2019 Bond Neighborhood 2 & 6
The 2019 Bond Neighborhoods 2 & 6 project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 2 & 6 project as well as the breakdown of the phases (Packages 1, 2 & 3). Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.
Project Timeline Q4 2022 - Q4 2026*
*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors, and will be updated as needed.
The 2019 Bond Neighborhoods 2 & 6 project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. Maps are provided to left (or bottom) for all streets that will be part of the Neighborhood 2 & 6 project as well as the breakdown of the phases (Packages 1, 2 & 3). Street reconstruction will include new curb and gutter, asphalt/concrete roadways and upgrading select water and/or wastewater facilities. There will be some areas of sidewalk and street lighting replacement and areas of new lighting & sidewalk.
Project Timeline Q4 2022 - Q4 2026*
*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction. Estimated project timelines may change due to weather, contractor scheduling, among other factors, and will be updated as needed.
-
TRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS
Share TRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS on Facebook Share TRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS on Twitter Share TRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS on Linkedin Email TRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS linkTRAFFIC CONTROL UPDATE - CRESCENT - LINDEN - THOMAS
Please look for notices on April 24 and be prepared to see a change in Traffic Control starting as soon as Friday April 26. See Map below for areas being impacted.
For more information - follow the SUNDT Project Update Site at:
Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
-
4/22/2024 Update and Lookahead
Share 4/22/2024 Update and Lookahead on Facebook Share 4/22/2024 Update and Lookahead on Twitter Share 4/22/2024 Update and Lookahead on Linkedin Email 4/22/2024 Update and Lookahead link(All dates are subject to change due to weather impacts or unforeseen circumstances.)
Maple Street:
Completed - Lime was mixed last week and left to mellow over the weekend.
What's Next - Lime will be remixed 4/22/24 followed by compaction and fine grading this week. Asphalt is currently scheduled for April 30th.
Broadway Street:
Completed - Made great progress on concrete driveway placements last week!
What's Next - This week Sundt will be forming and placing the remaining concrete driveways and the inlet throat adjacent to Malone. Asphalt currently scheduled for May 2nd.
Hillcrest St:
Completed - 8" main installation was completed last week and substantial progress was made on the laterals.What's Next - Complete laterals this week. The camera crew is schedule for Thursday. Plan to mill Hillcrest Friday 26th and Monday the 27th.
Crescent St (Ector St to Hillcrest St):
Completed - Removals completed last week followed rough grade starting.What's Next - Rough grading continuing and Lime is currently scheduled for Thursday 25th.
Thomas/Crescent/Linden:
What's Next - Notice to Residents will be going out Wednesday & Traffic Control will be placed Friday. Sewer Installation will begin next week.
For more information - follow the SUNDT Project Update Site at:
Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
-
4/5/2024 Update and Lookahead
Share 4/5/2024 Update and Lookahead on Facebook Share 4/5/2024 Update and Lookahead on Twitter Share 4/5/2024 Update and Lookahead on Linkedin Email 4/5/2024 Update and Lookahead link(All dates are subject to change due to weather impacts or unforeseen circumstances.)
Maple Street:
Completed - Transitioned traffic control to close the south side of Maple St. followed by pedestrian control measures including snow fence and chain link fence panels. Milling of the existing asphalt was completed with temporary pedestrian crosswalks installed afterwards. Concrete removals will be complete 4/5/24 .
Next week - Rough grading, with lime currently scheduled for Wednesday 4/10/24 with mixing and mellowing through the weekend.
Broadway Street:
Completed - Curb and gutter formwork this week and will be pouring the first round of concrete 4/5/24.
Next week - Concrete placements everyday to complete all curb and gutter and begin driveways followed by curb ramps and leadwalks.
Hillcrest St:
ONGOING - continued this week installing hundreds of feet of 8" sewer mains and a new manhole at Linden.Next week - Complete the main line and manhole at Panhandle. Service laterals will follow, starting at Crescent and working southward.
For more information - follow the SUNDT Project Update Site at:
Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
-
3/29/24 Update
Share 3/29/24 Update on Facebook Share 3/29/24 Update on Twitter Share 3/29/24 Update on Linkedin Email 3/29/24 Update linkGood Friday is wrapping up as is good progress on the Neighborhood 2&6 project street sections. On behalf of the Team, we appreciate your support and wish you a Safe and Happy Easter Weekend! There won't be any work this weekend but we'll be back on site Monday.
For more project information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
-
3/22/2024 Update
Share 3/22/2024 Update on Facebook Share 3/22/2024 Update on Twitter Share 3/22/2024 Update on Linkedin Email 3/22/2024 Update link(All dates are subject to change due to weather impacts or unforeseen circumstances)
MAPLE St.
- Completed - Northside curb and gutter installation. Remaining concrete activities on this north side are several ramps and small amount of sidewalk.
- Next week - Second lift of asphalt is scheduled for Tuesday 3/26 and Wednesday 3/27. Traffic Control Plan activities will follow second lift of asphalt which will require switching work to the south side for upcoming removal activities.
BROADWAY St.
- Completed - Earthwork activities have been completed this week and the lime-stabilized subgrade is now ready for the first lift of asphalt.
- Next week - First Lift of Asphalt scheduled for Monday 3/25. Following the asphalt installation concrete crew will begin curb and gutter, driveways, and a couple curb ramps.
CRESCENT / HILLCREST
- Completed - Installation of the sewer manholes (2) and piping on Cresent between Ector and Hillcrest.
- Next week - Trench work and pipe installation to begin at the intersection of Hillcrest/Crescent and move south.
For more information - follow the SUNDT Project Update Site at: Neighborhoods 2 & 6 - Denton Utilities Improvements by Sundt (sundtdenton.com)
-
February Update
Share February Update on Facebook Share February Update on Twitter Share February Update on Linkedin Email February Update linkNeighborhood 2 & 6 project is currently in the design and construction phases.
Expect to see survey crews and staff in the areas of the project.
Construction has started for Package 1. Expect to see crews, equipment and street closures in the areas of package one. (reference map)
Detour routes will be provided for street closures.
-
January Update
Share January Update on Facebook Share January Update on Twitter Share January Update on Linkedin Email January Update linkNeighborhood 2 & 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start for Package 1 will be January 2024
-
December Update for Neighborhood 2 & 6
Share December Update for Neighborhood 2 & 6 on Facebook Share December Update for Neighborhood 2 & 6 on Twitter Share December Update for Neighborhood 2 & 6 on Linkedin Email December Update for Neighborhood 2 & 6 linkNeighborhood 2 & 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start for Package 1 will be January 2024
-
November Update for Neighborhood 6
Share November Update for Neighborhood 6 on Facebook Share November Update for Neighborhood 6 on Twitter Share November Update for Neighborhood 6 on Linkedin Email November Update for Neighborhood 6 linkNeighborhood 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start is Q1 2024
-
September Update for Neighborhood 6
Share September Update for Neighborhood 6 on Facebook Share September Update for Neighborhood 6 on Twitter Share September Update for Neighborhood 6 on Linkedin Email September Update for Neighborhood 6 linkNeighborhood 6 project is currently in the planning and design phase.
Expect to see survey crews and staff in the areas of the project.
Estimated construction start is Q4 2023
Stay Informed
Click HERE to register to stay informed and ask the project manager a question about the project.