Southeast Denton Street Reconstruction

Share Southeast Denton Street Reconstruction on Facebook Share Southeast Denton Street Reconstruction on Twitter Share Southeast Denton Street Reconstruction on Linkedin Email Southeast Denton Street Reconstruction link

Improving Denton
Southeast Denton Street Reconstruction




The Southeast Denton Street Reconstruction (SED) project is a part of the City's focus on rebuilding existing streets that have reached the end of their useful life and is the first neighborhood that is being designed and constructed from the 2019 Street Reconstruction Bond. The SED project includes the reconstruction of 73 street segments located in Southeast Denton. These street segments were evaluated and given an Overall Condition Index (OCI) score of 40 or less. The City also intends to focus on one-time comprehensive neighborhood roadway infrastructure projects that complete both streets and utilities improvements. The

Improving Denton
Southeast Denton Street Reconstruction




The Southeast Denton Street Reconstruction (SED) project is a part of the City's focus on rebuilding existing streets that have reached the end of their useful life and is the first neighborhood that is being designed and constructed from the 2019 Street Reconstruction Bond. The SED project includes the reconstruction of 73 street segments located in Southeast Denton. These street segments were evaluated and given an Overall Condition Index (OCI) score of 40 or less. The City also intends to focus on one-time comprehensive neighborhood roadway infrastructure projects that complete both streets and utilities improvements. The intended results of the Southeast Denton Street Reconstruction Project will provide residents with a reconstructed street, improved utility services, among other improvements identified by residents dependent on funding and constructability.

Based on the number of street segments included in the SED project, the project is divided into two packages. Package A includes 22 roadway segments, and Package B includes 51 roadway segments. A map and street segments list of the two packages is included under the project resources section on this page.

Project Status

Package A - 22 Street Segments Included


Package B - 51 Street Segments Included



  • April Construction Update

    Share April Construction Update on Facebook Share April Construction Update on Twitter Share April Construction Update on Linkedin Email April Construction Update link
    supporting image

    Southeast Denton Package B - Work is progressing steadily on Southeast Denton Package B as there are three main operations currently ongoing throughout the SED-B construction limits.

    Utility crews continue the installation of domestic water and sanitary sewer lines from W Highland St (S Elm St to Carroll Blvd), Pierce St (Stroud St to W Prairie St), Austin St, W Mulberry St (Austin to Industrial), W Mulberry St (Industrial St to Bell St), and W Prairie St ( Bell to DCTA Rail).

    Earthwork crews are preparing the roadways for asphalt paving along Maple St (Carroll Blvd to S Elm St), Myrtle St (Eagle Dr to Maple), Myrtle St (Maple to W Highland), E Mulberry St (Crawford St to Wood St), W Mulberry (Austin to Industrial St).

    Concrete crews continue flatwork for new sidewalks, curb and gutter, and pavement along Maple St (Carroll Blvd to S Elm St), Myrtle St (Maple to Eagle Dr).

  • February Construction Update

    Share February Construction Update on Facebook Share February Construction Update on Twitter Share February Construction Update on Linkedin Email February Construction Update link
    supporting image

    February 2024 SED-B Discuss Denton Update Below:

    Southeast Denton Package B - Work is progressing steadily on Southeast Denton Package B as there are three main operations currently ongoing throughout the SED-B construction limits.

    Utility crews continue the installation of domestic water and sanitary sewer lines from Myrtle St (Fort Worth Dr to Maple St), Maple St (Carroll Blvd to S Elm St), W Highland St (S Elm St to Carroll Blvd), E Collins St, Pierce St ( Stroud St to W Prairie St) and Crawford St (E Mulberry St to E Sycamore St).

    Earthwork crews are preparing the roadways for asphalt paving along E Sycamore (Exposition St to Crawford St), E Sycamore St (Crawford st to Wood St), Myrtle St (Fort Worth Dr to Eagle Dr), and E Mulberry St (Crawford St to Wood St).

    Concrete crews continue flatwork for new sidewalks, curb and gutter, and pavement along Crawford St ( E Mulberry St to E Sycamore St), E Sycamore St (Exposition St to Crawford St), and Myrtle St (Fort Worth Dr to Eagle Dr).

  • January Construction Update

    Share January Construction Update on Facebook Share January Construction Update on Twitter Share January Construction Update on Linkedin Email January Construction Update link
    supporting image

    Southeast Denton Package B - Work is progressing steadily on Southeast Denton Package B as there are three main operations currently ongoing throughout the SED-B construction limits.

