Southeast Denton Street Reconstruction

Share Southeast Denton Street Reconstruction on Facebook Share Southeast Denton Street Reconstruction on Twitter Share Southeast Denton Street Reconstruction on Linkedin Email Southeast Denton Street Reconstruction link

Improving Denton
Southeast Denton Street Reconstruction




The Southeast Denton Street Reconstruction (SED) project is a part of the City's focus on rebuilding existing streets that have reached the end of their useful life and is the first neighborhood that is being designed and constructed from the 2019 Street Reconstruction Bond. The SED project includes the reconstruction of 73 street segments located in Southeast Denton. These street segments were evaluated and given an Overall Condition Index (OCI) score of 40 or less. The City also intends to focus on one-time comprehensive neighborhood roadway infrastructure projects that complete both streets and utilities improvements. The

Improving Denton
Southeast Denton Street Reconstruction




The Southeast Denton Street Reconstruction (SED) project is a part of the City's focus on rebuilding existing streets that have reached the end of their useful life and is the first neighborhood that is being designed and constructed from the 2019 Street Reconstruction Bond. The SED project includes the reconstruction of 73 street segments located in Southeast Denton. These street segments were evaluated and given an Overall Condition Index (OCI) score of 40 or less. The City also intends to focus on one-time comprehensive neighborhood roadway infrastructure projects that complete both streets and utilities improvements. The intended results of the Southeast Denton Street Reconstruction Project will provide residents with a reconstructed street, improved utility services, among other improvements identified by residents dependent on funding and constructability.

Based on the number of street segments included in the SED project, the project is divided into two packages. Package A includes 22 roadway segments, and Package B includes 51 roadway segments. A map and street segments list of the two packages is included under the project resources section on this page.

Project Status

Package A - 22 Street Segments Included


Package B - 51 Street Segments Included



  • April Construction Update

    Share April Construction Update on Facebook Share April Construction Update on Twitter Share April Construction Update on Linkedin Email April Construction Update link

    Southeast Denton Package A - Utility crews have completed work on Johnson and Industrial St. Water installation will be taking place on Mill St through April. Subgrade stabilization is underway on Johnson, Industrial and Wye. Paving to begin on those segments in early April pending weather. Project on schedule to be complete Aug 2023.

    Southeast Denton Package B – Utility crews continue installation of domestic water and sanitary sewer lines on S Bradshaw St (E Prairie St to E Sycamore St), Smith St (Dallas Dr to Johnson St), Smith St (Dallas Dr to Hill St), Wainwright St (E Highland St to E Prairie St) and Maddox St. The earthwork crews have mobilized to E Prairie St (Lakey St to S Bradshaw St) to prepare area for asphalt paving in the coming weeks and the flatwork concrete crew has mobilized to E Highland St (S Locust St to Wainwright St), Avenue S, and E Prairie St (Lakey St to S Bradshaw St) to start work on sidewalks, curb and gutter, and pavement. Asphalt paving crews have completed asphalt pavement operations on E Highland St (S Locust St to ) and Bailey St (Wilson St).

    • Upcoming Streets (tentative start date 4/24/23): Wainwright St (E Prairie St to E Sycamore St) and E Sycamore St (Wainwright St to Industrial St)
  • March Construction Update

    Share March Construction Update on Facebook Share March Construction Update on Twitter Share March Construction Update on Linkedin Email March Construction Update link

    Southeast Denton Package A - Utility crews have completed work on Johnson and Industrial St. Water installation will be taking place on Mill st through April. Subgrade stabilization is underway on Johnson, Industrial and Wye. Paving to begin on those segments in early April pending weather. Project on schedule to be complete Aug 2023.


    Southeast Denton Package B – Utility crews continue installation of domestic water and sanitary sewer lines on Bailey St, S Bradshaw St (E Prairie St to Wilson St), E Highland St (S Locust St to Wainwright St), Smith St (Dallas Dr to Johnson St), Smith St (Dallas Dr to Hill St) and Avenue S. The earthwork crew has mobilized to E Highland St to prepare area for asphalt paving in the coming weeks and the flatwork concrete crew has mobilized to S Bradshaw St (E Prairie St to Wilson St) and Bailey St to start work on sidewalks, curb and gutter, and pavement.

