhood 1B
The 2019 Bond Neighborhood 1B project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 1B project as well as the breakdown of the phases. Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.
Project Timeline Q4 2023 - Q4 2026*
*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors, and will be updated as needed.
The 2019 Bond Neighborhood 1B project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 1B project as well as the breakdown of the phases. Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.
Project Timeline Q4 2023 - Q4 2026*
*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors, and will be updated as needed.
-
August Update & Lookahead
Share August Update & Lookahead on Facebook Share August Update & Lookahead on Twitter Share August Update & Lookahead on Linkedin Email August Update & Lookahead linkUpdated as of 09-12-2025
- Juno Lane: Atlas Dr. to Stuart Rd. – Concrete construction complete. Final HMA lift scheduled for tomorrow 9/5.
- Cactus Circle: Yucca Dr. to Cul-de-sac – First Lift HMA today 9/4. Concrete Flatworks to follow.
- Huisache Street: Aspen Dr. to Yucca Dr. – Concrete curb & gutter complete, driveways started.
- Northridge Street: Hinkle Dr. to Bolivar St. – Sanitary sewer (SS) underway. Crew is installing services on Line B (Mesquite to Carroll). Main started on Line A (Mesquite to Hinkle).
- Selene Drive: Stuart Rd. to End – Trench line to be backfilled with base. Work will resume with tie in for Apollo, tentative early October.
- Sunnydale Lane: Kings Row to Sun Valley Dr. – SS main completing this week. Remaining services to follow. Estimated completion of main and services 9/10.
- Yellowstone Place: Hercules Lane to Juno Ln. – HMA first lift placed. Roadway prepared for concrete works to start following Huisache St.
- Sheraton Road: Imperial Dr. to Sun Valley Dr. – SS Main started 9/2.
- Pershing Drive: Atlas Dr. to Stuart Rd. – Revised drawings received. SS main started 9/2.
- Camelot Street: Hercules Ln. to Stuart Rd – Roadway work complete. Awaiting favorable weather to place sod. No current presence on the road.
- Redstone Road: Hercules Ln. End – SS delayed for Atmos gas line conflicts. Sundt demobilized 8/20.
Updated as of 08-20-2025
NBHD 1B
- Cactus Circle: Yucca Dr. to Cul-de-sac – Lime placed 8/18. First lift Hot mixed Asphalt (HMA) tentatively scheduled for the end of August with concrete work to follow.
- Camelot Street: Hercules Ln. to Stuart Rd. – Roadway work complete. Awaiting favorable weather to place sod. No current presence on the road.
- Huisache Street: Aspen Dr. to Yucca Dr. – Concrete placements starting week of 8/25 following the completion of Juno Lane
- Juno Lane: Atlas Dr. to Stuart Rd. – Concrete construction underway and expected to finish within a week. Final Hot mixed Asphalt (HMA) lift tentatively scheduled for the end of August.
- Northridge Street: Hinkle Dr. to Bolivar St. – Sanitary sewer underway. Crew is finishing Line B (Mesquite to Carroll). Fiber relocation completed 8/18, work has started on Line A (Mesquite to Hinkle). Line C (Carroll to Bolivar) expected to start week of 8/25.
- Pershing Drive: Atlas Dr. to Stuart Rd. – Sanitary Sewer delayed for Atmos gas line conflicts. Sundt demobilizing this week 8/19.
- Redstone Road: Hercules Ln. End – Sanitary Sewer delayed for Atmos gas line conflicts. Sundt demobilizing this week 8/20.
- Selene Drive: Stuart Rd. to End – SS main complete. Crew actively installing Sanitary Sewer services. Crew will demobilize to Northridge next week
- Sheraton Road: Imperial Dr. to Sun Valley Dr. – Crew mobilized 8/19 to pothole and commence Sanitary Sewer main.
- Sunnydale Lane: Kings Row to Sun Valley Dr. – Sanitary Sewer underway. Estimated completion of main and services 9/10.
- Titan Trail: Hercules Ln. to Redstone Rd. – Saw cut scheduled for next week. First deliveries expected 9/12.