    Utility crews continue the installation of domestic water and sanitary sewer lines from Myrtle St (Fort Worth Dr to Maple St), Maple St (Carroll Blvd to S Elm St), W Highland St (S Elm St to Carroll Blvd), E Collins St, Pierce St ( Stroud St to W Prairie St) And Crawford St (E Mulberry St to E Sycamore St).

    Earthwork crews are preparing the roadways for asphalt paving along E Sycamore (Exposition St to Crawford St), Myrtle St (Fort Worth Dr to Eagle Dr) and Industrial St (S Bell Ave to W Sycamore).

    Concrete crews continue flatwork for new sidewalks, curb and gutter, and pavement along Crawford St ( E Mulberry St to E Sycamore St), E Sycamore St (Exposition St to Crawford St), Industrial St (W Sycamore to Mulberry St) and Myrtle St (Fort Worth Dr to Eagle Dr).

  • November Construction Update

    Share November Construction Update on Facebook Share November Construction Update on Twitter Share November Construction Update on Linkedin Email November Construction Update link
    supporting image

    Southeast Denton Package A - Project has reached final completion and closeout underway.


    Southeast Denton Package B - Work is progressing steadily in Southeast Denton Package B as utility crews install domestic water and sanitary sewer lines from Myrtle St (Fort Worth Dr to Maple St), Maple St (Carroll Blvd to S Elm St) ,E Sycamore St (Bradshaw St to Crawford St) And Crawford St ( E Mulberry St to E Sycamore St) . Earthwork crews are preparing the roadways along Wainwright St (E Prairie St to E Sycamore), W Sycamore (S Locust St to S Bell Ave) and Industrial St (S Bell Ave to E Mulberry St) for asphalt paving. Concrete crews continue flatwork along Prairie (Lakey St to S Bradshaw St ), Wainwright St (E Prairie St to E Sycamore) and Industrial St (S Bell Ave to E Mulberry St) for new sidewalks, curb and gutter, and pavement.

  • October Construction Update

    Share October Construction Update on Facebook Share October Construction Update on Twitter Share October Construction Update on Linkedin Email October Construction Update link
    supporting image

    Southeast Denton Package A - Project has reached final completion and closeout underway.


    Southeast Denton Package B - Work is progressing steadily on Southeast Denton Package B as utility crews install domestic water and sanitary sewer lines from Industrial St (S Bell Ave to E Mulberry St) Myrtle St (Fort Worth Dr to Maple St), Maple St (Carroll Blvd to S Elm St) ,E Sycamore St (Bradshaw St to Crawford St) And Crawford St ( E Mulberry St to E Sycamore St). Earthwork crews are preparing the roadways along Wainwright St (E Prairie St to E Sycamore), E Prairie St (Lakey St to S Bradshaw St) and Industrial St (S Bell Ave to E Mulberry St) for asphalt paving. Concrete crews continue flatwork along Prairie St (Lakey St to S Bradshaw St ), Wainwright St (E Prairie St to E Sycamore), and Industrial St (S Bell Ave to E Mulberry St) for new sidewalks, curb and gutter, and pavement.

  • September Construction Update

    Share September Construction Update on Facebook Share September Construction Update on Twitter Share September Construction Update on Linkedin Email September Construction Update link
    supporting image

    Southeast Denton Package A - Sidewalk installs and final paving complete on Mill St. Sod being placed or parkway restoration. Project completion expected first part of October.


    Southeast Denton Package B - Work is progressing steadily in Southeast Denton Package B as utility crews install domestic water and sanitary sewer lines from S Bradshaw St (E Prairie St to E Sycamore St), Industrial St (S Bell Ave to E Mulberry St) Myrtle St (Fort Worth Dr to Maple St), Maple St (Carroll Blvd to S Elm St) and E Sycamore St (Bradshaw St to Crawford St). Earthwork crews are preparing the roadways along Smith St (Dallas Dr to Hills St), Wainwright St (E Prairie St to E Sycamore), S Bradshaw (E prairie St to E Sycamore) and E Prairie St (Lakey St to S Bradshaw St) for asphalt paving. Concrete crews continue flatwork along Smith St (Dallas Dr to Hills St), Prairie (Lakey St to Avenue S), Wainwright St (E Prairie St to E Sycamore) for new sidewalks, curb and gutter, and pavement.

  • August Construction Update

    Share August Construction Update on Facebook Share August Construction Update on Twitter Share August Construction Update on Linkedin Email August Construction Update link

    Southeast Denton Package A - Completion of sidewalk install and final paving of Mill st should be complete late August pending weather.