    • Upcoming Streets (tentative start date 3/20/23): Wainwright St (E Prairie St to E Highland St)
  • February Construction Update

    Share February Construction Update on Facebook Share February Construction Update on Twitter Share February Construction Update on Linkedin Email February Construction Update link

    Southeast Denton Package A - Utility crews are working on Johnson st and Mill st with installation of the wastewater lines. Paving crews are working on Wye st and Allen st. Paving should begin 2/16 and be complete by 2/24 on Allen and Wye. Project is still on schedule to be complete summer of 2023.

    Southeast Denton Package B – Utility crews have begun asphalt milling and excavation for the installation of domestic water and sanitary sewer lines on Bailey St, S Bradshaw St (E Prairie St to Wilson St), E Highland St (S Locust St to Wainwright St), and Smith St – Phase 1 (Dallas Dr to Johnson St). Earthwork and flatwork concrete crews plan to follow in the coming weeks.

    • Upcoming Streets (tentative start date 3/6/23): Maddox St, Avenue S, and Smith St – Phase 2 (Dallas Dr to Hill St)


  • January Construction Update

    Share January Construction Update on Facebook Share January Construction Update on Twitter Share January Construction Update on Linkedin Email January Construction Update link

    Southeast Denton Package A - Utility crews are completing water/wastewater installation on Wye and Allen streets. Crews will be moving to Mill street and Industrial street for utility installation. Flat work and paving crews will begin on Wye and Allen once utilities crews mobilize out.


    Southeast Denton Package B - Contractor has mobilized in and will begin utility installation on Jan 30. First streets will be Smith St at Dallas Dr, E Highland at Locust, Bailey St at Wilson st, and Bradshaw St between Sycamore and Wilson. Paving crews will follow utility installation crews in each segment.

  • December Construction Update

    Share December Construction Update on Facebook Share December Construction Update on Twitter Share December Construction Update on Linkedin Email December Construction Update link

    Crews have begun utility work on Wye st and Allen st. Paving crews will be focusing on Robertson st and Cook st. Asphalt is tentatively set to be placed on those 2 roadways the week of 12/19 pending weather.

  • Community Meeting on December 8th

    Share Community Meeting on December 8th on Facebook Share Community Meeting on December 8th on Twitter Share Community Meeting on December 8th on Linkedin Email Community Meeting on December 8th link

    The City of Denton will hold a Community Meeting on Thursday, Dec. 8 at 6 p.m. regarding the street and utility improvements in the area as part of the Southeast Denton Neighborhood Capital Improvement Project (CIP).

    During this time we plan to:

    • Receive an overview of the Southeast Denton Neighborhood Package A & B CIP project.
    • Meet the Southeast Denton Package B Contractor, McCarthy Building Companies.
    • Receive an update on project scope, timeline, and expected impacts during construction; and
    • Answer any questions the Community Members may have
  • October Construction Update

    Share October Construction Update on Facebook Share October Construction Update on Twitter Share October Construction Update on Linkedin Email October Construction Update link

    Crews are currently paving Jackson, Hill Alley, Martin, and Morse st (Lakey-DCTA Tracks). Utility crews are working on Robertson, followed by Cook st and Wye st. Project is on track for completion in summer of 2023.

  • September Construction Update

    Share September Construction Update on Facebook Share September Construction Update on Twitter Share September Construction Update on Linkedin Email September Construction Update link

    Crews have completed the utility installation on Morse Street, Jackson Street, Hill Alley Street, and Martin Street. Testing procedures will begin the week of September 12th followed by roadway demo and stabilization. Paving is anticipated to start the first week of October, pending weather. Utility crews have moved to Robertson Street to be followed by Cook Street. Southeast Denton Package A is still on schedule to be complete by summer of 2023.

  • Construction Starting

    Share Construction Starting on Facebook Share Construction Starting on Twitter Share Construction Starting on Linkedin Email Construction Starting link

    Crews will be moving in to begin construction on SED-A beginning the week of June 6th.

  • Virtual Community Meeting Replay - March 9, 2021

    Share Virtual Community Meeting Replay - March 9, 2021 on Facebook Share Virtual Community Meeting Replay - March 9, 2021 on Twitter Share Virtual Community Meeting Replay - March 9, 2021 on Linkedin Email Virtual Community Meeting Replay - March 9, 2021 link
    supporting image

    On Thursday, March 4 at 6 p.m., a virtual community meeting was held. Click here to watch the meeting.

Page last updated: 01 Apr 2024, 05:16 AM