Westgate Drive Improvement Project

Share Westgate Drive Improvement Project on Facebook Share Westgate Drive Improvement Project on Twitter Share Westgate Drive Improvement Project on Linkedin Email Westgate Drive Improvement Project link

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

The W. Westgate Drive Improvement Project will reconstruct the street to meet City of Denton residential standards. The project is divided into two phases, with Phase 1 set to begin in mid-June. This phased approach aims to complete a portion of the roadway before the 2025-2026 school year to help reduce traffic congestion during school drop-off and pickup.

Phase 1 includes constructing wet utilities, streetlights, pedestrian improvements, and roadway connectivity from Bronco Way to the existing W. Westgate Drive segment leading to the I-35 access road.

Phase 2 will improve the stretch from Windsor Drive/Westgate Drive to the I-35 access road, and the stretch along Westgate Drive/Windsor Drive, connecting to the Bronco Way intersection. Project scope will also include water, sanitary sewer upgrades, streetlights, pedestrian mobility enhancements, drainage improvements, and full-depth roadway reconstruction.

Project Timeline: 2021 - 2026

  • Phase 1 April Update

    Share Phase 1 April Update on Facebook Share Phase 1 April Update on Twitter Share Phase 1 April Update on Linkedin Email Phase 1 April Update link

    Phase 1 of this project is currently open for bidding, with the submission deadline set for April 9th. After receiving the bids, the City will conduct a thorough review, select a contractor, and award the contract. Once awarded, a Pre-Construction meeting will be held with the chosen contractor to finalize details and determine the construction start date.

  • Phase 2 - Right-of-way Acquisition

    Share Phase 2 - Right-of-way Acquisition on Facebook Share Phase 2 - Right-of-way Acquisition on Twitter Share Phase 2 - Right-of-way Acquisition on Linkedin Email Phase 2 - Right-of-way Acquisition link

    Right-of-way acquisition continues for Westgate Drive Phase 2 Project. The City must acquire permanent right-of-way, temporary construction easements, drainage and slope easements. Initial offer letters are being prepared by the Consultant Engineer.

  • New project limits - Westgate Drive Phase 2 Improvement Project

    Share New project limits - Westgate Drive Phase 2 Improvement Project on Facebook Share New project limits - Westgate Drive Phase 2 Improvement Project on Twitter Share New project limits - Westgate Drive Phase 2 Improvement Project on Linkedin Email New project limits - Westgate Drive Phase 2 Improvement Project link

    Westgate Drive Phase 2 Improvement Project limits are (1) from Barrow Drive to Windsor Drive.and (2) Windsor Drive from I35 access road to Westgate Drive. City Staff is currently working on right-of-way acquisition.

  • The East/West Westgate Drive will be first to be constructed.

    Share The East/West Westgate Drive will be first to be constructed. on Facebook Share The East/West Westgate Drive will be first to be constructed. on Twitter Share The East/West Westgate Drive will be first to be constructed. on Linkedin Email The East/West Westgate Drive will be first to be constructed. link

    City Staff has decided to construct the East/West Westgate Drive as the first phase of construction. The second phase will reconstruct North/South Westgate Drive and Windsor Drive.

  • Right-of-way Acquisition continues

    Share Right-of-way Acquisition continues on Facebook Share Right-of-way Acquisition continues on Twitter Share Right-of-way Acquisition continues on Linkedin Email Right-of-way Acquisition continues link

    The City of Denton continues forward with the preparation of the Surveyor's Exhibits needed for North/South Westgate Drive and Windsor Drive. The preparation of the Surveyor's Exhibits is the beginning of the process of appraising the required properties.

  • City has purchased 0.3 mitigation credit.

    Share City has purchased 0.3 mitigation credit. on Facebook Share City has purchased 0.3 mitigation credit. on Twitter Share City has purchased 0.3 mitigation credit. on Linkedin Email City has purchased 0.3 mitigation credit. link

    City has purchased 0.3 mitigation credit for the upcoming construction project within the recognized wetlands. The wetlands are located on the lowest elevations of the project where a culvert bridge must be constructed.

  • United States Army Corps of Engineers issues Permit Authorization Letter

    Share United States Army Corps of Engineers issues Permit Authorization Letter on Facebook Share United States Army Corps of Engineers issues Permit Authorization Letter on Twitter Share United States Army Corps of Engineers issues Permit Authorization Letter on Linkedin Email United States Army Corps of Engineers issues Permit Authorization Letter link

    The City of Denton has received the authorization letter to move forward with construction activities. The City will mitigate affected wetlands by the purchase of a third of a mitigation credit.

  • 100% Pre-Final Plan Set being reviewed by City.

    Share 100% Pre-Final Plan Set being reviewed by City. on Facebook Share 100% Pre-Final Plan Set being reviewed by City. on Twitter Share 100% Pre-Final Plan Set being reviewed by City. on Linkedin Email 100% Pre-Final Plan Set being reviewed by City. link

    After receiving the plans in late June, the City is reviewing the 100% Pre-Final Plans for any final changes.

  • Consultant Engineer plans to submit 100% Plan Set in late June 2024

    Share Consultant Engineer plans to submit 100% Plan Set in late June 2024 on Facebook Share Consultant Engineer plans to submit 100% Plan Set in late June 2024 on Twitter Share Consultant Engineer plans to submit 100% Plan Set in late June 2024 on Linkedin Email Consultant Engineer plans to submit 100% Plan Set in late June 2024 link

    The Consultant Engineer has compiled all of the City Staff comments and plans to submit the 100% Plan Set to the City in late June 2024.

  • Virtual Community Meeting

    Share Virtual Community Meeting on Facebook Share Virtual Community Meeting on Twitter Share Virtual Community Meeting on Linkedin Email Virtual Community Meeting link
    supporting image

    The City of Denton will hold a Community Meeting on Wednesday, June 12 at 6:00 p.m. regarding the roadway construction of the Westgate Drive Improvement Project. This includes improvements to the East/West Westgate Drive connection to Bronco Way, North/South Westgate Drive and Windsor Drive. The roadway improvements in your area are part of a major goal to permanently connect Bronco Way to the I-35 access road. The City will host the virtual community meeting providing residents, property and business owners the opportunity to: • Receive an overview of the Westgate Connector Paving and Drainage Improvement Project • Receive an update on project scope, timeline, and expected impacts during construction • Introduce the City’s Project Team • Field questions from community members. Click link to register for the meeting. https://cityofdenton.zoom.us/webinar/register/WN_NwrW3YpWTLuHHueTMqTQ6A#/registration