    Southeast Denton Package B - Work is progressing steadily in Southeast Denton Package B as utility crews continue to install domestic water and sanitary sewer lines from S Bradshaw St (E Prairie St to E Sycamore St), Industrial St (S Bell Ave to E Mulberry St) Myrtle St (Fort Worth Dr to Maple St), Maple St (Carroll Blvd to S Elm St) and E Sycamore St (Bradshaw St to Crawford St). The earthwork crew continues preparing the roadways along Smith St (Dallas Dr to Johnson St and Dallas Dr to Hills St), Wainwright St (E Prairie St to E Sycamore), S Bradshaw (E prairie St to Wilson St) and E Prairie St (Lakey St to S Bradshaw St) for asphalt paving. Concrete crews continue the flatwork along Smith St (Dallas Dr to Johnson St and Dallas Dr to Hills St), Prairie (Lakey St to Avenue S), Wainwright St (E Prairie St to E Sycamore) for new sidewalks, curb and gutter, and pavement.


  • July Construction Update

    Share July Construction Update on Facebook Share July Construction Update on Twitter Share July Construction Update on Linkedin Email July Construction Update link

    Southeast Denton Package A - Paving and subgrade treatment have begun on the final section of Mill St. Crews will begin with curb and gutter and sidewalk work the week of 7/17. Final paving of Mill st should be complete mid-late August pending weather.

    Southeast Denton Package B - Work is progressing steadily in Southeast Denton Package B as utility crews continue to install domestic water and sanitary sewer lines from S Bradshaw St (E Prairie St to E Sycamore St),Industrial St (S Bell Ave to E Mulberry St) Smith St (Dallas Dr to Johnson St and Dallas Dr to Hill St), Wainwright St (E Prairie St to E Sycamore St), and E Sycamore St (Bradshaw St to Crawford St). The earthwork crew continues preparing the roadways along Smith St (Dallas Dr to Johnson St), Maddox St, Wainwright St (E Highland St to E Prairie St), and E Prairie St (Lakey St to S Bradshaw St) for asphalt paving. Concrete crews continue the flatwork along Smith St (Dallas Dr to Johnson St) for new sidewalks, curb and gutter, and pavement.


  • June Construction Update

    Share June Construction Update on Facebook Share June Construction Update on Twitter Share June Construction Update on Linkedin Email June Construction Update link
    supporting image

    Southeast Denton Package A - Utility crews will be completing water installation on Mill St in May. Paving is complete on Johnson, Industrial and Wye. Paving to begin on Mill St. first of June. Project on schedule to be complete Aug 2023.

    Southeast Denton Package B - Work is progressing steadily in Southeast Denton Package B as utility crews continue to install domestic water and sanitary sewer lines from S Bradshaw St (E Prairie St to E Sycamore St), Smith St (Dallas Dr to Johnson St and Dallas Dr to Hill St), Wainwright St (E Prairie St to E Sycamore St), and E Sycamore St (Bradshaw St to Crawford St). The earthwork crew continues preparing the roadways along Smith St (Dallas Dr to Johnson St), Avenue S, and E Prairie St (Lakey St to S Bradshaw St) for asphalt paving. Concrete crews continue the flatwork along Smith St (Dallas Dr to Johnson St) and Wainwright St (E Highland St to E Prairie St) for new sidewalks, curb and gutter, and pavement.

  • May Construction Update

    Share May Construction Update on Facebook Share May Construction Update on Twitter Share May Construction Update on Linkedin Email May Construction Update link

    Southeast Denton Package A - Utility crews will be completing water installation on Mill St in May. Paving is complete on Johnson, Industrial and Wye. Paving to begin on Mill St. first of June. Project on schedule to be complete Aug 2023.

    • Southeast Denton Package B – Utility crews continue installation of domestic water and sanitary sewer lines on S Bradshaw St (E Prairie St to E Sycamore St), Smith St (Dallas Dr to Johnson St), Smith St (Dallas Dr to Hill St), Wainwright St (E Prairie St to E Sycamore St) E Sycamore St (Bradshaw St to Crawford St) and E Sycamore St (Wainwright St to Industrial St). The earthwork crews have mobilized to Smith St (Dallas Dr to Johnson St) to prepare the area for asphalt paving in the coming weeks and the flatwork concrete crew has mobilized to E Prairie St (Lakey St to S Bradshaw St) and Wainwright St (E Highland St to E Prairie St) to start work on sidewalks, curb and gutter, and pavement.
Page last updated: 01 Apr 2024, 05:16 AM