- Yellowstone Place: Hercules Lane to Juno Ln. – Hot mixed Asphalt (HMA) first lift placed. Roadway prepared for concrete works to start following Huisache St.
1. Apollo Drive: Selene Dr. to Redstone Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation
2. Cactus Circle: Yucca Dr. to Cul-de-sac
- Utility work to include lowering existing water services found to be too shallow. (Some residents may experience brief service interruptions)
- Earthwork to include rough grading, lime stabilization, and fine grading
- Paving to include asphalt placement followed by the installation of curb and gutter, driveways and miscellaneous concrete
3. Huisache Street: Aspen Dr. to Yucca Dr.
- Installation of curb and gutter, driveways and miscellaneous concrete
4. Juno Lane: Atlas Dr. to Stuart Rd.
- Earthwork to include lime stabilization, fine grading
- Paving to include the installation of curb and gutter, driveways and miscellaneous concrete
5. Northridge Street: Hinkle Dr. to Bolivar St.
- Utility work consisting of sewer installation
6. Pershing Drive: Atlas Dr. to Stuart Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation and waterline installation
7. Selene Drive: Stuart Rd. to End
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
- Earthwork to include rough grading, and lime stabilization
8. Sheraton Road: Imperial Dr. to Sun Valley Dr. (Notifications to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
- Earthwork to include rough grading
9. Sunnydale Lane: Kings Row to Sun Valley Dr.
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, driveways and sidewalks
- Earthwork to include rough grading, lime stabilization, and fine grading
10. Yellowstone Place: Hercules Lane to Juno Ln.
- Earthwork to include lime stabilization, fine grading
- Paving to include the installation of curb and gutter, driveways and miscellaneous concrete
11. Redstone Road: Hercules Ln. End
- Atmos gas conflicts have this segment in a delay. City is awaiting Atmos's completion of relocating their existing utilities before the contractor can proceed with the proposed improvements.
-
July Update
Share July Update on Facebook Share July Update on Twitter Share July Update on Linkedin Email July Update linkUtility improvements continue along various streets as well as road reconstruction on several street segments. The contractor took pro-active action by applying asphalt millings to streets where asphalt paving has been removed in advance of the 4th of July weekend. These efforts should prove helpful in the event we encounter any rain over the weekend.
-
June Update
Share June Update on Facebook Share June Update on Twitter Share June Update on Linkedin Email June Update linkThe contractor continues to make progress with utility installation along various segments of the project. Other improvements include subgrade preparation and some asphalt paving. The contractor will continue to provide door hanger notification to affected residents advising of pending road closures as they prepare to work on their street.
-
May Update
Share May Update on Facebook Share May Update on Twitter Share May Update on Linkedin Email May Update linkWith this project officially underway, the contractor has begun the removal of existing asphalt paving and curb and gutter along several segments. Additionally, the contractor has started utility installation.
-
April Update
Share April Update on Facebook Share April Update on Twitter Share April Update on Linkedin Email April Update linkCity staff conducted a virtual community meeting on Aril 3rd. The purpose of this meeting was to present the timeline, potential impacts, and ways to stay informed during the construction phase of this project. Residents were encouraged to ask questions which were answered during this meeting. It was explained that residents could expect to see the beginnings of construction activities on some of their streets as the contractor begins to move in the second week of April to begin staging, saw-cutting, and setting up traffic control measures.
-
March Update
Share March Update on Facebook Share March Update on Twitter Share March Update on Linkedin Email March Update linkNeighborhood 1B construction contract with Sundt Construction will go to City Council for approval on March 4, 2025.
Construction to start April 2025
Who's Listening
-
Phone (940) 349-8909 Email scott.fettig@cityofdenton.com -
Phone (940) 349-7104 Email dante.hale@cityofdenton.com
Project Budget and Information
Estimated Budget: $31 Million
Sponsoring Department:
Capital Projects
Water Distribution
Wastewater Collections
Streets
Project Location: Various Street Locations
Stay Informed
Click HERE to register to stay informed and ask the project manager a question about the project.