  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent
    üPrebid Completed
    üGMP Creation
    üILA Pflugerville/Denton for Temp Trailer Executed

    NEXT STEPS:

    qFinalize Permitting
    qGMP to the CoD 29-APR Negotiations
    qGMP to Purchasing for CC Meeting Agenda 5-MAY
    qGMP to CC 03-Jun
    qGMP NTP 20-Jun (Temp Facility)
    qProcurement – Switchgear, Panels, Generator and Structural Steel
    qFire Station 5 Construction Start 07-NOV
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üReceived Bids 25-MAR
    üPre-Bid Meeting 12-MAR
    üAdvertise for Bids 5-MAR
    üModular IT Equipment Plan
    üCORE Bid Package Submitted to City Purchasing for Review
    üTerracon Engineering Services Scope and Contract Approved by City Council
    ü100% Construction Documents Submitted for Permitting
    üFF&E Budget Development (DFS5&Modular)
    üArt Package Submitted for Bids

    NEXT STEPS:

    qSprung App Bay and Trailer Purchase and Transportation
    qFinalize Utilities for Temp Station
    qPlan Permit Review (In Progress)
    qArt Bids Due 31-MAR
    qGMP to City for Review 15-APR
    qGMP to Council 5-May
    qConstruction (June)
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link

    ACHIEVEMENTS:

    üCORE Bid Package Submitted to City Purchasing for Review
    üTerracon Engineering Services Scope and Contract Approved by City Council
    ü100% Construction Documents Submitted for Permitting
    üFF&E Budget Development (DFS6)
    üArt Package Submitted for Bids
    üStorm Shelter Consultant
    üFiber/DME Resolution
    üArt Package Submitted for Bids
    üStorm Shelter Consultant

    NEXT STEPS:

    qAdvertise for Bids 5-MAR
    qPrebid Meeting 12-MAR
    qFinalize Utilities for Temp Station
    qPlan Permit Review (In Progress)
    qGMP Creation (April)
    qGMP to Council (April-May)
    qConstruction (June)
  • Desing/Procurement Phase

    Share Desing/Procurement Phase on Facebook Share Desing/Procurement Phase on Twitter Share Desing/Procurement Phase on Linkedin Email Desing/Procurement Phase link
    supporting image

    ACHIEVEMENTS:

    üFF&E/IT Budget Development
    üArt Package Submitted to Parks
    üStorm Shelter Consultant
    ü95% Construction Documents
    üDFS6 SOV Decision

    NEXT STEPS:

    qTerracon Engineering Services Scope and Contract to PUB FEB
    qBudget Review CORE/Martinez/City of Denton
    qPlan Permit Review (In Progress)
    qPurchasing Review of Bid Package
    qLegal Advertisement (March)
    qGMP Creation (April)
    qGMP to Council (April-May)
    qConstruction (June)
  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link

    ACHIEVEMENTS:

    Construction Documents (City Review)

    FF&E Budget Development (DFS5&EMB)
    Art Package for Art Committee
    Budget Review with CMAR



  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link
    supporting image

    ACHIEVEMENTS:

    ü50% Construction Documents (City Review)
    ü100% Extreme Modular Building Design Document
    üEarly Estimate Received from CMAR and Reviewed by City Stakeholders
    üIT Page Turns and Budget Development (DFS5&EMB)
    üFF&E Budget Development (DFS5&EMB)
    üArt Package Returned from Art Committee with Comments
    üStorm Shelter Consultant
    ü50% Budget Review with CMAR
    ü90% Construction Documents
    üGMP-01 2nd Round of Bids Closed


    NEXT STEPS:

    qGMP-01 to City for Review 02-DEC
    qEMB Foundation and App Bay Design Changes
    qTerracon Engineering Services Scope and Contract to CC 17-DEC
    qExtreme Modular Building Construction Documents to be Approved by State
    qGMP-01 to CC for Approval Possibly 17-DEC
    q100% CD Issued for Permitting and Bidding 17-Dec
    qExtreme Modular Building Construction
    qArt Package back to CoD Art Committee
    qNext Estimates (Early December) to Include Changes in Masonry, Roof, and OTS Doors
  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link

    ACHIEVEMENTS:

    ü50% Construction Documents (City Review)
    ü100% Extreme Modular Building Design Document
    üEarly Estimate Received from CMAR
    üIT Page Turns and Budget Development (DFS5&EMB)
    üFF&E Budget Development (DFS5&EMB)
    üArt Package Returned from Art Committee
    üStorm Shelter Consultant

    NEXT STEPS:

    qTerracon Engineering Services Scope and Contract to CC 19-NOV
    q50% Budget Review with CMAR (Meeting 07-NOV)
    q90% Construction Documents 12-Nov
    qExtreme Modular Building Construction Documents to be Approved by State
    q100% CD Issued for Permitting and Bidding 17-Dec
    qExtreme Modular Building Construction
    qGMP-01 to Re-Bid 06-NOV
    qArt Package back to CoD Art Committee
  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link

    ACHIEVEMENTS:

    • 100% Design Documents

    • 100% Extreme Modular Building Design Document

    • Early Estimate Received from CMAR and Reviewed by City Stakeholders

    • 50% CD’s 01-Oct

    • Preconstruction efforts/Site Investigation

    • FF&E/IT Budgeting Meetings

    • EMB Foundation Design

    • CoD Capital Projects Partnering Session for FS5&6 13-Sep


    NEXT STEPS:

    • Terracon Engineering Services Scope and Contract to CC 22-Oct

    • 50% Construction Documents (City Review)

    • 50% Estimates

    • 90% Construction Documents 12-Nov

    • Extreme Modular Building Construction Documents to be Approved by State

    • 100% CD Issued for Permitting and Bidding 17-Dec

    • Extreme Modular Building Construction

    • GMP-01 to CC 22-NOV (EMB/Early Site Work/Gensets)

    • Project Kickoff 31-Oct

    • Early Permitting

    • Acquire Storm Shelter Consulting Service

    • Art Package to CoD Art Committee

  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link


    ACHIEVEMENTS:

    üCMAR Preconstruction Negotiation
    ü100% Schematic Design complete
    ü100% Design Documents 20-Aug
    üStorm Shelter Proposal Recieved

    NEXT STEPS:

    qTerracon Engineering Scope and Contract
    q100% DD Review by City
    qInitial Estimates (Mid-Sept)
    q50% Construction Documents 01-Oct
    q100% CD’s Complete 29-Nov
    q100% CD’s City Review (6 weeks)

  • Design Phase

    Share Design Phase on Facebook Share Design Phase on Twitter Share Design Phase on Linkedin Email Design Phase link
    supporting image


    ACHIEVEMENTS:

    üMaterial Testing
    üFinal Scoring of CMAR and Selection
    üCMAR Preconstruction Negotiation
    ü100% Schematic Design complete

    NEXT STEPS:

    qPrecon CMAR GMP - City Council Date Pending
    qTerracon Engineering Services Scope and Contract
    q100% Extreme Modular Building Construction Doc.
    q100% Design Documents
    q50% Construction Documents
    q100% CD Issued for Permitting and Bidding
    qExtreme Modular Building Delivery Dec-Jan
    qGMP to City Council Dec-Jan