Westgate Drive Improvement Project
The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.
Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.
Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026
The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.
Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.
Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026
-
Halff Associates continues to work on permanent and temporary construction easement documents.
Share Halff Associates continues to work on permanent and temporary construction easement documents. on Facebook Share Halff Associates continues to work on permanent and temporary construction easement documents. on Twitter Share Halff Associates continues to work on permanent and temporary construction easement documents. on Linkedin Email Halff Associates continues to work on permanent and temporary construction easement documents. linkHalff Associates continues to work on the permanent and temporary construction easements that will be needed for the construction project.
-
ROW acquisitions to begin soon.
Share ROW acquisitions to begin soon. on Facebook Share ROW acquisitions to begin soon. on Twitter Share ROW acquisitions to begin soon. on Linkedin Email ROW acquisitions to begin soon. linkThe City of Denton Real Estate Department and the Consultant Engineer have begun the process of preparing documents for right-of-way acquisitions.
-
Completing plan revisions
Share Completing plan revisions on Facebook Share Completing plan revisions on Twitter Share Completing plan revisions on Linkedin Email Completing plan revisions linkThe Consultant Engineer is completing the recommended changes to the 60% Plan Set.
-
60 percent plan set is complete!
Share 60 percent plan set is complete! on Facebook Share 60 percent plan set is complete! on Twitter Share 60 percent plan set is complete! on Linkedin Email 60 percent plan set is complete! linkThe Consultant Engineer has submitted to the City the 60% Plan Set for its review. City Staff is checking the plan set for compliance with current standards.
-
30 Percent Plan Schematic is complete.
Share 30 Percent Plan Schematic is complete. on Facebook Share 30 Percent Plan Schematic is complete. on Twitter Share 30 Percent Plan Schematic is complete. on Linkedin Email 30 Percent Plan Schematic is complete. linkThe 30% Plan Schematic has been completed by the Consultant Engineer. City Staff has reviewed it and given direction to the Consultant to move forward towards the 60% Plans Set.
-
Design Survey is Complete.
Share Design Survey is Complete. on Facebook Share Design Survey is Complete. on Twitter Share Design Survey is Complete. on Linkedin Email Design Survey is Complete. linkThe Design Consultant, Halff, has completed their design survey. The completion of the survey will allow the Consultant to begin the design of the construction plan set.
-
Westgate Drive
Share Westgate Drive on Facebook Share Westgate Drive on Twitter Share Westgate Drive on Linkedin Email Westgate Drive linkHalff Associates, Inc. have started the design plans. The anticipated completion of the project plans and specifications is September 2023.
-
Choosing the Consultant Engineer for Design
Share Choosing the Consultant Engineer for Design on Facebook Share Choosing the Consultant Engineer for Design on Twitter Share Choosing the Consultant Engineer for Design on Linkedin Email Choosing the Consultant Engineer for Design linkThe Engineering/Capital Improvement Project Department have completed their review of the "request for qualifications" process from a list of prequalified engineering firms. The selected engineering firm has been approached by City staff to submit their proposal for the completion of the design.
-
Westgate Project Scope Update
Share Westgate Project Scope Update on Facebook Share Westgate Project Scope Update on Twitter Share Westgate Project Scope Update on Linkedin Email Westgate Project Scope Update link
During the Tuesday, August 10 Work Session, City staff presented City Council with an overview of the traffic study that was conducted, additional analysis, and requested feedback from the Council on the final scope of the project. Under the Westgate Improvement Project Resources section, click the August 12 Westgate Resident Scope Update to review the direction received, next steps, preliminary schematic for the project, and how to stay informed throughout the process.
-
Westgate Improvements Project Update
Share Westgate Improvements Project Update on Facebook Share Westgate Improvements Project Update on Twitter Share Westgate Improvements Project Update on Linkedin Email Westgate Improvements Project Update link
Based on feedback received at the June 8 City Council Work Session Presentation on the scope of the Westgate Reconstruction Project, staff entered into a professional services agreement with Kimley-Horn and Associates to conduct a traffic study focusing on the general geography of the north/south extents of Westgate Drive including Westgate Drive, Windsor Drive, N. Bonnie Brae Street, and Bronco Way and the east/west portion of Westgate. Once completed, the traffic study will include baseline volumes and volume projections based on future development in the area. Results of this study along with more specific information on options for the proposed scope of the Westgate Reconstruction Project is currently planned to be presented at the August 10 City Council Work Session.
Prior to the August 10 City Council Work Session, staff will provide a resident mailer regarding the status of the project (using the same geographical boundaries we used to invite residents to participate in the May 20 Virtual Community Meeting), continue to provide status updates on this project page, and email residents who registered for the May 20 Virtual Community Meeting regarding project status. Following final direction from the City Council on the scope of the Westgate Reconstruction Project, staff will host an additional community meeting to solicit feedback once the project is at 30% design.
Who's Listening
-
Phone (940) 349-7104 Email dante.hale@cityofdenton.com -
Phone (940) 349-7715 Email Jesus.Perez@cityofdenton.com -
Phone (940) 349-8909 Email scott.fettig@cityofdenton.com
Follow Project
Updates by Year
Project Information
Estimated Budget: Reviewing Bids
Sponsoring Department: Capital Projects/Engineering
Funding Source: 2014 Bond Program
Project Location: Westgate Drive
Contact Information:
Multi-phase projects may require different project managers. Below are the current project managers and the phase they manage.
Upcoming Virtual Community Meeting Link:
Stay Updated and Have Your Say
Click HERE to register to stay informed and ask the project manager a question about the Westgate Improvements Capital Improvement Project.
Important Link - June 12, 2025 Virtual Community Meeting
Click on the Image or copy link provided to register for the meeting.
Westgate Drive Virtual Community Link