Fire House #5 and #6

Share Fire House #5 and #6 on Facebook Share Fire House #5 and #6 on Twitter Share Fire House #5 and #6 on Linkedin Email Fire House #5 and #6 link
Rendering of Station #5 and #6

Two (2) new Fire Stations with approximately 12,500 to 14,500 square feet. One (1) fire station, including four (4) apparatus bays, and one (1) fire station, including three (3) apparatus bays with living spaces that will support (10) personnel, including two (2) officers.

Two (2) new Fire Stations with approximately 12,500 to 14,500 square feet. One (1) fire station, including four (4) apparatus bays, and one (1) fire station, including three (3) apparatus bays with living spaces that will support (10) personnel, including two (2) officers.

  • Construction Progress

    Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link

    Fire Station #5

    ACHIEVEMENTS:

    üSprung Structure Grading
    üTemp Station Submittals
    üDomestic Water Line
    üUG Power Line
    üSanitary Sewer Line
    üFire 5 Erosion Control/Watershed Inspection

    NEXT STEPS:

    qTemp Station Flex base
    qSprung Foundation
    qInstall Sprung Structure
    qInstall OH Doors
    qInstall Electric Underground Feed from Transformer
    qInstall Sanitary Temp (In-Process)
    qInstall Concrete Pads for Generator and Riser Room
    qTemp Station Interior MEP

    Fire Station #6

    ACHIEVEMENTS:

    ü100% Piers Complete
    üGrade Beams (Apparatus Bay) Complete
    üGrade Beams (Operations Side) Formed
    üSouth Storm Sewer 50%

    NEXT STEPS:

    qPour Grade Beams (Operations Side)
    qStart Storm Sewer Install
    qExcavate & Install Water Line
    qExcavate & Install Storm Line
    qExcavate & Install Gas Line
    qExcavate & Install Power Line
    qUnderground MEP (Bay and Ops)
    qPour Slab
  • Construction Progress

    Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link
    supporting image

    ACHIEVEMENTS:

    üTree Protection, Clearing and Grubbing
    üGrading
    üMoisture Conditioning for Pad
    üSecurity Fence Complete
    üPier Survey
    ü50% Piers Complete
    üSprung Structure Procured
    üUtility Layout for Temp

    NEXT STEPS:

    qProject Submittals Ongoing
    q50% Pad Left (House, Storm Shelter, Dumpster Pad and Generator Pad Piers)
    qStart Sanitary Sewer Install
    qStart Storm Sewer Install
    qGrade Beam Forms and Excavation Perimeter
    qGrade Beam Forms and Excavation Interior
    qGrade Beam Forms and Excavation House
    qInstall RCP and Boxes – Area South
    qTemp Station Submittals
    qTemp Station Flex base
    qTemp Station Trailer MEP
    qInstall Domestic Water Line (In-Process)
    qSprung Foundation
    qInstall Sprung Structure
    qInstall OH Doors
    qInstall Electric Underground Feed from Transformer
    qInstall Sanitary Temp (In-Process)
    qInstall Concrete Pads for Generator and Riser Room
  • Construction Progress

    Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link
    supporting image

    ACHIEVEMENTS:

    üContract Negotiations
    üCity Council Approval 22-JUL
    üPermitting Finalized
    üSWPPP Permit Complete
    üTemporary Fire Station Trailer Delivered
    üObtain Construction Permit
    üKick-Off Meeting 01-AUG
    üIssue Notice to Proceed 01-AUG
    üCORE Construction Mobilization 04-AUG
    üTree Protection, Clearing and Grubbing

    NEXT STEPS:

    qTemp Station Submittals 11-AUG
    qProcure Sprung Structure
    qSprung Structure August –November
    qTemp Station Flex base
    qTemp Station Trailer MEP
    qSprung Foundation
    qInstall Sprung Structure
    qInstall OH Doors
    qMoisture Conditioning Building Pad 08-SEP
    qStart Sanitary Sewer Install 22-SEP
    qStart Storm Sewer Install 22-SEP
    qPier Survey Followed by Drilling 23-SEP
  • Design/Procurement Phase

    Share Design/Procurement Phase on Facebook Share Design/Procurement Phase on Twitter Share Design/Procurement Phase on Linkedin Email Design/Procurement Phase link
    supporting image

    ACHIEVEMENTS:

    üContract Negotiations
    üCity Council Approval 22-JUL
    üPermitting Finalized
    üSWPPP Permit Complete
    üTemporary Fire Station Trailer Delivered

    NEXT STEPS:

    qObtain Construction Permit
    qKick-Off Meeting 01-AUG
    qIssue Notice to Proceed 01-AUG
    qCORE Construction Mobilization 04-AUG
    qTemp Station Submittals 11-AUG
    qTemp Station Construction 12-AUG to 30-OCT
    qSprung Strructure August -November
    qGrading 04-AUG
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üGMP Creation
    üGMP Converted to Stipulated Lump Sum Contract
    üILA Pflugerville/Denton for Temp Trailer Executed
    üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent

    NEXT STEPS:

    qStipulated Sum GMP Negotiations
    qFinalized GMP to City 3-JUL
    qGMP to CC 15-JUL or 22-JUL
    qSWPPP Permitting to Compete
    qFinalize all Permitting
    qTemporary Fire Station 5 Trailer Delivery 3-JUL
    qNTP 16 or 23 JUL for Temp Fire 5 and Fire 6
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent
    üPrebid Completed
    üZoning Committee Approval
    üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent
    üPrebid Completed
    üGMP Creation
    üILA Pflugerville/Denton for Temp Trailer Executed
    üPermitting Finalized




    NEXT STEPS:

    qSubmit Landscaping and Civil for Permitting
    qStipulated Sum GMP Negotiations
    qFinalized GMP to City 13-JUN
    qGMP to CC 15-JUL
    qNTP 16-JUL
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent
    üPrebid Completed
    üGMP Creation
    üILA Pflugerville/Denton for Temp Trailer Executed

    NEXT STEPS:

    qFinalize Permitting
    qGMP to the CoD 29-APR Negotiations
    qGMP to Purchasing for CC Meeting Agenda 5-MAY
    qGMP to CC 03-Jun
    qGMP NTP 20-Jun (Temp Facility)
    qProcurement – Switchgear, Panels, Generator and Structural Steel
    qFire Station 5 Construction Start 07-NOV
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üReceived Bids 25-MAR
    üPre-Bid Meeting 12-MAR
    üAdvertise for Bids 5-MAR
    üModular IT Equipment Plan
    üCORE Bid Package Submitted to City Purchasing for Review
    üTerracon Engineering Services Scope and Contract Approved by City Council
    ü100% Construction Documents Submitted for Permitting
    üFF&E Budget Development (DFS5&Modular)
    üArt Package Submitted for Bids

    NEXT STEPS:

    qSprung App Bay and Trailer Purchase and Transportation
    qFinalize Utilities for Temp Station
    qPlan Permit Review (In Progress)
    qArt Bids Due 31-MAR
    qGMP to City for Review 15-APR
    qGMP to Council 5-May
    qConstruction (June)
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üCORE Bid Package Submitted to City Purchasing for Review
    üTerracon Engineering Services Scope and Contract Approved by City Council
    ü100% Construction Documents Submitted for Permitting
    üFF&E Budget Development (DFS6)
    üArt Package Submitted for Bids
    üStorm Shelter Consultant
    üFiber/DME Resolution
    üArt Package Submitted for Bids
    üStorm Shelter Consultant

    NEXT STEPS:

    qAdvertise for Bids 5-MAR
    qPrebid Meeting 12-MAR
    qFinalize Utilities for Temp Station
    qPlan Permit Review (In Progress)
    qGMP Creation (April)
    qGMP to Council (April-May)
    qConstruction (June)
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link
    supporting image

    ACHIEVEMENTS:

    üFF&E/IT Budget Development
    üArt Package Submitted to Parks
    üStorm Shelter Consultant
    ü95% Construction Documents
    üDFS6 SOV Decision

    NEXT STEPS:

    qTerracon Engineering Services Scope and Contract to PUB FEB
    qBudget Review CORE/Martinez/City of Denton
    qPlan Permit Review (In Progress)
    qPurchasing Review of Bid Package
    qLegal Advertisement (March)
    qGMP Creation (April)
    qGMP to Council (April-May)
    qConstruction (June)